Pages from 1st Monthly EM&A Report_v3_certified_Page_1

Pages from 1st Monthly EM&A Report_v3_certified_Page_2

 

 

Contents

Executive Summary

1                      inroduction                                                                            

1.1                   Purpose of the Report                                                     

1.2                   Structure of the Report                                                

2                      Project information                                                          

2.1                   Background                                                                           

2.2                   General Site Description                                                

2.3                   Construction Activities                                                   

2.4                   Project Organisation and Management Structure        

2.5                   Status of Environmental Approval Documents 4

3                      Environmental Monitoring Requirement, environmental Mitigation Measures                                                                                  

4                      Implementation Status on Environmental Protection Requirements         

5                      Waste Management                                                             

6                      Environmental Inspections                                            

6.1                   Weekly Site Audits                                                               

6.2                   Landscape and Visual Audit                                           

7                      Environmental Non-conformance                             

7.1                   Summary of Environmental Non-Compliance        

7.2                   Summary of Environmental Complaint                    

7.3                   Summary of Environmental Summon and Successful Prosecution     

8                      Future Key Issues                                                                

8.1                   Key Issues for the Coming Month                                

8.2                   Construction Programme                                              

9                      Conclusions                                                                           

 


 

LIST OF TABLES

Table 2.1

Summary of Construction Activities Undertaken in the Reporting Period

Table 2.2

Summary of Environmental Licensing, Notification and Permit Status

Table 5.1

Quantities of Waste Generated from the Project

Table 8.1

Construction Works to be undertaken in the Next Reporting Period

 

LIST OF ANNEXES

Annex A

Location of Project

Annex B

Works Location

Annex C

Construction Programme for the Project

Annex D

Project Organization Chart and Contact Detail

Annex E

Implementation Schedule of Mitigation Measures

Annex F

Waste Flow Table

Annex G

Environmental complaint, Environmental Summons and Prosecution Log

 

EXECUTIVE SUMMARY

The construction works of No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the Project) commenced on 21 May 2015.  This is the 1st monthly Environmental Monitoring and Audit (EM&A) report presenting the EM&A works carried out during the period from 21 May 2015 to 30 June 2015 in accordance with the EM&A Manual.

Summary of Construction Works undertaken during the Reporting Month

Works undertaken in the reporting month included:

¡P        Open cutting;

¡P        Pre-drilling; and

¡P        Piling.

Environmental Monitoring and Audit Progress

A summary of the monitoring activities undertaken in this reporting period is listed below:

 

¡P   Joint Environmental Site Inspection

5 times

¡P   Landscape & Visual Monitoring

2 times

Waste Management

Waste generated from this Project includes inert construction and demolition (C&D) materials (public fill) and non-inert C&D materials (construction wastes).  In total, 2266.14 tonnes of inert C&D material were generated from the Project. 2256.48 tonnes were disposed as public fill. 9.66 tonnes of general refuse was disposed as landfill. 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period.

Environmental Site Inspection

Five weekly joint environmental site inspections were carried out by the representatives of the Contractor, SOR and the Environmental Team (ET).  The IEC was also present at the joint inspection on 17 June 2015.  Details of the audit findings and implementation status of the mitigation measures are presented in Section 6.1.

Landscape & Visual

An onsite inspection on landscape and visual mitigation measures was performed on 5 and 17 June 2015.  Details of the audit findings and implementation status of the mitigation measures are presented in Sections 6.2.

Environmental Exceedance/Non-conformance/Compliant/Summons and Prosecution

No exceedance was recorded during the reporting period.

No non-compliance event was recorded during the reporting period.

No environmental complaint and summon/prosecution was received in this reporting period.

Future Key Issues

Works to be undertaken in the next reporting month include:

¡P        Piling;

¡P        Removing Topsoil from Building 2; and

¡P        Foundation Footing of Tower Crane.

Environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoffs, waste management and landscaping issues.

 


 

1                                            inroduction

ERM-Hong Kong, Limited (ERM) was appointed by OSCAR Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I (the Project).

1.1                                      Purpose of the Report

This is the 1st EM&A report which summarises the monitoring results and audit findings for the EM&A programme during the reporting period from 21 May 2015 to 30 June 2015.

1.2                                      Structure of the Report

The structure of the report is as follows:

Section 1:   Introduction

It details the scope and structure of the report.

