Contents
1.1
Purpose of the Report
1.2
Structure of the Report
2.1
Background
2.2
General Site Description
2.3
Major Activities Undertaken
2.4
Project Organisation and Management Structure
2.5
Status of Environmental Approval Documents
3
Environmental Monitoring and Audit Requirements
3.1
Environmental Monitoring
3.1.1
Air Quality
3.1.2
Odour
3.2
Site Audit
3.2.1
Water Quality
3.2.2
Landscape and Visual
4.1
Air Quality
4.1.1
Operation Phase Monitoring
4.2
Odour
4.2.1
Operation Phase Monitoring
4.3
Water Quality
4.3.1
Operation Phase Monitoring
4.4
Waste Management
4.4.1
Operation Phase Monitoring
5.1
Environmental Site Audit
5.1.1
Operation Phase
5.2
Landscape and Visual Audit
6
Environmental Non-conformance and Deficiencies
6.1
Summary of Environmental Non-Compliance and Deficiencies
6.2
Summary of Environmental Complaint
6.3
Summary of Environmental Summon and Successful Prosecution
7.1
Key Issues for the Coming Month
LIST OF TABLES
Table 2.1 Summary of Activities Undertaken in the Reporting Period
Table 2.2 Summary of Environmental Licensing, Notification and
Permit Status
Table 3.1 Sampling and Laboratory Analysis Methodology
Table 3.2 Emission Limit for
CAPCS Stack
Table 3.3 Emission Limit for
CHP Stack
Table 3.4 Emission Limit for
ASP Stack
Table 3.5 Emission Limit for
Standby Flaring Gas Unit
Table 3.6 Odour Intensity
Level
Table 3.7 Action and Limit
Levels for Odour Nuisance
Table 3.8 Event and Action
Plan for Odour Monitoring
Table 3.9 Discharge
Limits for Effluent from the Outlet Chamber of the Effluent Storage Tank
Table 3.10 Discharge
Limits for Effluent from the Petrol Interceptors
Table 4.1 Hourly
Average of Parameters Recorded for CAPCS
Table 4.2 Hourly
Average of Parameters Recorded for CHP 1
Table 4.3 Hourly
Average of Parameters Recorded for CHP 2
Table 4.4 Hourly
Average of Parameters Recorded for CHP 3
Table 4.5 Hourly Average of Parameters Recorded for ASP
Table 4.6 Hourly Average of Parameters Recorded for the Standby
Flaring Gas Unit
Table 4.7 Results
of the Discharge Sample from the Outlet Chamber of the Effluent Storage Tank
Table 4.8 Results
of the Discharge Sample from the Petrol Interceptor 1
Table 4.9 Results
of the Discharge Sample from the Petrol Interceptor 2
Table 4.10 Quantities of Waste Generated from the Operation of the
Project
Table 8.1 Exceedances
for Stack Emissions
LIST OF ANNEXES
Annex E Environmental
complaint, Environmental Summons and Prosecution Log |
The construction works of No.
EP/SP/61/10 Organic Resources Recovery Centre Phase 1 (the
Project) commenced on 21 May 2015. This
is the 96th monthly Environmental Monitoring and Audit (EM&A)
report presenting the EM&A works carried out during the period from 1 to 31
May 2023 in accordance with the EM&A Manual. Substantial completion
of the construction works was confirmed on 3 December 2018. In the
meantime, the operation phase EM&A programme had commenced in March 2019.
Substantial Completion in respect of substantial part of the Works was
confirmed on 24 February 2020. The construction phase EM&A programme
was completed in the end of February 2020.
Summary of Works undertaken during
the Reporting Month
Works undertaken in the reporting
month included:
·
Operation of the Project, including organic
waste reception, and operation of the pre-treatment facilities, anaerobic
digesters, composting facilities, air pollution control systems, on-line
emission monitoring system for the Centralised Air Pollution Control Unit
(CAPCS), Co-generation Units (CHP)s and Ammonia Stripping Plant (ASP), and the
wastewater treatment plant;
·
CEMS maintenance;
·
QAL 2 testing with 3rd Party Lab was conducted
for MCS 1 and MCS 2;
·
Replacement of membrane diffusers for all of
the SBR Tanks of the Waste Water Treatment Plant was completed; and
·
ASP plate heat exchanger cleaning was completed
(commenced April 2023).
Environmental Monitoring and Audit
Progress
Air Quality Monitoring
Non-compliance of emission limits of
Dust, VOCs, NOx and SO2 from CHP 1; Dust, NOx
and SO2 from CHP 2; NOx and SO2 from CHP 3;
and CO, NOx, SO2, NH3 and HF from ASP were
recorded during the reporting period.
Water
Quality
Non-compliance of discharge limits
of Total Nitrogen from the outlet chamber of the effluent storage tank was
recorded during the reporting period.
Waste
Management
Waste generated from the operation
of the Project includes waste generated from pre-treatment process and general
refuse.
No chemical waste was collected by
licenced waste collector from the operation of the Project.
662.27 tonnes of waste generated
from pre-treatment process from the operation of the Project was disposed of at
landfill. Among the recyclable waste generated from pre-treatment process
from the operation of the Project, 0.00 tonne of metals, 0.00 tonnes of papers/
cardboard packing and 0.00 tonne of plastics were sent to recyclers for
recycling during the reporting period.
