1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Construction Activities
2.4 Project Organisation and Management Structure
2.5 Status of Environmental Approval Documents
3 Environmental Monitoring Requirement, environmental
Mitigation Measures
4 Implementation Status on Environmental Protection
Requirements
6.1 Weekly Site Audits
6.2 Landscape and Visual Audit
7 Environmental Non-conformance
7.1 Summary of Environmental Non-Compliance
7.2 Summary of Environmental Complaint
7.3 Summary of Environmental Summon and Successful
Prosecution
8.1 Key Issues for the Coming Month
8.2 Construction Programme
LIST OF TABLES
Table 2.1 Summary
of Construction Activities Undertaken in the Reporting Period
Table
2.2 Summary of Environmental
Licensing, Notification and Permit Status
Table
5.1 Quantities of Waste Generated from
the Project
Table
8.1 Construction Works to be
undertaken in the Next Reporting Period
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
|
Annex F |
|
Annex G |
Environmental complaint,
Environmental Summons and Prosecution Log |
|
|
|
|
EXECUTIVE SUMMARY
The construction works of No. EP/SP/61/10 Organic Waste
Treatment Facilities Phase I (the Project) commenced
on 21 May 2015. This is the 22nd monthly Environmental Monitoring
and Audit (EM&A) report presenting the EM&A works carried out during the
period from 1 to 31 March 2017 in accordance with the EM&A Manual.
Summary of Construction Works undertaken during the
Reporting Month
Works undertaken in the reporting month included:
·
Building
1 - ABWF and finishing works, steel roof and covered walkway structure, E&M
installation.
·
Building
2 – ABWF and finishing work, covered walkway cladding, installation of GRP
ductwork at roof, E&M installation.
·
Building
3 – ABWF, Electrical and BS installation inside rooms at G/F & LR/F.
·
Link
bridge Bondex steel deck.
·
Weighbridge
and control room structure.
·
Collection
chamber 1 excavation.
·
NTH
mitigation works on slope.
·
AD
Tank –Cladding to AD3. Water drain from AD1. Erect external access
platform. Piping work
·
Pipe
rack and cable rack installation.
·
Ammonia
Stripping Plant –mechanical work.
·
CHP
pipework and accessories installation.
·
Electrical
installation (cable trays, MCC panels installation, B3 LV installation,
Energization of Main LV Switch Board, Cabling work to MCC Rooms)
·
Sitewide – Underground drainage and catchpit
work.
·
Portion
4 – Material handling and storage.
Environmental Monitoring and Audit Progress
A summary of the monitoring activities undertaken in
this reporting period is listed below:
·
Joint Environmental Site Inspection |
4 times |
·
Landscape & Visual Monitoring |
2 times |
Waste Management
Waste generated from this Project includes inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction wastes).
Inert C&D materials (public fill) include bricks,
concrete, building debris, rubble and excavated spoil. In total, 665.93 tonnes
of inert C&D material were generated from the Project, of which 460.00
tonnes were reused in this Contract. The 205.93 tonnes of inert C&D
material were disposed of as public fill to the Fill Banks at Tuen Mun Area 38.
Non-inert C&D materials (construction wastes)
include metals, paper / cardboard packaging waste, plastics and other wastes
such as general refuse. 11,660.00 kg of
metals, 29,370.00 kg of papers/ cardboard packing and 4,400.00 kg of plastics
were sent to recyclers for recycling during the reporting period. 99.59 tonnes of general refuse was disposed
of at the landfill.
660.00 L of chemical waste was collected by licenced
waste collector.
Environmental Site Inspection
Four weekly joint environmental site inspections were
carried out by the representatives of the Contractor, SOR and the Environmental
Team (ET). The IEC was also present at the joint inspection on 15 March 2017. Details of the audit findings and implementation
status of the mitigation measures are presented in Section 6.1.
Landscape & Visual
Onsite inspections on landscape and visual mitigation
measures were performed on 6 and 20 March 2017.
Details of the audit findings and implementation status of the mitigation
measures are presented in Sections 6.2.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance
was recorded during the reporting period.
No
non-compliance event was received during the reporting period.
No environmental complaint and summon/prosecution was
received in this reporting period.
Future Key Issues
Works to be undertaken in the next reporting month
include:
·
Building
1 - ABWF and finishing works, steel roof and covered walkway cladding, E&M
& BS installation.
·
Building
2 – ABWF and finishing work, installation of GRP ductwork at roof, E&M
& BS installation.
