Contents
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Major Activities Undertaken
2.4 Project Organisation and
Management Structure
2.5 Status of Environmental
Approval Documents
3 Environmental Monitoring and Audit Requirements
3.1 Environmental Monitoring
3.1.1 Air Quality
3.1.2 Odour
3.2 Site Audit
3.2.1 Water Quality
3.2.2 Landscape and
Visual
4.1 Air Quality
4.1.1 Operation Phase
Monitoring
4.2 Odour
4.2.1 Operation Phase
Monitoring
4.3 Water Quality
4.3.1 Operation Phase
Monitoring
4.4 Waste Management
4.4.1 Operation Phase
Monitoring
5.1 Environmental Site Audit
5.1.1 Operation Phase
5.2 Landscape and Visual Audit
6 Environmental Non-conformance
6.1 Summary of Environmental
Non-Compliance
6.2 Summary of Environmental
Complaint
6.3 Summary of Environmental
Summon and Successful Prosecution
7.1 Key Issues for the Coming
Reporting Period
LIST OF TABLES
Table 2.1 Summary of
Activities Undertaken in the Reporting Period
Table 2.2 Summary of
Environmental Licensing, Notification and Permit Status
Table 3.1 Sampling and
Laboratory Analysis Methodology
Table 3.2 Emission Limit
for CAPCS Stack
Table 3.3 Emission Limit
for CHP Stack
Table 3.4 Emission Limit
for ASP Stack
Table 3.5 Emission Limit
for Standby Flaring Gas Unit ()
Table 3.6 Odour Intensity
Level
Table 3.7 Action and Limit
Levels for Odour Nuisance
Table 3.8 Event and Action
Plan for Odour Monitoring
Table 4.1 Hourly Average
of Parameters Recorded for CAPCS
Table 4.2 Hourly Average
of Parameters Recorded for CHP 1
Table 4.3 Hourly Average
of Parameters Recorded for CHP 2
Table 4.4 Hourly Average
of Parameters Recorded for CHP 3
Table 4.5 Hourly Average
of Parameters Recorded for ASP
Table 4.6 Hourly Average
of Parameters Recorded for the Standby Flaring Gas Unit
Table 4.8 Results of the
Discharge Sample Collected from the Effluent Storage Tank in October 2022
Table 4.9 Results of the
Discharge Sample Collected from the Effluent Storage Tank in November 2022
Table 4.10 Results of the Discharge
Sample from the Petrol Interceptor 1 on 19 October 2022
Table
4.11 Results of the Discharge
Sample from the Petrol Interceptor 2 on 1 September 2022
Table
4.12 Results of the Discharge
Sample from the Petrol Interceptor 2 on 19 October 2022
Table 4.13 Quantities of
Waste Generated from the Operation of the Project
Table 8.1 Exceedances
for Stack Emissions
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
Environmental complaint, Environmental Summons and
Prosecution Log |
Annex F |
|
Annex G |
The construction works of No. EP/SP/61/10
Organic Resources Recovery Centre Phase 1 (the Project) commenced on 21 May 2015. This is the 30th Quarterly
Environmental Monitoring and Audit (EM&A) Report presenting the EM&A
works carried out during the period from 1 September 2022 to 30 November 2022 in
accordance with the EM&A Manual.
Substantial completion of the construction works was confirmed on 3
December 2018. In the meantime, the
operation phase EM&A programme had commenced in March 2019. Substantial Completion in respect of
substantial part of the Works was confirmed on 24 February 2020. The construction phase EM&A programme was
completed in the end of February 2020.
Summary of Works
undertaken during the Reporting Period
Works undertaken in the reporting period included:
·
Operation of the Project,
including organic waste reception, and operation of the pre-treatment
facilities, anaerobic digesters, composting facilities, air pollution control
systems, on-line emission monitoring system for the Centralised Air Pollution
Control Unit (CAPCS), Co-generation Units (CHP)s and Ammonia Stripping Plant
(ASP), and the wastewater treatment plant;
·
E50 Service for CHP 2
(overhaul works) was completed with testing and commissioning;
·
Emergency repair works for the
ECU (heat exchanger) for the ASP was conducted;
·
Four points calibration and
adjustment was conducted for the CEMS;
·
Steam Generator tube bundle
replacement and ECU cassette replacement were completed;
·
The VOC sensor for CAPCS was installed
in this reporting period, while further modification is still recommended;
·
Biogas booster replacement was
conducted; and
·
Setting adjustments of the CHP 2 engine were conducted
to fine tune and return the maximum loading of the engine to 1,500 kW.