Around 2.88 tonnes of general refuse
from the operation of the Project was disposed of at landfill. Among the
recycled general refuse from the operation of the Project, 0.00 tonnes of
metals, 0.00 tonnes of papers/ cardboard packing and 0.13 tonnes of plastics
were sent to recyclers for recycling during the reporting period.
Findings of Environmental Site Audit
A summary of the monitoring activities undertaken in this reporting
period is listed below:
·
Joint Environmental Site Inspections |
1 time |
1 monthly joint environmental site inspection was carried out by the
representatives of the Contractor and the MT. The IEC was also present at
the joint inspections on 23 May 2023. The environmental control/
mitigation measures (related to air quality, water quality, waste (including
land contamination prevention), hazard-to-life and landscape and visual)
recommended in the approved EIA Report and the EM&A Manual were properly
implemented by the Contractor during the reporting month.
Environmental Exceedance/Non-conformance/Compliant/Summons and
Prosecution
Exceedances for the air emission limits for CHPs and ASP stacks and
discharge limits for the effluent storage tank were recorded during the reporting period.
No complaint/ summon/prosecution was received in this reporting period.
Future Key Issues
Activities to be undertaken in the
next reporting month include:
·
Operation of the Project;
·
Tuning of CHPs by the Supplier; and
·
Repairing of the Chemical Scrubber 3.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR Bioenergy Joint
Venture (the Contractor) as the Environmental Team (ET) to undertake the
construction Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I, which
the project name has been updated to Organic Resources Recovery Centre
(Phase I) (the Project) since November 2017.
ERM was also appointed
by the Contractor to undertake the operation EM&A programme starting 1
March 2019.
This is the 96th EM&A report which summarises the
monitoring results and audit findings for the EM&A programme during the
reporting period from 1 to 31 May 2023.
The structure of the report is as follows:
Section
1: Introduction
It details the scope and structure of the
report.
Section 2: Project Information
It summarises the background and
scope of the Project, site description, project organisation and status of the
Environmental Permits (EP)/licences.
Section 3: Environmental
Monitoring and Audit Requirements
It summarises the environmental monitoring
requirements including monitoring parameters, programmes, methodologies,
frequency, locations, Action and Limit Levels, Event/Action Plans, as well as
environmental audit requirements as recommended in the EM&A Manual and
approved EIA report.
Section 4: Monitoring
Results
It summarises monitoring results of the
reporting period.
Section 5: Site Audit
It summarises the audit findings of the
environmental as well as landscape and visual site audits undertaken within the
reporting period.
Section 6: Environmental
Non-conformance
It summarises any exceedance of environmental
performance standard, environmental complaints and summons received within the
reporting period.
Section 7: Further Key
Issues
It summarises the impact forecast for the next
reporting month.
Section 8: Conclusions
The Organic Resources Recovery Centre (ORRC) Phase I development
(hereinafter referred to as “the Project”) is to design, construct and operate
a biological treatment facility with a capacity of about 200 tonnes per day and
convert source-separated organic waste from commercial and industrial sectors
(mostly food waste) into compost and biogas through proven biological treatment
technologies. The location of the Project site is shown in Annex A.
The environmental acceptability of the construction
and operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) Study completed in 2009. The
Director of Environmental Protection (DEP) approved this EIA Report under the Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register
No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report).
Subsequent Report on Re-assessment on Environmental Implications and Report on
Re-assessment on Hazard to Life Implications were completed in 2013,
respectively.
An Environmental Permit (EP) (No. EP-395/2010)
was issued by the DEP to the EPD (Project Team), the Permit Holder, on 21 June
2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No.
EP-395/2010/B), respectively. The Design Build and Operate Contract for
the ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre
(Phase 1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL
Engineering Limited and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR
Bioenergy Joint Venture (OSCAR or the Contractor). A Further EP (No.
FEP-01/395/2010/B) was issued by the DEP to the OSCAR on 16 February
2015. Variation to both EPs (Nos. EP-395/2010/B and FEP-01/395/2010/B)
were made in December 2015. The latest EPs, Nos. EP-395/2010/C and
FEP-01/395/2010/C, were issued by the DEP on 21 December 2015.
Under the requirements of Condition 5 of the EP (No.
FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme
as set out in the approved EM&A Manual (hereinafter referred to as EM&A
Manual) is required to be implemented during the construction and operation of
the Project. ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the
Environmental Team (ET) for the construction phase EM&A programme and the
Monitoring Team (MT) for the operation phase EM&A programme for the
implementation of the EM&A programme in accordance with the
requirements of the EP and the approved EM&A Manual.
The construction works commenced on
21 May 2015. The construction phase EM&A programme was completed in
the end of February 2020. The operation phase of the EM&A programme
commenced on 1 March 2019 ([1]).
The Project Site is located at Siu Ho Wan in North Lantau with an area
of about 2 hectares.
The layout of the Project Site is illustrated in Annex A. The facility
received an average of 134.05 tonnes and treated an average of 112.69 tonnes of
source separated organic waste per day during the reporting month.
A summary of the major activities undertaken in the reporting period is
shown in Table 2.1.