·
Building
3 – ABWF and finishing work, Electrical and BS installation.
·
Link
bridge cladding.
·
Weighbridge
and control room structure, guard house and water meter cabinet structure.
·
Collection
chamber 1 construction.
·
NTH
mitigation works on slope.
·
AD
Tank – Erect scaffolding, piping and nozzle inside Tank 2. Piping work
·
Biogas
holder installation.
·
Pipe
rack and cable rack installation.
·
Ammonia
Stripping Plant –mechanical and electrical work.
·
Electrical
installation (cable trays, MCC panels installation, B3 LV installation,
Energization of Building 2 MCC rooms, Cabling work to Building 1 MCC Rooms)
·
Sitewide – Underground drainage and catchpit
work, water pipe, boundary fence wall construction.
·
Portion
4 – Material handling and storage.
·
Start
dry commissioning of star screen unit.
Environmental impacts arising from the above
construction activities are mainly associated with dust, construction noise,
site runoffs, waste management and landscaping issues.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR
Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to
undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I
(the Project).
This is the 22nd EM&A report which
summarises the monitoring results and audit findings for the EM&A programme
during the reporting period from 1 to 31 March 2017.
The structure of the report is as follows:
Section 1: Introduction
It
details the scope and structure of the report.
Section
2: Project Information
It
summarises the background and scope of the Project, site description, project
organization, construction programme, construction works undertaken and status
of the Environmental Permits (EP)/licences over the construction phase of the
Project.
Section
3: Environmental Monitoring
Requirements
It
summarises the environmental monitoring requirements including monitoring
parameters, programmes, methodologies, frequency, locations, Action and Limit
Levels, Event/Action Plans, environmental mitigation measures as recommended in
the EM&A Manual and approved EIA report.
Section
4: Implementation Status on Environmental Mitigation Measures
It
summarises the implementation of environmental protection measures during the
reporting period.
Section
5: Waste Management
It
summarises the quantity of public fill and construction waste generated in the
reporting period
Section
6: Environmental Site Inspection
It
summarises the audit findings of the weekly site inspections undertaken within
the reporting period.
Section
7: Environmental Non-conformance
It
summarises any exceedance of environmental performance standard, environmental
complaints and summons received within the reporting period.
Section
8: Further Key Issues
It
summarises the impact forecast and monitoring schedule for the next reporting
month.
Section
9: Conclusions
The
Organic Waste Treatment Facilities (OWTF) Phase I development (hereinafter
referred to as “the Project”) is to design, construct and operate a biological
treatment facility with a capacity of about 200 tonnes per day and convert
source-separated organic waste from commercial and industrial sectors (mostly
food waste) into compost and biogas through proven biological treatment
technologies.
The environmental acceptability of the construction and operation
of the Project had been confirmed by findings of the associated Environmental
Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection
approved this EIA Report under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010)
(hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on
Environmental Implications and Report on Re-assessment on Hazard to Life
Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010)
was issued by the Environmental Protection Department (EPD) to the EPD, the
Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A)
and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the
OWTF (Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the
Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited
and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint
Venture (OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was
issued by the EPD to the OSCAR on 16 February 2015. Variation to both EPs No.
EP-395/2010/B and No. FEP-01/395/2010/B were made in December 2015.
The latest EPs, No. EP-395/2010/C and No.
FEP-01/395/2010/C, were issued by the EPD on 21 December 2015.
Under the requirements of Condition 5 of the EP (No.
FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme
as set out in the Agreement No. CE7/2008 (EP) EM&A Manual (hereinafter
referred to as EM&A Manual) is required to be implemented. ERM-Hong Kong, Ltd (ERM) has been appointed
by OSCAR as the Environmental Team (ET) to undertake the EM&A programme for the Contract.
The construction works commenced on 21 May 2015 and
are scheduled for completion by April 2017.
The
Project Site is located at Siu Ho Wan in North Lantau with an area of about 2
hectares. The layout of
the Project Site is illustrated in Annex A.
A summary of the major
construction activities undertaken in the reporting period is shown in Table 2.1. The locations of the construction activities
are shown in Annex B.
The construction programme of the Project is presented in Annex
C.