Environmental
Monitoring and Audit Progress
Air Quality
Monitoring
Exceedances on NOx, SO2 and HCl from
CHPs and NOx, and NH3 from ASP were recorded on the
on-line monitoring system
from
September 2022 to November 2022. It should be noted that
measurements recorded under abnormal operating conditions, e.g.
start up and stopping of stacks, unstable operation, test runs and interference
of sensor, are disregarded.
The exceedances of SO2
from CHPs occurred due to tripping of the de-sulphurisation system caused by
the failure of one of the columns of the system. The exceedances of NOx from
CHPs occurred due to insufficient feedstock and system unstability.
The exceedance of HCl from CHP 2 occurred due to system instability caused by
the ongoing performance optimisation of the CHP 2, resulting in a lowered
temperature of the system and the incomplete combustion of biogas. The exceedance of NH3 and NOx from ASP
occurred due to system instability caused by the ongoing performance optimisation of the ASP, resulting in a lowered temperature
of the system and the incomplete combustion of biogas.
The
Contractor has implemented mitigation measures to control the exceedance (including
replacement of malfunctioned parts (desulphurisation system, columns of the
ASP), cleaning for various parts (i.e. heat exchangers of all CHPs, stripping column and packaging of the ASP), and
carried out fine-tuning of equipment of the ASP).
The Contractor is
recommended to closely monitor the processes of the modification of the ASP and
the post-modification monitoring of emission level to avoid any exceedance. As similar
issues have been re-occurred for sometimes, the Contractor is advised to
undertake a comprehensive review of the operation of the concerned systems and
the effectiveness of the existing mitigation measures and proposed further
measures to avoid the exceedance.
Odour patrols were conducted by the independent odour
patrol team of ALS Technichem (HK) Pty Ltd on 9 and
22 September 2022. Level 2 Odour Intensity was not recorded during odour
patrols.
No non-compliance to the effluent discharge limit
stipulated in the discharge license issued by the EPD under the Water Pollution
Control Ordinance was recorded during this reporting period.
Waste generated from the operation of the Project
includes chemical waste, waste generated from pre-treatment process and general
refuse.
0 L of chemical waste was collected by licenced waste
collector from the operation of the Project.
1,678.17 tonnes of waste generated from pre-treatment
process from the operation of the Project was disposed of at landfill. Among the recyclable waste generated from
pre-treatment process from the operation of the Project, 0 tonnes of metals, 0
tonnes of papers/ cardboard packing and 0 tonnes of plastics were sent to
recyclers for recycling during the reporting period.
Around 8.18 tonnes of general refuse from the
operation of the Project was disposed of at
landfill. Among the recycled general
refuse from the operation of the Project, 0.020 tonnes of metals, 0.035 tonnes of
papers/ cardboard packing and 0.020 tonnes of plastics were sent to recyclers
for recycling during the reporting period.
Findings of
Environmental Site Audit
A summary of the
monitoring activities undertaken in this reporting period is listed below:
·
Joint
Environmental Site Inspections |
3
times |
Monthly joint
environmental site inspections were carried out. The environmental control/ mitigation measures
(related to air quality, water quality, waste (including land contamination
prevention), hazard-to-life and landscape and visual) recommended in the
approved EIA Report and the EM&A Manual were properly implemented by the
Contractor during the reporting period.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
Exceedances for
the air emission limits for the CHPs and ASP stacks were recorded during the
reporting period.
No complaint/ summon/prosecution was received in this
reporting period.
