Contents
Executive
Summary
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Construction Activities
2.4 Project Organisation and
Management Structure
2.5 Status of Environmental
Approval Documents
3 Environmental Monitoring Requirement, environmental
Mitigation Measures
4 Implementation Status on Environmental Protection
Requirements
6.1 Weekly Site Audits
6.2 Landscape and Visual Audit
7 Environmental Non-conformance
7.1 Summary of Environmental
Non-Compliance
7.2 Summary of Environmental
Complaint
7.3 Summary of Environmental
Summon and Successful Prosecution
8.1 Key Issues for the Coming
Month
8.2 Construction Programme
LIST OF TABLES
Table 2.1 Summary of Construction Activities
Undertaken in the Reporting Period
Table 2.2 Summary
of Environmental Licensing, Notification and Permit Status
Table 5.1 Quantities
of Waste Generated from the Project
Table 8.1 Construction
Works to be undertaken in the Next Reporting Period
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
|
Annex F |
|
Annex G |
Environmental complaint,
Environmental Summons and Prosecution Log |
Annex H |
|
|
|
EXECUTIVE SUMMARY
The construction works of No. EP/SP/61/10 Organic Waste
Treatment Facilities Phase I (the Project) commenced
on 21 May 2015. This is the 17th monthly Environmental Monitoring
and Audit (EM&A) report presenting the EM&A works carried out during
the period from 1 October 2016 to 31 October 2016 in accordance with the
EM&A Manual.
Summary of Construction Works undertaken during the Reporting
Month
Works undertaken in the reporting month included:
·
Building 1 – superstructure works, water tanks
construction.
·
Building 2 – defect rectification, ABWF and finishing
work, steel work for covered walkway, installation of pump and pipework at
roof, Electrical and BS installation work.
·
Building 3 – superstructure works, ABWF, Electrical
and BS installation inside G/F rooms.
·
AD Tank – Erection of AD 3 and Suspension Buffer Tank,
testing, scaffolding erection and cladding work to AD 1, water filling to AD2.
·
Biogas Holder & Plant Area –erection of De-sulphurisation tank 1 & 2, blowers, standby flare,
carbon filter.
·
Ammonia Stripping Plant –structural steel and
mechanical erection work.
·
Mechanical installation (guide rail) at Building 1.
·
Tiles installation inside tunnel of Building 2.
·
Sitewide –
Underground drainage and drawpit work.
·
Portion 2 – temp. traffic
arrangement, roadworks.
·
Portion 4 – Material handling and storage, steel bending
& cutting.
Environmental Monitoring and Audit Progress
A summary of the monitoring activities undertaken in
this reporting period is listed below:
·
Joint Environmental Site Inspection |
5 times |
·
Landscape & Visual Monitoring |
3 times |
Waste Management
Waste generated from this Project includes inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction wastes).
Inert C&D materials (public fill) include bricks,
concrete, building debris, rubble and excavated spoil. In total, 1522.82 tonnes of inert C&D material
were generated from the Project, of which 0.00 tonnes were reused in this
Contract. The 1522.82 tonnes of inert
C&D material were disposed of as public fill to the Fill Banks at Tuen Mun Area 38.
Non-inert C&D materials (construction wastes)
include metals, paper / cardboard packaging waste, plastics and other wastes
such as general refuse. 40,000.00 kg of
metals, 9300.00 kg of papers/ cardboard packing and 0.00 kg of plastics were
sent to recyclers for recycling during the reporting period. 114.7 tonnes of general refuse was disposed as
landfill.
0.00 L of chemical waste was collected by licenced
waste collector and sent to West New Territories (WENT) Landfill.
Environmental Site Inspection
Five weekly joint environmental site inspections were
carried out by the representatives of the Contractor, SOR and the Environmental
Team (ET). The IEC was also present at the joint inspection on 19 October 2016. Details of the
audit findings and implementation status of the mitigation measures are
presented in Section 6.1.
Landscape & Visual
Onsite inspections on landscape and visual
mitigation measures were performed on 3, 19 and 31 October 2016. Details of the audit findings and
implementation status of the mitigation measures are presented in Sections 6.2.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance
was recorded during the reporting period.
No non-compliance
event was received during the reporting period.
No environmental complaint and summon/prosecution was
received in this reporting period.
Future Key Issues
Works to be undertaken in the next reporting month
include:
·
Building
1 - superstructure works, defect rectification and ABWF works.
·
Building
2 - ABWF and finishing work, steel work for covered walkway, installation of
pump and pipework at roof, Electrical and BS installation work.
·
Building
3 - ABWF, Electrical and BS installation inside G/F rooms.
·
AD
Tank - Erection of AD 3, cladding work to AD 1, water filling, testing,
scaffolding erection to AD2.