Table 2.1 Summary
of Construction Activities Undertaken in the Reporting Period
Construction Activities
Undertaken |
·
Building 1 - ABWF and finishing
works, steel roof and covered walkway structure, E&M installation. ·
Building 2 – ABWF and finishing
work, covered walkway cladding, installation of GRP ductwork at roof, E&M
installation. ·
Building 3 – ABWF, Electrical and
BS installation inside rooms at G/F & LR/F. ·
Link bridge
Bondex steel deck. ·
Weighbridge and control room
structure. ·
Collection chamber 1 excavation. ·
NTH mitigation works on slope. ·
AD Tank –Cladding to AD3. Water
drain from AD1. Erect external access platform. Piping work ·
Pipe rack and cable rack installation. ·
Ammonia Stripping Plant
–mechanical work. ·
CHP pipework and accessories
installation. ·
Electrical installation (cable
trays, MCC panels installation, B3 LV installation, Energization of Main LV
Switch Board, Cabling work to MCC Rooms) ·
Sitewide –
Underground drainage and catchpit work. ·
Portion 4 – Material handling and
storage. |
The project organisation chart and contact details are
shown in Annex D.
A summary of the valid permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary
of Environmental Licensing, Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December
2015 |
Notification of Construction
Works under the Air Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00021482-2015 |
21 May 2015 – 31 May 2020 |
Approved on 21 May 2015 |
Construction Noise Permit –
P1&P2 |
GW-RW0678-16 |
12
December 2016 – 11 June 2017 |
Approved
on 2 December 2016 |
Construction Noise Permit – P3 |
GW-RW0628-16 |
1
December 2016 – 31 May 2017 |
Approved
on 8 November 2016 |
Chemical Waste Producer
Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
All
the relevant environmental mitigation measures listed in the EIA Report and
EM&A Manual are summarised in Annex E.
According to the EM&A Manual and EP requirement,
no air quality, noise and water quality monitoring is required.
Bi-weekly landscape and visual audit is required to ensure that the design,
implementation and maintenance of landscape and visual mitigation measures
recommended in the EIA Report are fully achieved.
The Contractor has implemented environmental
mitigation measures and requirements as stated in the approved EIA Report and
EM&A Manual. The implementation
status of the measures during the reporting period is summarised in Annex
E.
Wastes generated from this Project include inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction waste).
Construction waste comprises general refuse, metals and paper/cardboard
packaging materials. Metals generated
from the Project are also grouped into construction waste as the materials were
not disposed of with others at public fill.
Reference has been made to the Monthly Summary Waste Flow Table prepared
by the Contractor (see Annex F). With reference to the relevant handling
records and trip tickets of this Project, the quantities of different types of
waste generated in the reporting month are summarised in Table 5.1.
Table 5.1 Quantities of Waste Generated from the
Project
Month / Year |
Quantity |
|||
|
Total Inert C&D Materials Generated (a) |
Non-inert C&D Materials (b) |
||
C&D Materials Recycled (c) |
C&D Waste Disposed of at Landfill (d) |
Chemical Waste |
||
March 2017 |
665.93 tonnes |
45,430.00 kg |
99.59 tonnes |
660.00 L |
Notes: (a) Inert
C&D materials (public fill) include bricks, concrete, building debris,
rubble and excavated spoil. In total, 665.93 tonnes
of inert C&D material were generated from the Project, of which 460.00
tonnes were reused in this Contract and the 205.93 tonnes
were disposed as public fill to the Fill Bank at Tuen
Mun Area 38.
The detailed waste flow is presented in Annex F. (b) Non-inert
C&D materials (construction wastes) include metals, paper / cardboard
packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were
grouped into construction wastes as the materials were not disposed of with
others at the public fill. (c) 11,660.00
kg of metals, 29,370.00 kg of papers/ cardboard packing and 4,400.00 kg of
plastics were sent to recyclers for recycling during the
reporting period. (d) Construction wastes other than
metals, paper/cardboard packaging, plastics and chemicals were disposed of at
NENT Landfill by subcontractors. |
Joint site
inspections were conducted by representatives of the Contractor, the ER, IC and
the ET on 6, 15, 20 and 27 March 2017. The IEC was also present at the joint inspection on 15 March 2017.
Follow-up actions resulting from the last site inspections were
generally taken as reported by the Contractor.
Key observations
during the reporting period are summarised as follows:
6 March 2017
· Chemical containers without
trip tray were observed in pipe gallery and the contractor was reminded to
provide drip tray to avoid chemical spillage.
· Chemical waste was observed being placed in Building 1 and near staff
entrance and the contractor was reminded to put all the chemical wastes in proper
chemical waste storage area according to the Code of Practice
15 March 2017
· Open stockpiles were observed not covered by impervious cover near
Building 3 and Building 2 and the contractor was reminded to cover the
stockpiles properly.