 

Section 2:   Project Information

It summarises the background and scope of the Project, site description, project organization, construction programme, construction works undertaken and status of the Environmental Permits (EP)/licences over the construction phase of the Project.

 

Section 3:   Environmental Monitoring Requirements

It summarises the environmental monitoring requirements including monitoring parameters, programmes, methodologies, frequency, locations, Action and Limit Levels, Event/Action Plans, environmental mitigation measures as recommended in the EM&A Manual and approved EIA report.

 

Section 4:   Implementation Status on Environmental Mitigation Measures

It summarises the implementation of environmental protection measures during the reporting period.

 

Section 5:   Waste Management

It summarises the quantity of public fill and construction waste generated in the reporting period

 

Section 6:   Environmental Site Inspection

It summarises the audit findings of the weekly site inspections undertaken within the reporting period.

 

Section 7:   Environmental Non-conformance

It summarises any exceedance of environmental performance standard, environmental complaints and summons received within the reporting period.

 

Section 8:   Further Key Issues

It summarises the impact forecast and monitoring schedule for the next reporting month.

 

Section 9:   Conclusions

 

2                                            Project information

2.1                                      Background

The Organic Waste Treatment Facilities (OWTF) Phase I development (hereinafter referred to as ¡§the Project¡¦) is to design, construct and operate a biological treatment facility with a capacity of about 200 tonnes per day and convert source-separated organic waste from commercial and industrial sectors (mostly food waste) into compost and biogas through proven biological treatment technologies. 

The environmental acceptability of the construction and operation of the Project had been confirmed by findings of the associated Environmental Impact Assessment (EIA) Study completed in 2009.  The Director of Environmental Protection approved this EIA Report under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report).  Subsequent Report on Re-assessment on Environmental Implications and Report on Re-assessment on Hazard to Life Implications were completed in 2013, respectively.

An Environmental Permit (EP) (No. EP-395/2010) was issued by the Environmental Protection Department (EPD) to the EPD, the Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No. EP-395/2010/B), respectively.  The Design Build and Operate Contract for the OWTF (Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint Venture (OSCAR or the Contractor).  A Further EP (No. FEP-01/395/2010/B) was issued by the EPD to the OSCAR on 16 February 2015.

Under the requirements of Condition 5 of the EP (No. FEP-01/395/2010/B), an Environmental Monitoring and Audit (EM&A) programme as set out in the Agreement No. CE7/2008 (EP) EM&A Manual (hereinafter referred to as EM&A Manual) is required to be implemented.  ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the Environmental Team (ET) to undertake the EM&A programme for the Contract.

The construction works commenced on 21 May 2015 and are scheduled for completion by April 2017.

2.2                                      General Site Description

The Project Site is located at Siu Ho Wan in North Lantau with an area of about 2 hectares.  The layout of the Project Site is illustrated in Annex A.

2.3                                      Construction Activities

A summary of the major construction activities undertaken in the reporting period is shown in Table 2.1.  The locations of the construction activities are shown in Annex B.  The construction programme of the Project is presented in Annex C.

Table 2.1        Summary of Construction Activities Undertaken in the Reporting Period

Construction Activities Undertaken

¡P           Open cutting

¡P           Pre-drilling

¡P           Piling

2.4                                      Project Organisation and Management Structure

The project organisation chart and contact details are shown in Annex D.

2.5                                      Status of Environmental Approval Documents

A summary of the valid permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2.

Table 2.2        Summary of Environmental Licensing, Notification and Permit Status

Permit/ Licences/ Notification

Reference

Validity Period

Remarks

Environmental Permit

FEP-01/395/2010/B

Throughout the Contract

Permit granted on 16 February 2015

Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation

Ref No. 386715

Throughout the Contract

-

Water Discharge License

WT00021482-2015

21 May 2015 ¡V 31 May 2020

-

Construction Noise Permit

GW-RW0078-15

1 April 2015 ¡V 30 August 2015

 

Chemical Waste Producer Registration

WPN 5213-961-O2231-01

Throughout the Contract

Licence approved on 29 April 2015

3                                            Environmental Monitoring Requirement, environmental Mitigation Measures

All the relevant environmental mitigation measures listed in the EIA Report and EM&A Manual are summarised in Annex E.

According to the EM&A Manual and EP requirement, no air quality, noise and water quality monitoring is required.