Table 2.1
Summary of Activities Undertaken in the Reporting Period
Activities Undertaken in the
Reporting Period |
·
Systems being operated – waste reception, pre-treatment, CAPCS
extraction, the digesters, the centrifuge, the composting tunnels, the
de-sulphurisation, the emergency flare, the CHPs, the ASP and the biological
waste water treatment plant (134.05 t/d SSOW received); ·
CEMS maintenance; ·
QAL 2 testing with 3rd Party Lab was conducted for MCS 1 and MCS 2; ·
Replacement of membrane diffusers for all of the SBR Tanks of the
Wastewater Treatment Plant was completed; and ·
ASP plate heat exchanger cleaning was completed (commenced April
2023). |
The project organisation chart and contact details are shown in Annex B.
A summary of the valid permits, licences, and/or notifications on
environmental protection for this Project is presented in Table 2.2.
Table 2.2
Summary of Environmental Licensing, Notification and Permit Status
Permit/
Licences/ Notification |
Reference |
Validity
Period |
Remarks |
Environmental
Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December 2015 |
Effluent
Discharge Licence |
WT00038391-2021 |
7 July 2021
– 30 June 2026 |
Approved on
7 July 2021 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-02 |
Throughout the implementation of the Project |
Approved on 10 November 2017 |
Waste
Disposal Billing Account |
Account
number: 702310 |
Throughout
the Contract |
- |
The air quality (including odour) monitoring to be carried out during
the commissioning and operation phase of the Project are described below.
Although water quality monitoring is not required for the operation phase under
the EM&A programme, there are water quality monitoring requirement under
the Water Discharge Licence of the plant under the Water Pollution Control
Ordinance (WPCO). As part of this EM&A programme, the monitoring
results will be reviewed to check the compliance with the WPCO requirements.
According to the EM&A Manual and EP requirements, stack monitoring
are required during the commissioning and operation phase of the Project.
On-line monitoring (using continuous environmental monitoring system
(CEMS) shall be carried out for the centralised air pollution unit (CAPCS),
cogeneration units (CHP) and the ammonia stripping plant (ASP) during the
commissioning and operation phase. The last maintenance was carried out
from 1 to 4 May 2023.
The monitoring data is transmitted instantaneously to EPD (Regional
Office) by telemetry system.
When the on-line monitoring for certain parameter cannot be undertaken,
monitoring will be carried out using the following methodology approved by the
EPD.
Table 3.1
Sampling and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be
Monitored |
Gaseous and vaporous
organic substances (including methane) |
USEPA Method 18 |
·
CAPCS ·
CHP ·
ASP |
Particulate |
USEPA Method 5 |
·
CAPCS ·
CHP ·
ASP |
Carbon monoxide (CO) |
USEPA
Method 10 |
·
CHP ·
ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
·
CHP ·
ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
·
CHP ·
ASP |
Hydrogen chloride
(HCl) |
USEPA Method 26A |
·
CHP ·
ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
·
CHP ·
ASP |
Oxygen (O2); |
USEPA Method 3A |
·
CAPCS ·
CHP ·
ASP |
Velocity and
Volumetric Flow |
USEPA Method 2 |
·
CAPCS ·
CHP ·
ASP |
Ammonia (NH3) |
USEPA CTM 027 |
·
ASP |
Odour (including NH3
and H2S) |
EN 13725 |
·
CAPCS |
Water vapour content
(continuous measurement of the water vapour content should not be required if
the sample exhaust gas is dried before the emissions are analysed) |
USEPA Method 4 |
·
CAPCS ·
CHP ·
ASP |
Temperature |
USEPA Method 4 |
·
CAPCS ·
CHP ·
ASP |
With reference to the EM&A Manual, the air emission of the stacks
shall meet the following emission limits as presented in Tables 3.2 to
3.5.
Table 3.2
Emission Limit for CAPCS Stack
Parameter |
Emission Level
(mg/Nm3) (a) |
VOCs (including
methane) |
680 |
Dust (or Total Suspended
Particulates (TSP)) |
6 |
Odour (including NH3
& H2S) |
220 (b) |
Notes: (a) Hourly average concentration (b) The odour unit is OU/Nm3 |
Table 3.3
Emission Limit for CHP Stack
Parameter |
Maximum Emission
Level (mg/Nm3) (a) (b) |
Dust (or Total
Suspended Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs
(c) |
150 |
VOCs
(including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b)
Hourly average concentration (c)
NMVOCs should be monitored by gas sampling and laboratory analysis at an
agreed interval. For the first 12 months (starting from August 2019),
monitoring should be carried out at quarterly intervals. The monitoring
frequency should then be reduced to half-yearly for next 12 months (starting
from August 2020). The monitoring of NMVOCs ended in August 2021. (d)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. |
Table 3.4
Emission Limit for ASP Stack
Parameter |
Maximum Emission Level
(mg/Nm3) (a) (b) |
Dust (or Total Suspended
Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs
(including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen
content in the exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include
methane as biogas is adopted as fuel in the combustion process. |
Table
3.5 Emission Limit for Standby
Flaring Gas Unit ([2])
Parameter |
Maximum Emission
level (mg/Nm3) (a) (b) |
Dust (or Total
Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including
methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the
exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include
methane as biogas is adopted as fuel in the combustion process. |
To determine the effectiveness of
the proposed odour mitigation measures and to ensure that the operation of the
ORRC1 will not cause adverse odour impacts, odour monitoring of the CAPCS stack
(see Section 3.1.1) and odour patrol will be carried out.