Future Key
Issues
Activities to be undertaken in the next reporting period
include:
·
Operation
of the Project;
·
Additional
setting adjustments of CHP2; and
·
Further
testing in preparation of the Biogas Holder replacement works.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR
Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to
undertake the construction Environmental Monitoring and Audit (EM&A)
programme for the Contract No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I,
which the project name has been updated to Organic Resources Recovery
Centre (Phase I) (the Project) since November
2017. ERM was also appointed by the Contractor to undertake
the operation EM&A programme starting 1 March 2019.
This is the 30th Quarterly EM&A report
which summarises the monitoring results and audit findings for the EM&A
programme during the reporting period from 1 September 2022 to 30 November 2022.
The structure of the report is as follows:
Section
1: Introduction
It details the
scope and structure of the report.
Section 2: Project Information
It summarises
the background and scope of the Project, site description, project organisation
and status of the Environmental Permits (EP)/licences.
Section 3: Environmental Monitoring and Audit Requirements
It summarises the environmental
monitoring requirements including monitoring parameters, programmes,
methodologies, frequency, locations, Action and Limit Levels, Event/Action
Plans, as well as environmental audit requirements as recommended in the
EM&A Manual and approved EIA report.
Section 4: Monitoring Results
It summarises monitoring results of
the reporting period.
Section 5: Site Audit
It summarises the audit findings of
the environmental as well as landscape and visual site audits undertaken within
the reporting period.
Section 6: Environmental Non-conformance
It summarises any exceedance of
environmental performance standard, environmental complaints and summons
received within the reporting period.
Section 7: Further Key Issues
It summarises the impact forecast
for the next reporting period.
Section 8: Conclusions
The Organic Resources Recovery Centre (ORRC) Phase I
development (hereinafter referred to as “the Project”) is to design, construct
and operate a biological treatment facility with a capacity of about 200 tonnes
per day and convert source-separated organic waste from commercial and
industrial sectors (mostly food waste) into compost and biogas through proven
biological treatment technologies. The
location of the Project site is shown in Annex A.
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection
(DEP) approved this EIA Report under the Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register
No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on
Environmental Implications and Report on Re-assessment on Hazard to Life
Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010) was issued by the DEP to the EPD (Project Team), the
Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A)
and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the
ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre (Phase
1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering
Limited and Ros-Roca, Sociedad Anonima jointly
trading as the OSCAR Bioenergy Joint Venture (OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was
issued by the DEP to the OSCAR on 16 February 2015. Variation to both EPs (Nos. EP-395/2010/B and
FEP-01/395/2010/B) were made in December 2015.
The latest EPs, Nos. EP-395/2010/C and FEP-01/395/2010/C, were issued by
the DEP on 21 December 2015.
Under the requirements of Condition 5 of
the EP (No. FEP-01/395/2010/C), an Environmental Monitoring and Audit
(EM&A) programme as set out in the approved EM&A Manual (hereinafter
referred to as EM&A Manual) is required to be implemented during the construction
and operation of the Project. ERM-Hong
Kong, Ltd (ERM) has been appointed by OSCAR as the Environmental Team (ET) for
the construction phase EM&A programme and the Monitoring Team (MT) for the
operation phase EM&A programme for the implementation of the EM&A programme in
accordance with the requirements of the EP and the approved EM&A Manual.
The
construction works commenced on 21 May 2015.
The operation phase of the EM&A programme commenced on 1 March 2019 ([1]).
The construction phase EM&A
programme was completed in the end of February 2020.
The Project Site
is located at Siu Ho Wan in North Lantau with an area of about 2 hectares. The
layout of the Project Site is illustrated in Annex A. The facility received an average of 139.33 to
144.23 tonnes and treated an average of 121.87 to 124.72 tonnes of source
separated organic waste per day during the reporting period.
A summary of the major activities undertaken in the reporting
period is shown in Table 2.1.
