Contents
Executive
Summary
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Construction Activities
2.4 Project Organisation and
Management Structure
2.5 Status of Environmental
Approval Documents
3 Environmental Monitoring Requirement, environmental
Mitigation Measures
4 Implementation Status on Environmental Protection
Requirements
6.1 Weekly Site Audits
6.2 Landscape and Visual Audit
7 Environmental Non-conformance
7.1 Summary of Environmental
Non-Compliance
7.2 Summary of Environmental
Complaint
7.3 Summary of Environmental
Summon and Successful Prosecution
8.1 Key Issues for the Coming
Month
8.2 Construction Programme
LIST OF TABLES
Table 2.1 Summary of Construction Activities
Undertaken in the Reporting Period
Table 2.2 Summary
of Environmental Licensing, Notification and Permit Status
Table 5.1 Quantities
of Waste Generated from the Project
Table 8.1 Construction
Works to be undertaken in the Next Reporting Period
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
|
Annex F |
|
Annex G |
Environmental
complaint, Environmental Summons and Prosecution Log |
|
|
|
|
EXECUTIVE SUMMARY
The construction works of No. EP/SP/61/10 Organic Waste
Treatment Facilities Phase I (the Project) commenced
on 21 May 2015. This is the 21st monthly Environmental Monitoring
and Audit (EM&A) report presenting the EM&A works carried out during
the period from 1 to 28 February 2017 in accordance with the EM&A Manual.
Summary of Construction Works undertaken during the Reporting
Month
Works undertaken in the reporting month included:
·
Building
1 - ABWF and finishing works, steel roof structure, E&M installation.
·
Building
2 – ABWF and finishing work, covered walkway cladding, installation of GRP
ductwork at roof, E&M installation.
·
Building
3 – ABWF, Electrical and BS installation inside rooms at G/F & LR/F.
·
Link
bridge Bondex steel deck.
·
Weighbridge
and control room structure.
·
NTH
mitigation works on slope.
·
AD
Tank –Cladding to AD3. Water drain from AD1 & 2.
·
Pipe
rack and cable rack installation.
·
Ammonia
Stripping Plant –structural steel and mechanical erection work.
·
Mechanical
installation (monorail, decanter and diffuser) at Building 1.
·
Electrical
installation (cable trays installation, B2 MCC panels installation, B3 LV
installation, Cabling work to B2 MCC)
·
Sitewide – Underground drainage and drawpit
work.
·
m. Portion 4 – Material handling and storage,
steel bending & cutting.
Environmental Monitoring and Audit Progress
A summary of the monitoring activities undertaken in
this reporting period is listed below:
·
Joint Environmental Site Inspection |
5 times |
·
Landscape & Visual Monitoring |
2 times |
Waste Management
Waste generated from this Project includes inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction wastes).
Inert C&D materials (public fill) include bricks,
concrete, building debris, rubble and excavated spoil. In total, 553.80 tonnes
of inert C&D material were generated from the Project, of which 440.00 tonnes
were reused in this Contract. The 113.80 tonnes of inert C&D material were
disposed of as public fill to the Fill Banks at Tuen Mun Area 38.
Non-inert C&D materials (construction wastes)
include metals, paper / cardboard packaging waste, plastics and other wastes
such as general refuse. 14,940.00 kg of
metals, 18,820.00 kg of papers/ cardboard packing and 2,880.00 kg of plastics
were sent to recyclers for recycling during the reporting period. 83.46 tonnes of general refuse was disposed of
at the landfill.
460.00 L of chemical waste was collected by licenced
waste collector.
Environmental Site Inspection
Five weekly joint environmental site inspections were
carried out by the representatives of the Contractor, SOR and the Environmental
Team (ET). The IEC was also present at the joint inspection on 15 February 2017. Details of the audit findings and implementation
status of the mitigation measures are presented in Section 6.1.
Landscape & Visual
Onsite inspections on landscape and visual
mitigation measures were performed on 6 and 20 February 2017. Details
of the audit findings and implementation status of the mitigation measures are
presented in Sections 6.2.
Environmental Exceedance/Non-conformance/Compliant/Summons
and Prosecution
No exceedance
was recorded during the reporting period.
No non-compliance
event was received during the reporting period.
No environmental complaint and summon/prosecution was
received in this reporting period.
Future Key Issues
Works to be undertaken in the next reporting month
include:
·
Building
1 - ABWF and finishing works, steel roof and covered walkway structure, E&M
installation.