Odour patrol shall be conducted by independent trained personnel/
competent persons in summer months (i.e. from July to September) for the first
two operational years of ORRC1 at monthly intervals along an odour patrol route
at the Project Site boundary as shown in Annex A([3]).
The perceived odour intensity is divided into 5 levels. Table
3.6 describes the odour intensity for different levels.
Table 3.6
Odour Intensity Level
Level |
Odour
Intensity |
0 |
Not detected. No odour perceived or an odour so weak that it
cannot be easily characterised
or described |
1 |
Slight identifiable
odour, and slight
chance to have odour
nuisance |
2 |
Moderate identifiable
odour, and moderate chance to have odour nuisance |
3 |
Strong identifiable,
likely to have odour nuisance |
4 |
Extreme severe
odour, and unacceptable odour level |
Table 3.7 shows the action level and limit level to be
used for odour patrol. Should any exceedance of the action and limit levels
occurs, actions in accordance with the event and action plan in Table 3.8
should be carried out.
Table 3.7
Action and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from
odour patrol) |
When one documented
compliant is received (a), or Odour
Intensity of 2 is measured from odour patrol. |
Two or
more documented complaints
are received (a) within a week; or Odour intensity of 3 or above is measured
from odour patrol. |
Note: (a) Once the complaint is received by
the Project Proponent (EPD), the Project Proponent would investigate and
verify the complaint whether it is related to the potential odour emission
from the ORRC1 and its on-site wastewater treatment unit. |
Table 3.8
Event and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project Proponent (a) |
Action Level |
|
|
Exceedance of action
level (Odour Patrol) |
1. Identify
source/reason of exceedance; 2. Repeat odour patrol
to confirm finding. |
1. Carry out
investigation to identify the source/reason of exceedance.
Investigation should be completed within 2 weeks; 2. Rectify any
unacceptable practice; 3. Implement more
mitigation measures if necessary; 4. Inform Drainage
Services Department (DSD) or the operator of the Siu Ho Wan Sewage Treatment
Works (SHWSTW) if exceedance is considered to be caused by the operation of
the SHWSTW. 5. Inform North Lantau
Refuse Transfer Station (NLTS) operator if exceedance is considered to be
caused by the operation of NLTS. |
Exceedance of action
level (Odour Complaints) |
1. Identify
source/reason of exceedance; 2. Carry out odour
patrol to determinate odour intensity. |
1. Carry out
investigation and verify the complaint whether it is related to potential
odour emission from the nearby SHWSTW; 2. Carry out
investigation to identify the source/reason of exceedance.
Investigation should be completed within 2 weeks; 3. Rectify any
unacceptable practice; 4. Implement more
mitigation measures if necessary; 5. Inform DSD or the
operator of the SHWSTW if exceedance is considered to be caused by the
operation of the SHWSTW. 6. Inform NLTS
operator if exceedance is considered to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit level |
1. Identify
source/reason of exceedance; 2. Inform EPD; 3. Repeat odour patrol
to confirm findings; 4. Increase odour
patrol frequency to bi-weekly; 5. Assess
effectiveness of remedial action and keep EPD informed of the results; 6. If exceedance
stops, cease additional odour patrol. |
1. Carry out
investigation to identify the source/reason of exceedance.
Investigation should be completed within 2 week; 2. Rectify any
unacceptable practice; 3. Formulate remedial
actions; 4. Ensure remedial
actions properly implemented; 5. If exceedance
continues, consider what more/enhanced mitigation measures should be
implemented; 6. Inform DSD or the
operator of the SHWSTW if exceedance is considered to be caused by the
operation of the SHWSTW. |
Note: (a) Project Proponent shall identify an
implementation agent. |
Environmental mitigation measures (related to air quality, water
quality, waste, land contamination, hazard-to-life, and landscape and visual)
to be implemented during the operation phase of the Project are recommended in
the approved EIA Report and EM&A Manual and are summarised in Annex C. Monthly site
audits for operation phase will be carried out to check the implementation of
these measures.
Compliance audits are to be undertaken to ensure that a valid discharge
licence has been issued by EPD prior to the discharge of effluent from the
operation of the Project site. The audit shall be conducted to ensure
that the effluent quality is in compliance with the discharge licence
requirements. As stipulated in the operation phase discharge licence,
effluent discharge are to be sampled monthly from the outlet chamber of the
Effluent Storage Tank, while effluent discharge are to be sampled bi-monthly from
the Petrol Interceptors. The effluent quality shall meet the discharge
limits as described in Table 3.9 and Table 3.10.