·
Biogas
Holder & Plant Area -erection of De-sulphurisation
tank 1 & 2, carbon filter.
·
Ammonia
Stripping Plant -structural steel and mechanical erection work.
·
CHP
pipework and accessories installation.
·
Mechanical
installation (pre-treatment equipment, grab crane) at Building 1.
·
Mechanical
installation (star screen) and tiles installation inside tunnels at Building 2.
·
Sitewide - Underground drainage and drawpit
work.
·
Portion
2 - temp. traffic arrangement, roadworks.
·
Portion
4 - Material handling and storage, steel bending & cutting.
Environmental impacts arising from the above
construction activities are mainly associated with dust, construction noise,
site runoffs, waste management and landscaping issues.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR
Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to
undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I
(the Project).
This is the 17th EM&A report which summarises
the monitoring results and audit findings for the EM&A programme during the
reporting period from 1 to 31 October 2016.
The structure of the report is as follows:
Section 1: Introduction
It details the scope and structure of the report.
Section 2: Project
Information
It summarises the background and
scope of the Project, site description, project organization, construction
programme, construction works undertaken and status of the Environmental
Permits (EP)/licences over the construction phase of the Project.
Section 3: Environmental Monitoring Requirements
It summarises the environmental monitoring requirements
including monitoring parameters, programmes, methodologies, frequency,
locations, Action and Limit Levels, Event/Action Plans, environmental
mitigation measures as recommended in the EM&A Manual and approved EIA
report.
Section 4: Implementation
Status on Environmental Mitigation Measures
It summarises the implementation of environmental
protection measures during the reporting period.
Section 5: Waste
Management
It summarises the quantity of public fill and
construction waste generated in the reporting period
Section 6: Environmental
Site Inspection
It summarises the audit findings of the weekly site
inspections undertaken within the reporting period.
Section 7: Environmental
Non-conformance
It summarises any exceedance of environmental
performance standard, environmental complaints and summons received within the
reporting period.
Section 8: Further Key Issues
It summarises the impact forecast and monitoring
schedule for the next reporting month.
Section 9: Conclusions
The
Organic Waste Treatment Facilities (OWTF) Phase I development (hereinafter
referred to as “the Project”) is to design, construct and operate a biological
treatment facility with a capacity of about 200 tonnes per day and convert
source-separated organic waste from commercial and industrial sectors (mostly
food waste) into compost and biogas through proven biological treatment
technologies.
The environmental acceptability of the construction and operation
of the Project had been confirmed by findings of the associated Environmental
Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection
approved this EIA Report under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010)
(hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on
Environmental Implications and Report on Re-assessment on Hazard to Life
Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010)
was issued by the Environmental Protection Department (EPD) to the EPD, the
Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A)
and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the
OWTF (Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the
Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited
and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint Venture
(OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was
issued by the EPD to the OSCAR on 16 February 2015. Variation to both EPs No.
EP-395/2010/B and No. FEP-01/395/2010/B were made in December 2015.
The latest EPs, No. EP-395/2010/C and No.
FEP-01/395/2010/C, were issued by the EPD on 21 December 2015.
Under the requirements of Condition 5 of the EP (No.
FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme
as set out in the Agreement No. CE7/2008 (EP) EM&A Manual (hereinafter
referred to as EM&A Manual) is required to be implemented. ERM-Hong Kong, Ltd (ERM) has been appointed
by OSCAR as the Environmental Team (ET) to undertake the EM&A programme for the Contract.
The construction works commenced on 21 May 2015 and
are scheduled for completion by April 2017.
The
Project Site is located at Siu Ho Wan in North Lantau with an area of about 2
hectares. The layout of
the Project Site is illustrated in Annex A.
A summary of the major construction activities
undertaken in the reporting period is shown in Table 2.1. The locations of the construction activities
are shown in Annex
B. The construction programme of the Project is
presented in Annex
C.
Table 2.1 Summary of Construction Activities
Undertaken in the Reporting Period
Construction Activities
Undertaken |
·
Building 1 – superstructure works,
water tanks construction. ·
Building 2 – defect rectification,
ABWF and finishing work, steel work for covered walkway, installation of pump
and pipework at roof, Electrical and BS installation work. ·
Building 3 – superstructure works,
ABWF, Electrical and BS installation inside G/F rooms. ·
AD Tank – Erection of AD 3 and
Suspension Buffer Tank, testing, scaffolding erection and cladding work to AD
1, water filling to AD2. ·
Biogas Holder & Plant Area
–erection of De-sulphurisation tank 1 & 2,
blowers, standby flare, carbon filter. ·
Ammonia Stripping Plant
–structural steel and mechanical erection work. ·
Mechanical installation (guide
rail) at Building 1. ·
Tiles installation inside tunnel
of Building 2. ·
Sitewide –
Underground drainage and drawpit work. ·
Portion 2 – temp. traffic arrangement, roadworks. ·
Portion 4 – Material handling and
storage, steel bending & cutting. |
The project organisation chart and contact details are
shown in Annex D.