Table 2.1 Summary
of Activities Undertaken in the Reporting Period
Activities Undertaken in the Reporting Period |
·
Systems being operated – waste reception,
pre-treatment, CAPCS extraction, the digesters, the centrifuge, the
composting tunnels, the de-sulphurisation, the emergency flare, the CHPs, the
ASP and the biological waste water treatment plant
(405.43 t/d SSOW received); ·
E50 Service for CHP 2 (overhaul works) was completed
with testing and commissioning; ·
Emergency repair works for the ECU (heat exchanger)
for the ASP was conducted; ·
Four points calibration and adjustment was conducted for the CEMS; ·
Steam Generator tube bundle replacement and ECU
cassette replacement were completed; ·
The VOC sensor for CAPCS was installed in this
reporting period, while further modification is still recommended; ·
Biogas booster replacement was conducted; and ·
Setting adjustments of the CHP 2 engine were
conducted to fine tune and return the maximum loading of the engine to 1,500
kW |
The project organisation chart and contact details are
shown in Annex B.
A summary of the valid permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary of Environmental Licensing,
Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December
2015 |
Effluent Discharge License |
WT00038391-2021 |
7 July 2021 – 30 June 2026 |
Approved on 7 July 2021 |
Chemical Waste
Producer Registration |
WPN 5213-961-O2231-02 |
Throughout the
implementation of the Project |
Approved on 10
November 2017 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
The air quality (including odour) monitoring to be carried out during
the operation phase of the Project are described below. Although water quality monitoring is not
required for the operation phase under the EM&A programme, there are water
quality monitoring requirement under the Water Discharge Licence of the plant
under the Water Pollution Control
Ordinance (WPCO). As part of this
EM&A programme, the monitoring results will be reviewed to check the
compliance with the WPCO requirements.
According to the EM&A Manual and EP requirements,
stack monitoring are required during the operation
phase of the Project.
On-line monitoring (using continuous environmental
monitoring system (CEMS) shall be carried out for the centralised air pollution
unit (CAPCS), cogeneration units (CHP) and the ammonia stripping plant (ASP)
during the operation phase. The last
calibration was carried out on November 2022.
The monitoring data is transmitted instantaneously to
EPD (Regional Office) by telemetry system.
When the on-line monitoring for certain parameter
cannot be undertaken, monitoring will be carried out using the following
methodology approved by the EPD.
Table 3.1 Sampling
and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be Monitored |
Gaseous
and vaporous organic substances (including methane) |
USEPA Method 18 |
· CAPCS · CHP · ASP |
Particulate |
USEPA Method 5 |
· CAPCS · CHP · ASP |
Carbon
monoxide (CO) |
USEPA
Method 10 |
· CHP · ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
· CHP · ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
· CHP · ASP |
Hydrogen chloride (HCl) |
USEPA Method 26A |
· CHP · ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
· CHP · ASP |
Oxygen (O2); |
USEPA Method 3A |
· CAPCS · CHP · ASP |
Velocity and Volumetric Flow |
USEPA Method 2 |
· CAPCS · CHP · ASP |
Ammonia (NH3) |
USEPA CTM 027 |
· ASP |
Odour (including NH3
and H2S) |
EN 13725 |
· CAPCS |
Water vapour content (continuous
measurement of the water vapour content should not be required if the sample
exhaust gas is dried before the emissions are analysed) |
USEPA Method 4 |
· CAPCS · CHP · ASP |
Temperature |
USEPA Method 4 |
· CAPCS · CHP · ASP |
With reference to the EM&A Manual, the air
emission of the stacks shall meet the following emission limits as presented in
Tables 3.2 to 3.5.