Table 3.9
Discharge Limits for Effluent from the Outlet Chamber of the Effluent Storage Tank
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day)
(a) |
645 |
pH (pH units) (b) |
6-10 (c) |
Suspended Solids
(b) |
800 |
Biochemical Oxygen
Demand (5 days, 20°) (b) |
800 |
Chemical Oxygen Demand
(b) |
2,000 |
Oil & Grease
(b) |
40 |
Total Nitrogen
(b) |
200 |
Total Phosphorus
(b) |
50 |
Surfactants (total)
(b) |
25 |
Notes: (a) Flow rate is not a parameter required to be
monitored and reported by the Contractor in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. (b) Parameters required to be monitored and
reported by the Contractor in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. (c) Range. |
Table 3.10
Discharge Limits for Effluent from the Petrol Interceptors
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day)
|
245 (a) |
Suspended Solids
(b) |
30 |
Chemical Oxygen Demand
(c) |
80 |
Oil & Grease
(c) |
20 |
Surfactants (total)
(b) |
15 |
Notes: (a) The surface runoff flow rate limit was estimated
by the overall yearly rainfall data. As the actual flowrate from the
petrol interceptors depends on the weather condition instead of the
performance of the petrol interceptor, monitoring and reporting of this
parameter is not required. Hence this parameter is not reported in Table
4.8 and Table 4.9. (b) Parameter not required to be reported in
accordance to Section B2 of the Effluent Discharge Licence under the WPCO.
(c) Parameters required to be reported
in accordance to Section B2 of the Effluent Discharge Licence under the
WPCO. |
In accordance with EM&A Manual, the landscape and visual mitigation
measures shall be implemented.
For operation phase, site inspection shall be conducted once a month for
the first year of operation of the Project. All measures as stated in the
implementation schedule of the EM&A Manual (see Annex C), including
compensatory planting, undertaken by both the Contractor and the specialist
Landscape Sub-Contractor during the first year of the operation phase shall be
audited by a Registered Landscape Architect (RLA) to ensure compliance with the
intended aims of the measures and the effectiveness of the mitigation
measures. After the one-year maintenance period, the landscape
maintenance and monitoring shall be carried out by the Contractor.
The concentrations of concerned air pollutants emitted from the stacks
of the CAPCS, CHP, ASP and the Standby Flaring Gas Unit during the reporting
period are monitored on-line by the continuous environmental monitoring system
(CEMS). During the reporting period, the standby flare operated on 3 May
2023.
With reference to the emission limits shown in Tables 3.2, 3.3,
3.4 and 3.5, the hourly average concentrations and the number of
exceedances of the concerned air emissions monitored for the CAPCS, CHP, ASP
and the Standby Flaring Gas Unit during this reporting period are presented in Tables
4.1 to 4.6.
It should be noted that measurements recorded under abnormal operating
conditions, e.g. start up and stopping of stacks, unstable operation, test runs
and interference of sensor, are disregarded.
Table 4.1
Hourly Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) |
Emission Limit
(mg/Nm3) |
Exceedance
Identified |
Remarks |
VOCs (including
methane) |
0.00 – 679.02 |
680 |
Nil |
Nil |
Dust (or TSP) |
0.00 – 0.03 |
6 |
Nil |
Nil |
Odour (including NH3
& H2S) (a) |
0.00 – 154.07 |
220 |
Nil |
Nil |
Notes: (a) The odour unit is OU/Nm3. |
Table 4.2
Hourly Average of Parameters Recorded for CHP 1
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust
(or TSP) |
0
- 132 |
15 |
Identified
(c) |
System
unstable (e.g. low efficiency, unstable column temperature) |
Carbon
Monoxide |
0
- 125 |
650 |
Nil |
Nil |
NOx |
0
- 549 |
300 |
Identified
(d) |
System
unstable (e.g. low efficiency, unstable column temperature) |
SO2
|
0
– 250 |
50 |
Identified
(e) |
De-sulphurisation
system tripped / Under Maintenance |
VOCs (including methane) (b) |
0
– 12,808 |
1,500 |
Identified
(f) |
System
unstable (e.g. low efficiency, unstable column temperature) |
HCl |
0
– 5 |
10 |
Nil |
Nil |
HF |
0
- 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) The VOCs emission limit include
methane as biogas is adopted as fuel in the combustion process. (c) Date with exceedances on Dust
(number of exceedance on the day) was identified on 8 (1) May 2023. (d) Dates with exceedances on NOx
(number of exceedance on the day) were identified on 1 (21), 2 (17), 3 (12),
4 (12), 5 (12), 6 (9), 7 (5), 8 (1), 10 (5), 11 (8), 13 (11), 14 (12), 15
(17), 16 (5), 17 (16), 18 (10), 19 (21), 20 (21), 21 (18), 22 (13), 23 (11),
24 (17), 25 (1), 30 (7) and 31 (1) May 2023. (e) Dates with exceedances on SO2
(number of exceedance on the day) were identified on 1 (1), 2 (1), 3
(4), 4 (3), 5 (5), 8 (1), 11 (6), 15 (1), 17 (2), 18 (1), 19 (7), 20 (13), 21
(1), 22 (9), 23 (9), 24 (17), 25 (1), 30 (2) and 31 (1) May 2023.