· Chemical spillage was observed near the AD tank area and the contractor
was reminded to remove the contaminated land with chemicals and ensure good
maintenance of vehicles and equipment to avoid spillage.
· Chemicals without drip tray were observed in Building 1 and the
contractor was reminded to provide the drip tray to avoid chemical spillage.
· Unsorted general refuse not stored in enclosed bins was observed near
Building 1 and the contractor was reminded to remove the refuse regularly and
provide proper sorting.
· The contractor was reminded to provide impervious cover to more than 20
bags of cement bags to avoid dust emission.
20 March 2017
· Cement mixer without three-side enclosure and top covering was observed
on Building 1 roof and the contractor was reminded to provide the three-side
enclosure and the top covering to avoid dust emission.
· Chemicals without drip tray were observed in
Building 1 and on Building 1 roof and the contractor was reminded to provide the drip tray to avoid chemical spillage.
· Unsorted general refuse not stored in enclosed bins was observed in
Building 1 and the contractor was reminded to remove the refuse regularly and
provide proper sorting.
· Stagnant water was observed in Building 1 and the contractor was
reminded to remove the stagnant water.
· The contractor was further reminded to provide impervious cover to more
than 20 bags of cement bags to avoid dust emission.
27 March 2017
· Chemical containers without
drip tray were observed in Building 1 and the contractor was reminded to provide
the drip tray to avoid chemical spillage.
· General refuse in the
broken water horse was observed near AD rank area and the contractor was
reminded to remove the refuse regularly and change the broken water horse.
· The contractor was reminded
to remove the stagnant water within the site to prevent mosquito breeding.
In
accordance with the EM&A Manual, bi-weekly landscape and visual inspection is required to ensure that the
design, implementation and maintenance of landscape and visual mitigation
measures recommended in the EIA Report are fully achieved. Onsite inspections of the landscape and
visual mitigation measures were performed on 6 and 20 March 2017.
It was confirmed that the necessary landscape and visual mitigation measures as summarised in Annex
E were generally implemented by the Contractor. No specific observation was found during
site inspection on 6 and 20 March 2017.
No non-compliance was received during the reporting
period.
No complaint was received during the reporting
period. The cumulative environmental
complaint log is shown in Annex G.
No summon/prosecution was received during the
reporting period. The cumulative
summons/prosecution log is shown in Annex G.
Works to be undertaken for the coming monitoring
period are summarised in Table 8.1.
Table 8.1 Construction Works to be undertaken in
the Next Reporting Period
Construction Activities
Undertaken |
·
Building
1 - ABWF and finishing works, steel roof and covered walkway cladding,
E&M & BS installation. ·
Building
2 – ABWF and finishing work, installation of GRP ductwork at roof, E&M
& BS installation. ·
Building
3 – ABWF and finishing work, Electrical and BS installation. ·
Link
bridge cladding. ·
Weighbridge
and control room structure, guard house and water meter cabinet structure. ·
Collection
chamber 1 construction. ·
NTH
mitigation works on slope. ·
AD
Tank – Erect scaffolding, piping and nozzle inside Tank 2. Piping work ·
Biogas
holder installation. ·
Pipe
rack and cable rack installation. ·
Ammonia
Stripping Plant –mechanical and electrical work. ·
Electrical
installation (cable trays, MCC panels installation, B3 LV installation,
Energization of Building 2 MCC rooms, Cabling work to Building 1 MCC Rooms) ·
Sitewide – Underground drainage and catchpit
work, water pipe, boundary fence wall construction. ·
Portion
4 – Material handling and storage. ·
Start
dry commissioning of star screen unit. |
Potential environmental impacts arising from the above
construction activities will be mainly associated with dust, construction
noise, site runoffs, waste management and landscaping issues.
The most up-to-date construction programme for the
Project is presented in Annex C.
This EM&A Report presents the EM&A programme
undertaken during the reporting period from 1 to 31 March 2017 in accordance
with EM&A Manual and requirements of EP (FEP-01/395/2010/C).
No air quality, noise and water quality monitoring is
required.
Bi-weekly landscape
and visual monitoring was conducted in the reporting period. The necessary landscape and visual mitigation
measures recommended in the EIA Report were generally implemented by the
Contractor.
No non-compliance event was received during reporting
period.
No complaint and summons/prosecution was received
during the reporting period.
The ET will keep track of the EM&A programme to
ensure compliance of environmental requirements and the proper implementation
of all the necessary mitigation measures in the coming periods.