Table 3.2 Emission
Limit for CAPCS Stack
Parameter |
Emission Level (mg/Nm3) (a) |
VOCs (including
methane) |
680 |
Dust (or Total Suspended Particulates (TSP)) |
6 |
Odour (including
NH3 & H2S) |
220
(b) |
Notes: (a) Hourly average
concentration (b) The odour unit
is OU/Nm3 |
Table 3.3 Emission
Limit for CHP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended
Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs (c) |
150 |
VOCs
(including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes: (a) All
values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) Hourly
average concentration (c) NMVOCs
should be monitored by gas sampling and laboratory analysis at an agreed
interval. For the first 12 months
(starting from August 2019), monitoring should be carried out at quarterly
intervals. The monitoring frequency should then be reduced to half-yearly for
next 12 months (starting from August 2020). (d) The VOCs
emission limit include methane as biogas is adopted as fuel in the combustion
process. |
Table 3.4 Emission
Limit for ASP Stack
Parameter |
Maximum Emission Level
(mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs
(including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes:
(a)
All values refer to an oxygen content in the exhaust
gas of 11% and dry basis. (b)
Hourly average concentration (c)
The VOCs emission limit include methane as biogas is
adopted as fuel in the combustion process. |
Table 3.5 Emission
Limit for Standby Flaring Gas Unit ([2])
Parameter |
Maximum Emission level (mg/Nm3) (a)
(b) |
Dust
(or Total Suspended Particulates) |
5 |
Carbon
Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs
(including methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes:
(a)
All values refer to an oxygen content in the exhaust
gas of 11% and dry basis. (b)
Hourly average concentration (c)
The VOCs emission limit include methane as biogas is
adopted as fuel in the combustion process. |
To
determine the effectiveness of the proposed odour mitigation measures and to
ensure that the operation of the ORRC1 will not cause adverse odour impacts,
odour monitoring of the CAPCS stack (see Section
3.1.1) and odour patrol will be carried out.
Odour patrol shall be conducted by independent trained
personnel/ competent persons in summer months (i.e.
from July to September) for the first two operational years of ORRC1 at monthly
intervals along an odour patrol route at the Project Site boundary as shown in Annex A.
The perceived odour intensity is divided into 5
levels. Table 3.6 describes the odour intensity for different levels.
Table 3.6 Odour
Intensity Level
Level |
Odour Intensity |
0 |
Not detected. No odour perceived
or an odour so weak that it cannot be easily
characterised or described |
1 |
Slight identifiable odour,
and slight chance to have
odour nuisance |
2 |
Moderate identifiable
odour, and moderate chance to have odour nuisance |
3 |
Strong identifiable, likely
to have odour nuisance |
4 |
Extreme severe odour,
and unacceptable odour level |
Table 3.7 shows the
action level and limit level to be used for odour patrol. Should any exceedance
of the action and limit levels occurs, actions in accordance with the event and
action plan in Table 3.8 should be
carried out.
Table 3.7 Action
and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from odour patrol) |
When one documented compliant is received (a),
or Odour Intensity of
2 is measured from odour patrol. |
Two or more documented complaints
are received (a) within a week; or Odour intensity of 3 or above is measured
from odour patrol. |
Note: (a) Once the
complaint is received by the Project Proponent (EPD), the Project Proponent
would investigate and verify the complaint whether it is related to the
potential odour emission from the ORRC1 and its on-site wastewater treatment
unit. |
Table 3.8 Event
and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project
Proponent (a) |
Action Level |
|
|
Exceedance of action level (Odour Patrol) |
1. Identify source/reason of exceedance; 2. Repeat odour patrol to confirm finding. |
1. Carry out investigation to identify the source/reason
of exceedance. Investigation should
be completed within 2 weeks; 2. Rectify any unacceptable practice; 3. Implement more mitigation measures if necessary; 4. Inform Drainage Services Department (DSD) or the
operator of the Siu Ho Wan Sewage Treatment Works (SHWSTW) if exceedance is considered to be caused by the operation of the SHWSTW. 5. Inform North Lantau Refuse Transfer Station
(NLTS) operator if exceedance is considered to be
caused by the operation of NLTS. |
Exceedance of action level (Odour Complaints) |
1. Identify source/reason of exceedance; 2. Carry out odour patrol to determinate odour
intensity. |
1. Carry out investigation and verify the complaint
whether it is related to potential odour emission from the nearby SHWSTW; 2. Carry out investigation to identify the
source/reason of exceedance.
Investigation should be completed within 2 weeks; 3. Rectify any unacceptable practice; 4. Implement more mitigation measures if necessary; 5. Inform DSD or the operator of the SHWSTW if
exceedance is considered to be caused by the
operation of the SHWSTW. 6. Inform NLTS operator if exceedance is considered to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit
level |
1.