(f) Dates with exceedances on VOC
(number of exceedances on the day) was identified on 8 (1) May 2023. |
Table 4.3
Hourly Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) (a) |
Max. Emission
Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 - 25 |
15 |
Identified(c) |
System unstable (e.g.
low efficiency, unstable column temperature) |
Carbon Monoxide |
0 – 328 |
650 |
Nil |
Nil |
NOx |
0 – 571 |
300 |
Identified(d) |
System unstable (e.g.
low efficiency, unstable column temperature) |
SO2 |
0 – 113 |
50 |
Identified(e) |
De-sulphurisation
system tripped / Under Maintenance |
VOCs
(including methane) (b) |
0 – 1,483 |
1,500 |
Nil |
Nil |
HCl |
0 – 10 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) The VOCs emission limit include methane as
biogas is adopted as fuel in the combustion process. (c) Date with exceedance on Dust
(number of exceedance on the day) was identified on 8 (1) May 2023. (d) Dates with exceedances on NOx
(number of exceedance on the day) were identified on 1 (20), 2 (16), 3 (3), 4
(3), 5 (4), 6 (12), 7 (4), 8 (7), 9 (1), 10 (9), 11 (24), 12 (24), 13 (24),
14 (24), 15 (20), 16 (14), 17 (15), 18 (10), 19 (2), 20 (24), 21 (24), 22
(11), 23 (24), 24 (24), 25 (24), 26 (24), 27 (17), 28 (8), 29 (6), 30 (1) and
31 (5) May 2023. (e) Dates with exceedances on SO2
(number of exceedance on the day) were identified on 1 (4), 2 (4), 4 (2), 5
(5), 6 (1), 8 (6), 9 (20), 10 (3), 12 (1), 16 (1), 18 (1), 28 (3), 29 (3), 30
(1) and 31 (6) May 2023. |
Table 4.4
Hourly Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) (a) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 4 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 61 |
650 |
Nil |
Nil |
NOx |
0 – 589 |
300 |
Identified(c) |
System unstable (e.g.
low efficiency, unstable column temperature) |
SO2 |
0 – 67 |
50 |
Identified(d) |
De-sulphurisation
system tripped / Under Maintenance) |
VOCs
(including methane) (b) |
0 – 1,414 |
1,500 |
Nil |
Nil |
HCl |
0 – 8 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) The VOCs emission limit include methane as
biogas is adopted as fuel in the combustion process. (c) Dates with exceedances on NOx
(number of exceedance on the day) were identified on 21 (4), 22 (12), 23 (4),
24 (1), 25 (14), 26 (6), 27 (4), 28 (4), 29 (2) and 30 (15) May 2023. (d) Dates with exceedances on SO2
(number of exceedance on the day) were identified on 21 (4), 22 (6), 25 (1),
26 (2), 27 (2), 28 (3), 29 (2) and 30 (5) May 2023. |
Table 4.5
Hourly Average of Parameters Recorded for ASP
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust
(or TSP) |
0
– 1 |
5 |
Nil |
Nil |
Carbon
Monoxide |
0
– 186 |
100 |
Identified
(c) |
System
unstable (e.g. low efficiency, unstable column temperature ) |
NOx |
0
– 503 |
200 |
Identified
(d) |
System
unstable (e.g. low efficiency, unstable column temperature ) |
SO2 |
0
– 112 |
50 |
Identified(e) |
De-sulphurization
system tripped / Under Maintenance |
VOCs (including methane) (b) |
0
– 19 |
20 |
Nil |
Nil |
NH3 |
0 – 276 |
35 |
Identified (f) |
System unstable (e.g.
low efficiency, unstable column temperature ) |
HCl |
0 – 2 |
10 |
Nil |
Nil |
HF |
0 – 2 |
1 |
Identified (g) |
System unstable (e.g.
low efficiency, unstable column temperature ) |
Notes: (a) All values refer to an oxygen content in the
exhaust gas of 11% and dry basis. (b) The VOCs emission limit include methane as
biogas is adopted as fuel in the combustion process. (c) Dates with exceedances on CO
(number of exceedances on the day) were identified on 29 (2) May 2023. (d) Dates with exceedances on NOx
(number of exceedances on the day) were identified on 1 (4), 2 (7), 3 (9), 4
(20), 5 (18), 6 (24), 7 (23), 8 (6), 10 (5), 24 (1), 29 (3), 30 (4) and 31
(5) May 2023. (e) Dates with exceedances on SO2
(number of exceedances on the day) were identified on 3 (1), 29 (1), 30 (1)
and 31 (2) May 2023. (f) Dates with exceedances on NH3
(number of exceedances on the day) were identified on 1 (1), 4 (1), 5 (1), 8
(9), 9 (24), 10 (16), 11 (23), 12 (19), 13 (18), 14 (22), 15 (9), 16 (22), 17
(14), 18 (18), 19 (14), 20 (22), 21 (1), 22 (8), 23 (16), 24 (14), 25 (9), 26
(9), 27 (1), 29 (6) and 30 (3) May 2023. (g) Date with exceedances on HF (number of
exceedances on the day) was identified on 19 (1) May 2023. |
Table
4.6 Hourly Average of
Parameters Recorded for the Standby Flaring Gas Unit
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a)(c) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 0 |
5 |
Nil |
Nil |
Carbon Monoxide |
0 – 0 |
100 |
Nil |
Nil |
NOx |
0 – 0 |
200 |
Nil |
Nil |
SO2 |
0 – 0 |
50 |
Nil |
Nil |
VOCs
(including methane) (b) |
0 – 0 |
20 |
Nil |
Nil |
HCl |
0 – 0 |
10 |
Nil |
Nil |
HF |
0 – 0 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the
exhaust gas of 11% and dry basis. (b) The VOCs emission limit include methane as biogas
is adopted as fuel in the combustion process. (c) The standby flare operated on 3
May 2023. |
No odour patrol was required to be conducted for this reporting period.