·
Building
2 – ABWF and finishing work, covered walkway cladding, installation of GRP
ductwork at roof, E&M installation.
·
Building
3 – ABWF, Electrical and BS installation inside rooms at G/F & LR/F.
·
Link
bridge Bondex steel deck and
cladding.
·
Weighbridge
and control room structure.
·
Collection
chamber 1 excavation and construction.
·
NTH
mitigation works on slope.
·
Boundary
fence wall construction.
·
AD
Tank –Cladding to AD3, water drain from AD1 & 2, erect scaffolding, piping
and nozzle inside Tank 2 and piping work.
·
Pipe
rack and cable rack installation.
·
Ammonia
Stripping Plant –mechanical and electrical work.
·
CHP
pipework and accessories installation.
·
Mechanical
equipment installation at Building 1.
·
Mechanical
installation (Centrifuges equipment) at Building 2.
·
Electrical
installation (cable trays installation, MCC panels installation, B3 LV
installation, energization of Main LV Switch Board and cabling work to MCC
Rooms)
·
Sitewide – Underground drainage and drawpit
work.
·
Portion
4 – Material handling and storage.
Environmental impacts arising from the above
construction activities are mainly associated with dust, construction noise,
site runoffs, waste management and landscaping issues.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR
Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to
undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I
(the Project).
This is the 21st EM&A report which summarises
the monitoring results and audit findings for the EM&A programme during the
reporting period from 1 to 28 February 2017.
The structure of the report is as follows:
Section 1: Introduction
It details the
scope and structure of the report.
Section 2: Project
Information
It summarises the background and scope of the Project, site description,
project organization, construction programme, construction works undertaken and
status of the Environmental Permits (EP)/licences over the construction phase
of the Project.
Section 3: Environmental Monitoring Requirements
It
summarises the environmental monitoring requirements including monitoring
parameters, programmes, methodologies, frequency, locations, Action and Limit
Levels, Event/Action Plans, environmental mitigation measures as recommended in
the EM&A Manual and approved EIA report.
Section 4: Implementation
Status on Environmental Mitigation Measures
It
summarises the implementation of environmental protection measures during the
reporting period.
Section 5: Waste
Management
It
summarises the quantity of public fill and construction waste generated in the
reporting period
Section 6: Environmental
Site Inspection
It
summarises the audit findings of the weekly site inspections undertaken within
the reporting period.
Section 7: Environmental
Non-conformance
It
summarises any exceedance of environmental performance standard, environmental
complaints and summons received within the reporting period.
Section
8: Further Key Issues
It
summarises the impact forecast and monitoring schedule for the next reporting
month.
Section
9: Conclusions
The
Organic Waste Treatment Facilities (OWTF) Phase I development (hereinafter
referred to as “the Project”) is to design, construct and operate a biological
treatment facility with a capacity of about 200 tonnes per day and convert
source-separated organic waste from commercial and industrial sectors (mostly
food waste) into compost and biogas through proven biological treatment
technologies.
The environmental acceptability of the construction and operation
of the Project had been confirmed by findings of the associated Environmental
Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection
approved this EIA Report under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010)
(hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on
Environmental Implications and Report on Re-assessment on Hazard to Life
Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010)
was issued by the Environmental Protection Department (EPD) to the EPD, the
Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A)
and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the
OWTF (Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the
Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited
and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint Venture
(OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was
issued by the EPD to the OSCAR on 16 February 2015. Variation to both EPs No.
EP-395/2010/B and No. FEP-01/395/2010/B were made in December 2015.
The latest EPs, No. EP-395/2010/C and No.
FEP-01/395/2010/C, were issued by the EPD on 21 December 2015.
Under the requirements of Condition 5 of the EP (No.
FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme
as set out in the Agreement No. CE7/2008 (EP) EM&A Manual (hereinafter
referred to as EM&A Manual) is required to be implemented. ERM-Hong Kong, Ltd (ERM) has been appointed
by OSCAR as the Environmental Team (ET) to undertake the EM&A programme for the Contract.
The construction works commenced on 21 May 2015 and
are scheduled for completion by April 2017.
The
Project Site is located at Siu Ho Wan in North
Lantau with an area of about 2 hectares. The layout of the Project Site is illustrated
in Annex
A.
A summary of the major construction
activities undertaken in the reporting period is shown in Table 2.1.
The locations of the construction activities are shown in Annex
B. The
construction programme of the Project is presented in Annex
C.