Bi-weekly landscape and visual audit is required to ensure that the design, implementation and maintenance of landscape and visual mitigation measures recommended in the EIA Report are fully achieved.

 

4                                            Implementation Status on Environmental Protection Requirements

The Contractor has implemented environmental mitigation measures and requirements as stated in the approved EIA Report and EM&A Manual.  The implementation status of the measures during the reporting period is summarised in Annex E.

5                                            Waste Management 

Wastes generated from this Project include inert construction and demolition (C&D) materials (public fill) and non-inert C&D materials (construction waste).  Construction waste comprises general refuse, metals and paper/cardboard packaging materials.  Metals generated from the Project are also grouped into construction waste as the materials were not disposed of with others at public fill.  Reference has been made to the Monthly Summary Waste Flow Table prepared by the Contractor (see Annex F).  With reference to the relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 5.1. 

Table 5.1        Quantities of Waste Generated from the Project

Month / Year

Quantity

 

Total Inert C&D Materials Generated (a)

Non-inert C&D Materials (b)

C&D Materials Recycled (c)

C&D Waste Disposed of at Landfill (d) 

Chemical Waste

May 2015

29.58 tonnes

0.00 kg

0.00 tonnes

0 L

June 2015

2,218.13 tonnes

0.00 kg

9.66 tonnes

0 L

Notes:

(a)   Inert C&D materials (public fill) include bricks, concrete, building debris, rubble and excavated spoil.  In total, 2266.14 tonnes of inert C&D material were generated from the Project. 2256.48 tonnes were disposed as public fill. 9.66 tonnes of general refuse was disposed as landfill.   The detailed waste flow is presented in Annex F.

(b)   Non-inert C&D materials (construction wastes) include metals, paper / cardboard packaging waste, plastics and other wastes such as general refuse.  Metals generated from the Project were grouped into construction wastes as the materials were not disposed of with others at the public fill.

(c)    0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period.

(d)   Construction wastes other than metals, paper/cardboard packaging, plastics and chemicals were disposed of at NENT Landfill by subcontractors. 

 

6                                            Environmental Inspections

6.1                                      Weekly Site Audits

Joint site inspections were conducted by representatives of the Contractor, the ER, IC and the ET on 28 May, and 5, 12, 17 and 26 June 2015.  The IEC was also present at the joint inspection on 17 June 2015.  Follow-up actions resulting from the last site inspections were taken as reported by the Contractor and their results were observed in the site inspections conducted in the reporting period.

Major observations during the reporting period are summarised as follows:

28 May 2015

¡P        The discharge point is not yet covered properly.  It is recommended to place sand bags around the discharge point or cover the discharge point to avoid untreated wastewater run-off.

¡P        The sedimentation tank was observed to be full after raining and the untreated water in the sedimentation tank was discharged onto the site without passing through the WetSep for treatment.  It is recommended to recirculate the untreated water back to the sump pit and stop pumping water to the sedimentation tank from sump pit when the WetSep is shut down for emergency or maintenance purpose.

¡P        General refuse and debris was observed within the tree protection zone of Trees T40, T41 and T44.  It is recommended to clear general refuse near the trees (T40, 41 and T44) and provide toolbox talk to all workers on tree protection measures.

¡P        The tree trunk of Trees T40, T41 and T44 was observed to be tied too tight by plastic strips.  It is recommended to loosen ropes and plastic strips and avoid tying around the trees.

¡P        No protection zone was set up for trees T43 and T44 within the site.  It is recommended to fence off the identified trees to block the access to the identified trees.

¡P        Wire was observed to be hanged on the branches of Tree T44.  It is recommended to remove wires and avoid hanging any materials on the tree.

5 June 2015

¡P        Pond water is found in the tray under the chemical container. It is recommended to clear the pond water regularly, especially after raining.

12 June 2015

¡P        Pond water is found in some areas such as areas near vehicle washing facilities, parking area, on tarpaulin sheets and in the U-channel. It is recommended to clear the pond water regularly, especially after raining. Pond water is found in the cop of an excavator. It is recommended to check if there is any pond water regularly, especially after raining. It is also recommended to turn it upside down to prevent pond water.

¡P        Pond water is found in drip trays. It is recommended to clear the pond water regularly, especially after raining.

¡P        Drip tray is missing for some of the chemical containers. It is recommended to provide drip tray under every chemical containers, even if the chemical are recently arrived to avoid chemical leakage.