A summary of the valid permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary of Environmental Licensing,
Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December
2015 |
Notification of Construction
Works under the Air Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00021482-2015 |
21 May 2015 – 31 May 2020 |
Approved on 21 May 2015 |
Construction Noise Permit –
P1&P2 |
GW-RW0483-16 |
12
September 2016 – 11 December 2016 |
Approved
on 22 August 2016 |
Construction Noise Permit – P3 |
GW-RW0272-16 |
1 June
2016 – 30 November 2016 |
Approved
on 17 May 2016 |
Chemical Waste Producer
Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
All
the relevant environmental mitigation measures listed in the EIA Report and
EM&A Manual are summarised in Annex E.
According to the EM&A Manual and EP requirement,
no air quality, noise and water quality monitoring is required.
Bi-weekly landscape and visual audit is required to ensure that the design,
implementation and maintenance of landscape and visual mitigation measures
recommended in the EIA Report are fully achieved.
The Contractor has implemented environmental
mitigation measures and requirements as stated in the approved EIA Report and
EM&A Manual. The implementation
status of the measures during the reporting period is summarised in Annex E.
Wastes generated from this Project include inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction waste). Construction
waste comprises general refuse, metals and paper/cardboard packaging
materials. Metals generated from the Project
are also grouped into construction waste as the materials were not disposed of
with others at public fill. Reference
has been made to the Monthly Summary Waste Flow Table prepared by the
Contractor (see Annex F). With reference to the relevant handling
records and trip tickets of this Project, the quantities of different types of
waste generated in the reporting month are summarised in Table 5.1.
Table 5.1 Quantities
of Waste Generated from the Project
Month / Year |
Quantity |
|||
|
Total Inert C&D Materials Generated (a) |
Non-inert C&D Materials (b) |
||
C&D Materials Recycled (c) |
C&D Waste Disposed of at Landfill (d) |
Chemical Waste |
||
October 2016 |
1522.82 tonnes |
49,300.00 kg |
114.47 tonnes |
0.00 L |
Notes: (a) Inert
C&D materials (public fill) include bricks, concrete, building debris,
rubble and excavated spoil. In total, 1522.82 tonnes
of inert C&D material were generated from the Project, of which 0.00 tonnes
were reused in this Contract and the 1522.82 tonnes
were disposed as public fill to the Fill Bank at Tuen
Mun Area 38. The detailed waste flow is presented
in Annex F. (b) Non-inert
C&D materials (construction wastes) include metals, paper / cardboard
packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were grouped
into construction wastes as the materials were not disposed of with others at
the public fill. (c) 40,000.00
kg of metals, 9300.00 kg of papers/ cardboard packing and 0.00 kg of
plastics were sent to recyclers for recycling during the
reporting period. (d) Construction wastes other than
metals, paper/cardboard packaging, plastics and chemicals were disposed of at
NENT Landfill by subcontractors. |
Joint site inspections were conducted by representatives of the Contractor,
the ER, IC and the ET on 3, 11, 19, 24 and 31 October 2016. The IEC was also
present at the joint inspection on 19 October 2016. Follow-up actions resulting
from the last site inspections were generally taken as reported by the
Contractor, except the setting up of the chemical waste collection area, and
their results were observed in the site inspections conducted in the reporting
period. It is understood that the chemical waste collection area will shortly
be set up properly by the contractor. The progress will be monitored and further
reported in the next monthly EM&A report.
Key observations
during the reporting period are summarised as follows:
3 October 2016
· Chemical containers without drip trays were observed within the AD area and Building 2 area. The
Contractor was reminded to provide drip trays
or remove the used-up chemical containers..
· General refuse without proper bagging and disposal was observed within Building 1 area..
·
Different types of waste
were not segregated and stored in different containers, skips or stockpiles
within Building 1 area. The contractor
was reminded to segregate and store the wastes in different containers to
ensure properly disposal or recycle.
·
Stagnant water was observed
within the AD Tank area and Building 2 area. The contractor was reminded to clean the water
to avoid mosquito breeding.
11 October 2016
· General refuse without proper disposal was observed within Building 1 area and Building 2 area.
· Different types of waste were not segregated in different containers, skips or stockpiles within Building 1 area. The Contractor was
reminded to segregate and store the wastes in different
containers to ensure proper disposal or for recycle.
· The contractor was reminded to provide a cover to the overnight
stockpile to avoid dust emission.
19 October 2016
· General refuse without proper disposal was observed within Building 1 area.