Table 2.1 Summary of Construction Activities
Undertaken in the Reporting Period
Construction Activities
Undertaken |
·
Building 1 - ABWF and finishing
works, steel roof structure, E&M installation. ·
Building 2 – ABWF and finishing
work, covered walkway cladding, installation of GRP ductwork at roof, E&M
installation. ·
Building 3 – ABWF, Electrical and
BS installation inside rooms at G/F & LR/F. ·
Link bridge
Bondex steel deck. ·
Weighbridge and control room
structure. ·
NTH mitigation works on slope. ·
AD Tank –Cladding to AD3. Water
drain from AD1 & 2. ·
Pipe rack and cable rack
installation. ·
Ammonia Stripping Plant
–structural steel and mechanical erection work. ·
Mechanical installation (monorail,
decanter and diffuser) at Building 1. ·
Electrical installation (cable
trays installation, B2 MCC panels installation, B3 LV installation and cabling
work to B2 MCC) ·
Sitewide –
Underground drainage and drawpit work. ·
Portion 4 – Material handling and
storage, steel bending & cutting. |
The project organisation chart and contact details are
shown in Annex D.
A summary of the valid permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary of Environmental Licensing,
Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December
2015 |
Notification of Construction
Works under the Air Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00021482-2015 |
21 May 2015 – 31 May 2020 |
Approved on 21 May 2015 |
Construction Noise Permit –
P1&P2 |
GW-RW0678-16 |
12 December
2016 – 11 June 2017 |
Approved
on 2 December 2016 |
Construction Noise Permit – P3 |
GW-RW0628-16 |
1 December
2016 – 31 May 2017 |
Approved
on 8 November 2016 |
Chemical Waste Producer
Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
All
the relevant environmental mitigation measures listed in the EIA Report and
EM&A Manual are summarised in Annex E.
According to the EM&A Manual and EP requirement,
no air quality, noise and water quality monitoring is required.
Bi-weekly landscape and visual audit is required to ensure that the design,
implementation and maintenance of landscape and visual mitigation measures
recommended in the EIA Report are fully achieved.
The Contractor has implemented environmental
mitigation measures and requirements as stated in the approved EIA Report and
EM&A Manual. The implementation
status of the measures during the reporting period is summarised in Annex
E.
Wastes generated from this Project include inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction waste). Construction
waste comprises general refuse, metals and paper/cardboard packaging
materials. Metals generated from the Project
are also grouped into construction waste as the materials were not disposed of
with others at public fill. Reference
has been made to the Monthly Summary Waste Flow Table prepared by the
Contractor (see Annex F). With reference to the relevant handling
records and trip tickets of this Project, the quantities of different types of
waste generated in the reporting month are summarised in Table 5.1.
Table 5.1 Quantities
of Waste Generated from the Project
Month / Year |
Quantity |
|||
|
Total Inert C&D Materials Generated (a) |
Non-inert C&D Materials (b) |
||
C&D Materials Recycled (c) |
C&D Waste Disposed of at Landfill (d) |
Chemical Waste |
||
February 2017 |
553.80 tonnes |
36,640.00 kg |
83.46 tonnes |
460.00 L |
Notes: (a) Inert
C&D materials (public fill) include bricks, concrete, building debris,
rubble and excavated spoil. In total, 553.80 tonnes
of inert C&D material were generated from the Project, of which 440.00 tonnes
were reused in this Contract and the 113.80 tonnes
were disposed as public fill to the Fill Bank at Tuen
Mun Area 38. The detailed waste flow is presented in Annex F. (b) Non-inert
C&D materials (construction wastes) include metals, paper / cardboard
packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were grouped
into construction wastes as the materials were not disposed of with others at
the public fill. (c) 14,940.00
kg of metals, 18,820.00 kg of papers/ cardboard packing and 2,880.00 kg of
plastics were sent to recyclers for recycling during the
reporting period. (d) Construction wastes other than
metals, paper/cardboard packaging, plastics and chemicals were disposed of at
NENT Landfill by subcontractors. |
Joint site inspections were conducted by representatives of the
Contractor, the ER, IC and the ET on 1, 6, 15, 20 and 27 February 2017. The IEC was also
present at the joint inspection on 15 February 2017. Follow-up actions resulting
from the last site inspections were generally taken as reported by the
Contractor.
Key observations
during the reporting period are summarised as follows:
1 February 2017
· No particular observation
during this site inspection..
6 February 2017
· No particular observation during this site inspection.
15 February 2017
· Oil stain was observed on the ground near AD tank area and the
contractor was reminded to clean the oil stain and dispose of as chemical waste.