17 June 2015

¡P        A single chemical container without a drip tray is found. It is recommended to provide drip tray under every chemical containers, and to place the same type of chemical in the same area.

¡P        Exposed area is found to be dry and dusty. It is recommended to spray water regularly to prevent dry and dusty situation.

26 June 2015

¡P        Soil is found to be not completely covered by tarpaulin. It is recommended to fully cover it to prevent dry and dusty situation.

¡P        Drip tray is missing for some of the chemical containers. It is recommended to provide drip tray under every chemical containers, even if the chemical are recently arrived to avoid chemical leakage.

¡P        General refuse is found in a tank.  It is recommended to provide general refuse point in AD Plant Tank area.

¡P        Pond water is found in drip trays.  It is recommended to clear the pond water regularly, especially after raining

6.2                                      Landscape and Visual Audit

In accordance with the EM&A Manual, bi-weekly landscape and visual inspection is required to ensure that the design, implementation and maintenance of landscape and visual mitigation measures recommended in the EIA Report are fully achieved.  An onsite inspection of the landscape and visual mitigation measures was performed on 5 and 17 June 2015.

Follow-up actions resulting from the last site inspections were taken as reported by the Contractor and their results were observed in the site inspections conducted in the reporting period.

It was confirmed that most of the necessary landscape and visual mitigation measures as summarised in Annex E were implemented by the Contractor. 

The major findings are summarised as follows:


5 June 2015

Item

Observation & Recommendation

Photo Record

1.

The tree trunk of Tree T10 was observed to be tied too tight by plastic strips.  It is recommended to loosen ropes and plastic strips and avoid tying around the trees.

Photo 5-6-15 9 47 47 am

(T10)

2.

A branch of a tree outside the site boundary is found to be tied around the trunk of Tree T11. It is recommended to loosen ropes and plastic strips and avoid unwanted tying around the trees.

Photo 5-6-15 9 53 53 am

Photo 5-6-15 9 54 00 am

Photo 5-6-15 9 56 59 am

(T11)

3.

Name tag for tree T43 is lost.  It is recommended to fence off the identified tree to block the access to the identified trees and tag the tree properly.

Photo 5-6-15 10 18 37 am

(T43)

 

4.

Trees at the northern site boundary are tagged properly and a fence is erected to separate the trees and the site office.   However, to give a clear indication on protecting those trees, it is recommended to provide a ¡§Tree Protection Zone¡¨ sign on the fence to restrict the access to the trees.

 

N/A

17 June 2015

No observation is recorded.       

7                                            Environmental Non-conformance

7.1                                      Summary of Environmental Non-Compliance

No non-compliance event was recorded during the reporting period.

7.2                                      Summary of Environmental Complaint

No complaint was received during the reporting period.  The cumulative environmental complaint log is shown in Annex G.

7.3                                      Summary of Environmental Summon and Successful Prosecution

No summon/prosecution was received during the reporting period.  The cumulative summons/prosecution log is shown in Annex G.

 

8                                            Future Key Issues

8.1                                      Key Issues for the Coming Month

Works to be undertaken for the coming monitoring period are summarised in Table 8.1.

Table 8.1        Construction Works to be undertaken in the Next Reporting Period

Construction Activities Undertaken

 

¡P           Piling

¡P           Removing Topsoil from Building 2

¡P           Foundation Footing of Tower Crane

Potential environmental impacts arising from the above construction activities will be mainly associated with dust, construction noise, site runoffs, waste management and landscaping issues.

8.2                                      Construction Programme

The most up-to-date construction programme for the Project is presented in Annex C.

 

9                                            Conclusions

This EM&A Report presents the EM&A programme undertaken during the reporting period from 21 May 2015 to 30 June 2015 in accordance with EM&A Manual and requirements of EP (FEP-01/395/2010/B). 

No air quality, noise and water quality monitoring is required.

Bi-weekly landscape and visual monitoring was conducted in the reporting period.  Most of the necessary landscape and visual mitigation measures recommended in the EIA Report were implemented by the Contractor.  Follow-up actions are required by the Contractor to improve protection of the retained or to-be transplanted trees.

No non-compliance event was recorded during the reporting period.

No complaint and summons/prosecution was received during the reporting period.

The ET will keep track of the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all the necessary mitigation measures in the coming periods.