Effluent discharge was sampled from the outlet chamber of the Effluent
Storage Tank monthly and from the Petrol Interceptor(s) bi-monthly as
stipulated in the operation phase discharge licence. The results of the
discharge samples from the outlet chamber of the Effluent Storage Tank are
recorded in Table 4.6 and the results from the Petrol Interceptors are
recorded in Tables 4.7 – 4.9.
Table 4.7
Results of the Discharge Sample from the Outlet
Chamber of the Effluent
Storage Tank
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow
Rate (m3/day) (a) |
0
- 161 (e) |
645 |
Yes |
pH
(pH units) (b) |
7.32
– 8.6 (e) |
6-10
(c) |
Yes |
Suspended
Solids (b) (d) |
293
(d) |
800 |
Yes |
Biochemical
Oxygen Demand (5 days, 20°) (b) (d) |
70
(d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
1,430
(d) |
2,000 |
Yes |
Oil
& Grease (b) (d) |
<5
(d) |
40 |
Yes |
Total Nitrogen (b) (d) |
218
(d) |
200 |
No |
Total
Phosphorus (b) (d) |
35.8
(d) |
50 |
Yes
|
Surfactants
(total) (b) (d) |
<1.0
(d) |
25 |
Yes |
Notes: (a) Parameter not required to be reported in
accordance to Section B2 of the Effluent Discharge Licence under the WPCO. (b) Parameters required to be reported in
accordance to Section B2 of the Effluent Discharge Licence under the
WPCO. (c) Daily Range. (d) Effluent sample collected on 5 May 2023. (e) Data collected daily |
Table 4.8
Results of the Discharge Sample from the Petrol Interceptor 1
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended
Solids (b) |
-
(a) |
30 |
NA |
Chemical
Oxygen Demand (c) |
-
(a) |
80 |
NA |
Oil
& Grease (c) |
-
(a) |
20 |
NA |
Surfactants
(total) (b) |
-
(a) |
15 |
NA |
Notes: (a) No sampling was required in May 2023. (b) Parameter not required to be reported in accordance
to Section B2 of the Effluent Discharge Licence under the WPCO. (c) Parameters required to be reported
in accordance to Section B2 of the Effluent Discharge Licence under the
WPCO. |
Table 4.9
Results of the Discharge Sample from the Petrol Interceptor 2
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended
Solids (b) |
-
(a) |
30 |
NA |
Chemical
Oxygen Demand (c) |
-
(a) |
80 |
NA |
Oil
& Grease (c) |
-
(a) |
20 |
NA |
Surfactants
(total) (b) |
-
(a) |
15 |
NA |
Notes: (a) No sampling was required in May 2023. (b) Parameter not required to be reported in
accordance to Section B2 of the Effluent Discharge Licence under the
WPCO. (c) Parameters required to be reported
in accordance to Section B2 of the Effluent Discharge Licence under the
WPCO. |
Wastes generated from the operation of the Project include chemical
waste, wastes generated from pre-treatment process and general refuse ([4]).
Reference has been made to the Monthly Summary Waste Flow Table prepared by the
Contractor (see Annex D).
With reference to the relevant handling records and trip tickets of this
Project, the quantities of different types of waste generated from the
operation of the Project in the reporting month are summarised in Table 4.10.
Table 4.10
Quantities of Waste Generated from the Operation of the Project
Month / Year |
Chemical Waste |
Waste Generated from |
General Refuse |
||
|
Disposal of at CWTC |
Disposed of at Landfill (a) |
Recycled (b) |
Disposed of at Landfill (a) |
Recycled (c) |
May 2023 |
0 L (d) |
662.27 tonnes |
0 tonnes |
2.88 tonnes (e) |
0.13 tonne |
Notes: (a) Waste generated from pre-treatment process
and general refuse other than chemical waste and recyclables were disposed of
at NENT Landfill by sub-contractors. (b) Among waste generated from pre-treatment process,
0.00 tonne of metals, 0.00 tonnes of papers/ cardboard packing and 0.00 tonne
of plastics were sent to recyclers for recycling during the reporting period.
(c) Among general refuse, 0.00 tonnes
of metals, 0.00 tonnes of papers/ cardboard packing and 0.13 tonnes of
plastics were sent to recyclers for recycling during the reporting period. (d) No chemical waste was disposed of at CWTC in
May 2023. (e) It was assumed that four 240-litre bins
filled with 80% of general refuse were collected at each collection.
The general refuse density was assumed to be around 0.15 kg/L. |
The monthly inspection for the
operation phase of the Project on 23 May 2023 covered the operation phase
environmental site audit. Joint site inspection was conducted by
representatives of the Contractor, IEC, and the MT on 23 May 2023 as required for
the operation of the Project.
The audits checked the
implementation of the recommended mitigation measures for air quality,
landscape and visual, water quality, waste (land contamination) and
hazard-to-life stated in the Implementation Schedule (see Annex C).
Key observations during the reporting period are summarised as follows:
23 May 2023
·
No particular observation
during this inspection.
Other than the above observations, the Contractor has implemented
environmental mitigation measures recommended in the approved EIA Report and
EM&A Manual.
Inspection of the landscape and
visual mitigation measures for the operation phase of the Project was performed on 23 May 2023.