· Chemical containers without trip tray were observed near first vehicle
access and the contractor was reminded to provide drip tray to avoid chemical
spillage.
· Chemical waste was observed being placed at Building 2 and near the
chemical storage tank and the contractor was reminded to put all the chemical
waste in proper chemical waste storage area according to the Code of Practice.
· General refuse was observed not stored in enclosed bins or compaction
units on Building 2 roof and the contractor was reminded to remove the refuse.
· The contractor was reminded to enhance the protection measures along the
nullah to prevent any sandy material or construction
material entering it.
20 February 2017
·
General
refuse was observed not stored in enclosed bins or compaction units in building
one and the contractor was reminded to remove the general refuse in enclosed
bins or compaction units.
·
Chemical
waste was observed being placed near Building 2 and the contractor was reminded
to put all the chemical waste in proper chemical waste storage area according
to the Code of Practice.
27 February 2017
· Oil stain was observed on
the ground near Building 2 area and the contractor was reminded to clean the
oil stain and dispose of as chemical waste.
· Chemical containers without
trip tray were observed in Building 2 and the contractor was reminded to
provide drip tray to avoid chemical spillage.
· Chemical waste was observed
placed near Building 2 and the contractor was reminded to put all the chemical
waste in proper chemical waste storage area according to the Code of Practice.
· Stagnant water was observed
on Building 2 roof and the contractor was reminded to clear the water.
In accordance with the EM&A Manual, bi-weekly landscape and
visual inspection is required to
ensure that the design, implementation and maintenance of landscape and visual
mitigation measures recommended in the EIA Report are fully achieved. Onsite inspections of the landscape and visual
mitigation measures were performed on 6 and 20 February 2017.
It was confirmed that the necessary landscape and visual mitigation measures as summarised in Annex
E were generally implemented by the Contractor. No
specific observation was found during site inspection on 6 and 20 February 2017.
No non-compliance was received during the reporting
period.
No complaint was received during the reporting
period. The cumulative environmental
complaint log is shown in Annex G.
No summon/prosecution was received during the
reporting period. The cumulative
summons/prosecution log is shown in Annex G.
Works to be undertaken for the coming monitoring
period are summarised in Table 8.1.
Table 8.1 Construction
Works to be undertaken in the Next Reporting Period
Construction Activities
Undertaken |
·
Building
1 - ABWF and finishing works, steel roof and covered walkway structure,
E&M installation. ·
Building
2 – ABWF and finishing work, covered walkway cladding, installation of GRP
ductwork at roof, E&M installation. ·
Building
3 – ABWF, Electrical and BS installation inside rooms at G/F & LR/F. ·
Link
bridge Bondex steel deck
and cladding. ·
Weighbridge
and control room structure. ·
Collection
chamber 1 excavation and construction. ·
NTH
mitigation works on slope. ·
Boundary
fence wall construction. ·
AD
Tank –Cladding to AD3, water drain from AD1 & 2, erect scaffolding,
piping and nozzle inside Tank 2 and piping work ·
Pipe
rack and cable rack installation. ·
Ammonia
Stripping Plant –mechanical and electrical work. ·
CHP
pipework and accessories installation. ·
Mechanical
equipment installation at Building 1. ·
Mechanical
installation (Centrifuges equipment) at Building 2. ·
Electrical
installation (cable trays installation, MCC panels installation, B3 LV
installation, energization of Main LV Switch Board and Cabling work to MCC
Rooms) ·
Sitewide – Underground drainage and drawpit
work. ·
Portion
4 – Material handling and storage. |
Potential environmental impacts arising from the above
construction activities will be mainly associated with dust, construction
noise, site runoffs, waste management and landscaping issues.
The most up-to-date construction programme for the
Project is presented in Annex C.
This EM&A Report presents the EM&A programme undertaken
during the reporting period from 1 to 28 February 2017 in accordance with
EM&A Manual and requirements of EP (FEP-01/395/2010/C).
No air quality, noise and water quality monitoring is
required.
Bi-weekly landscape
and visual monitoring was conducted in the reporting period. The necessary landscape and visual mitigation
measures recommended in the EIA Report were generally implemented by the
Contractor.
No non-compliance event was received during reporting
period.
No complaint and summons/prosecution was received
during the reporting period.
The ET will keep track of the EM&A programme to
ensure compliance of environmental requirements and the proper implementation
of all the necessary mitigation measures in the coming periods.