Identify source/reason of exceedance; 2. Inform
EPD; 3.
Repeat odour patrol to confirm findings; 4.
Increase odour patrol frequency to bi-weekly; 5.
Assess effectiveness of remedial action and keep EPD informed of the results; 6.
If exceedance stops, cease additional odour patrol. |
1.
Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2
week; 2.
Rectify any unacceptable practice; 3.
Formulate remedial actions; 4.
Ensure remedial actions properly implemented; 5.
If exceedance continues, consider what more/enhanced mitigation measures
should be implemented; 6.
Inform DSD or the operator of the SHWSTW if exceedance is
considered to be caused by the operation of the SHWSTW. |
Note: (a) Project
Proponent shall identify an implementation agent. |
Environmental mitigation measures (related to air
quality, water quality, waste, land contamination, hazard-to-life, and
landscape and visual) to be implemented during the operation phase of the
Project are recommended in the approved EIA Report and EM&A Manual and are
summarised in Annex
C. Monthly site audits for
operation phase will be carried out to check the implementation of these
measures.
Compliance audits are to be undertaken to ensure that
a valid discharge licence has been issued by EPD prior to the discharge of
effluent from the operation of the Project site. Under Effluent Discharge Licence
WT00038391-2021 (effective from July 2021), the effluent quality shall meet the
discharge limits as described in Table 3.9
and Table 3.10.
Table 3.9 Discharge
Limits for Effluent from
the Effluent Storage Tank (as stipulated in
WT00038391-2021)
Parameters |
Discharge
Limit (mg/L) |
Flow Rate (m3/day) (a) |
645 |
pH (pH units) (b) |
6-10 (c) |
Suspended Solids (b) |
800 |
Biochemical Oxygen Demand (5 days,
20°) (b) |
800 |
Chemical Oxygen Demand (b) |
2,000 |
Oil & Grease (b) |
40 |
Total Nitrogen (b) |
200 |
Total Phosphorus (b) |
50 |
Surfactants (total) (b) |
25 |
Notes:
(a)
Flow
rate is not a parameter required to be monitored and reported by the
Contractor in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. (b)
Parameters
required to be monitored and reported by the Contractor in accordance to Section B2 of the Effluent Discharge Licence under the WPCO.
(c)
Range. |
Table 3.10 Discharge
Limits for Effluent from
the Petrol Interceptor(s) (as stipulated in
WT00038391-2021)
Parameters |
Discharge
Limit (mg/L) |
Flow Rate (m3/day) |
245 (a) |
Suspended Solids (b) |
30 |
Chemical Oxygen Demand (c) |
80 |
Oil & Grease (c) |
20 |
Surfactants (total) (b) |
15 |
Notes: (a)
The
surface runoff flow rate limit was estimated by the overall yearly rainfall
data. As the actual flowrate from the
petrol interceptors depends on the weather condition instead of the
performance of the petrol interceptor, monitoring and reporting of this
parameter is not required. Hence this
parameter is not reported in Table 4.10 and
Table 4.11. (b)
Parameter
not required to be reported in accordance to Section
B2 of the Effluent Discharge Licence under the WPCO. (c)
Parameters
required to be reported in accordance to Section B2
of the Effluent Discharge Licence under the WPCO. |
In accordance with EM&A Manual, the landscape and
visual mitigation measures shall be implemented.
For operation phase, site inspection shall be
conducted once a month for the first year of operation of the Project. All measures as stated in the implementation
schedule of the EM&A Manual (see Annex C), including compensatory planting,
undertaken by both the Contractor and the specialist Landscape Sub-Contractor
during the first year of the operation phase shall be audited by a Registered
Landscape Architect (RLA) to ensure compliance with the intended aims of the
measures and the effectiveness of the mitigation measures.
The concentrations of concerned air pollutants emitted
from the stacks of the CAPCS, CHP, and ASP during the reporting period are
monitored on-line by the continuous environmental monitoring system
(CEMS). During the reporting period, the
standby flare operated on 31 October 2022.