· Chemical waste containers were observed without drip trays within the second access area. The contractor was reminded to provide trip trays for the chemical waste containers.
· Some Chemical waste containers were observed without proper chemical waste label. The
contractor was reminded to ensure
proper chemical waste labels for each chemical waste
containers onsite in accordance with the COP.
· The contractor was reminded to implement sufficient mitigation measures
along the nullah near the wastewater treatment plant as
stipulated in the latest incident report for the non-compliance incident.
· The contractor was reminded to remove the excess water near the main
vehicle entrance to avoid site runoff offsite especially after rainstorm event.
· The contractor was reminded to implement proper sorting onsite for metal
and other C&D wastes.
24 October 2016
·
General
refuse without proper disposal was observed within the Building 1 area. The contractor was reminded to remove the refuse regularly.
·
Stagnant
water was observed in Building 1.
·
The
contractor was reminded to set up the chemical waste collection area properly
according to COP.
·
The
contractor was reminded to provide the tarpaulin or impervious cover to the
overnight stockpile.
·
The
contractor was reminded to implement proper sorting onsite for metal and other
C&D wastes.
31 October 2016
·
Chemical containers without drip tray were observed
within the Building 1 area, Building 2 area and AD tank area. The contractor was reminded to provide drip
trays to the chemical containers or remove the used-up chemical containers.
·
Stagnant
water was observed within the AD tank area.
·
Oil
leakage for equipment maintenance was observed within the main staff entrance. The contractor was reminded to remove the
contaminated sand and provide a drip tray or impervious tarpaulin under the
equipment.
·
The
contractor was reminded to provide tarpaulin or impervious cover to the cement
bag stored in open area within the Building 3 area.
· The contractor was reminded to provide tarpaulin or
impervious cover to the overnight stockpile within the Building 3 area.
In accordance with the EM&A Manual, bi-weekly landscape and
visual inspection is required to
ensure that the design, implementation and maintenance of landscape and visual
mitigation measures recommended in the EIA Report are fully achieved. Onsite inspections of the landscape and
visual mitigation measures were performed on 3, 19and 31 October 2016.
Follow-up actions resulting from the last site inspections were taken as
reported by the Contractor and their results were observed in the site
inspections conducted in the reporting period.
It was confirmed that the necessary landscape and visual mitigation measures as summarised in Annex E were generally implemented by the Contractor. No
specific observation was found during site inspection on 3, 19 and 31 October
2016.
No non-compliance was received during the reporting
period.
The non-compliance event of inappropriate wastewater
discharge identified by EPD during August 2016 had been investigated and the
agreed remedial works and follow-up actions will be completed by the Contractor
shortly, which will be further reported in the next monthly EM&A report. The
Investigation Report is shown in Annex H.
Works to be undertaken for the coming monitoring
period are summarised in Table 8.1.
Table 8.1 Construction
Works to be undertaken in the Next Reporting Period
Construction Activities
Undertaken |
·
Building
1 - superstructure works, defect rectification and ABWF works. ·
Building
2 - ABWF and finishing work, steel work for covered walkway, installation of
pump and pipework at roof, Electrical and BS installation work. ·
Building
3 - ABWF, Electrical and BS installation inside G/F rooms. ·
AD
Tank - Erection of AD 3, cladding work to AD 1, water filling, testing,
scaffolding erection to AD2. ·
Biogas
Holder & Plant Area -erection of De-sulphurisation
tank 1 & 2, carbon filter. ·
Ammonia
Stripping Plant -structural steel and mechanical erection work. ·
CHP
pipework and accessories installation. ·
Mechanical
installation (pre-treatment equipment, grab crane) at Building 1. ·
Mechanical
installation (star screen) and tiles installation inside tunnels at Building
2. ·
Sitewide - Underground drainage and drawpit
work. ·
Portion
2 - temp. traffic arrangement, roadworks. ·
Portion
4 - Material handling and storage, steel bending & cutting. |
Potential environmental impacts arising from the above
construction activities will be mainly associated with dust, construction
noise, site runoffs, waste management and landscaping issues.
The most up-to-date construction programme for the
Project is presented in Annex C.
This EM&A Report presents the EM&A programme undertaken
during the reporting period from 1 October 2016 to 31 October 2016 in
accordance with EM&A Manual and requirements of EP (FEP-01/395/2010/C).
No air quality, noise and water quality monitoring is
required.
Bi-weekly landscape
and visual monitoring was conducted in the reporting period. The necessary landscape and visual mitigation
measures recommended in the EIA Report were generally implemented by the
Contractor.
No non-compliance event was received during reporting
period.
No complaint and summons/prosecution was received
during the reporting period.
The ET will keep track of the EM&A programme to
ensure compliance of environmental requirements and the proper implementation
of all the necessary mitigation measures in the coming periods.