It was confirmed that the necessary
landscape and visual mitigation measures during the operation phase as
summarised in Annex C
were generally implemented by the Contractor. No specific observation was
found during the joint site inspection on 23 May 2023. No non-compliance
in relation to the landscape and visual mitigation measures was identified
during the site audits in this reporting period and therefore no further
actions are required. The ET/MT will keep track of the EM&A programme
to check compliance with environmental requirements and the proper
implementation of all necessary mitigation measures.
Non-compliance of emission limits of Dust, VOCs, NOx and SO2
from CHP 1; Dust, NOx and SO2 from CHP 2; NOx
and SO2 from CHP 3; and CO, NOx, SO2, NH3
and HF from ASP were recorded during the reporting period.
Non-compliance of discharge limits of Total Nitrogen from the outlet
chamber of the effluent storage tank was recorded during the reporting period.
The Contractor has reviewed the organic waste treatment processes (i.e.
waste reception, waste pre-treatment, anaerobic digesters, and composting
processes) and found that they were operated normally during the reporting
period. The Contractor has investigated the de-sulphurisation system,
CHPs and the ASP, the
potential causes for the exceedance were identified.
The investigation reports of the above exceedance are presented in Annex F.
Activities to be undertaken for the coming reporting period are:
·
Operation of the
Project;
·
CEMS maintenance;
·
QAL 2 testing with 3rd
Party Lab was conducted for MCS 1 and MCS 2; and
·
Completed the
replacement of membrane diffusers for all of the SBR Tanks of the Waste Water
Treatment Plant.
This EM&A Report presents the EM&A programme undertaken during
the reporting period from 1 to 31 May 2023 in accordance with EM&A
Manual (Version F) and requirements of EP (FEP-01/395/2010/C).
For the operation phase, exceedances of the emission limits for the CHPs
and the ASP stack monitoring were recorded under normal operating conditions
during the reporting period (see Table 8.1).
Table 8.1
Exceedances for Stack
Emissions
Stack |
Exceedances During
the Reporting Period |
Cogeneration Unit 1 (CHP 1) |
·
Exceeded emission
limit of Dust on 8 May 2023. ·
Exceeded emission
limit of NOx on 1, 2, 3, 4, 5, 6, 7, 8, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 21,
22, 23, 24, 25, 30 and 31 May 2023. ·
Exceeded emission
limit of SO2 on 1, 2, 3, 4, 5, 8, 11, 15, 17, 18, 19, 20, 21, 22, 23, 24, 25, 30 and
31 May 2023. ·
Exceeded emission
limit of VOC on 8 May 2023. |
Cogeneration Unit 2 (CHP 2) |
·
Exceeded emission
limit of Dust on 8 May 2023. ·
Exceeded emission
limit of NOx on 1 - 31 May 2023. ·
Exceeded emission
limit of SO2 on 1, 2, 4, 5, 6, 8, 9, 10, 12, 16, 18, 28, 29, 30 and 31 May 2023. |
Cogeneration Unit 3 (CHP 3) |
·
Exceeded emission
limit of NOx on 21, 22, 23, 24, 25, 26, 27, 28, 29 and 30 May 2023. ·
Exceeded emission
limit of SO2 on 21, 22, 25, 26, 27, 28, 29 and 30 May 2023. |
Ammonia Stripping Plant (ASP) |
·
Exceeded emission
limit of CO on 29 May 2023. ·
Exceeded emission
limit of NOx on 1, 2, 3, 4, 5, 6, 7, 8, 10, 24, 29, 30 and 31 May
2023. ·
Exceeded emission
limit of SO2 on 3, 29, 30 and 31 May 2023. ·
Exceeded emission
limit of NH3 on 1, 4, 5, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18,
19, 20, 21, 22, 23, 24, 25, 26, 27, 29 and 30 May 2023. ·
Exceeded emission
limit of HF on 19 May 2023. |
Non-compliance of emission limits of
Dust, VOCs, NOx and SO2 from CHP 1; Dust, NOx
and SO2 from CHP 2; NOx and SO2 from CHP 3;
and CO, NOx, SO2, NH3 and HF from ASP were
recorded during the reporting period. The exceedances
of SO2 from the CHPs and ASP occurred due to tripping of the
de-sulphurisation system. The exceedances of Dust, VOCs and NOx from
CHPs and the exceedances of CO, NOx and HF from ASP occurred due to system
instability.
Non-compliance of discharge limits of Total Nitrogen from the outlet
chamber of the effluent storage tank and Suspended Solids from Petrol
Interceptor 1 were recorded during the reporting period.
The environmental control /mitigation measures related to air quality,
water quality, waste (including land contamination prevention), hazard-to-life
and landscape and visual recommended in the approved EIA Report and the
EM&A Manual were properly implemented by the Contractor during the
reporting month.
Monthly landscape and visual monitoring were conducted in the reporting
period. The necessary landscape and visual mitigation measures
recommended in the approved EIA Report were generally implemented by the
Contractor.
No complaint/summon/prosecution was received.
([1])
As some of the minor items are yet to be closed out in March
2019, the construction phase EM&A programme and Operation Phase EM&A
programme were undertaking in parallel in March 2019.
([2])
A standby facility. Only operate when the CHPs
are not in operation or when the biogas generated exceeded the utilisation rate
of the CHPs.