With reference to the emission limits shown in Tables 3.2, 3.3, 3.4 and 3.5, the hourly
average concentrations and the number of exceedances of the concerned air
emissions monitored for the CAPCS, CHP, ASP and the Standby Flare Gas Unit during
this reporting period are presented in Tables
4.1 to 4.6.
It should be noted that measurements recorded under
abnormal operating conditions, e.g. start up and
stopping of stacks, unstable operation, test runs and interference of sensor, are
disregarded.
Table 4.1 Hourly
Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly Average Conc. (mg/Nm3) |
Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
VOCs (including
methane) |
0.00 – 675.20 |
680 |
Nil |
Nil |
Dust (or TSP) |
0.00 – 0.15 |
6 |
Nil |
Nil |
Odour (including
NH3 & H2S) (a) |
0.00 – 194.60 |
220
|
Nil |
Nil |
Note: (a)
The odour unit is OU/Nm3. |
Table 4.2 Hourly
Average of Parameters Recorded for CHP 1
Parameter |
Range of Hourly Average Conc. (mg/Nm3)
(a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust
(or TSP) |
0 - 15 |
15 |
Nil |
Nil |
Carbon
Monoxide |
0 - 256 |
650 |
Nil |
Nil |
NOx |
0 – 500 |
300 |
Identified (c) |
System unstable (e.g. low
efficiency, unstable column temperature) |
SO2 |
0 – 101 |
50 |
Identified
(d) |
De-sulphurisation
system tripped / Under Maintenance |
VOCs
(including methane) (b) |
0 – 1,500 |
1,500 |
Nil |
Nil |
HCl |
0 - 7 |
10 |
Nil |
Nil |
HF |
0 - 0 |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6% and
dry basis. (b)
The
VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. (c) Dates with exceedances on NOx (number of
exceedance on the day) were identified on 1
(15), 2 (5), 3 (20), 4 (17), 5 (16), 6 (23), 7 (23), 8 (24), 9 (15), 10 (9),
11 (11), 14 (6), 15 (8), 16 (24), 17 (22), 18 (24), 19 (24), 20 (24), 21
(20), 22 (2), 23 (21), 24 (21), 25 (24), 26 (20), 27 (14) and 28 (9) October
2022; 3 (9), 4 (21), 5 (1),
8 (1), 9 (6), 10 (9), 11 (3), 12 (8), 13 (10), 14 (4), 15 (7), 16 (12), 17
(9), 18 (16), 19 (15), 20 (12), 21 (5), 22 (13), 23 (8), 24 (4) and 25 (2)
November 2022. (d)
Dates
with exceedances on SO2 (number of exceedance
on the day) were identified on 17 (12) and 18 (10)
October 2022; 16 (8) and 18 (6) November 2022. |
Table 4.3 Hourly
Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 10 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 176 |
650 |
Nil |
Nil |
NOx |
0 – 498 |
300 |
Identified
(c) |
System
unable (e.g. low efficiency, unstable column
temperature) |
SO2 |
0 – 220 |
50 |
Identified
(d) |
De-sulphurization system tripped / Under Maintenance |
VOCs
(including methane) (b) |
0 – 1,367 |
1,500 |
Nil |
Nil |
HCl |
0 – 14 |
10 |
Identified
(e) |
System
unstable (e.g. low efficiency, unstable column
temperature) |
HF |
0 – 0 |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6% and
dry basis. (b)
The VOCs emission limit include methane as biogas is
adopted as fuel in the combustion process. (c)
Dates with exceedances on NOx (number of
exceedance on the day) were identified on 17
(6), 18 (3), 19 (1), 22 (1), 26 (2), 27 (2), 28 (2), 29 (4), 30 (2) and 31
(10) October 2022; 1 (16), 2 (16), 3 (14), 4 (4), 5 (10), 6 (19), 7 (14), 8
(15), 9 (6), 10 (4), 11 (3), 12 (5), 14 (7), 15 (19), 16 (13), 17 (24), 18
(24), 19 (22), 20 (21), 21 (23), 22 (24), 23 (18), 24 (24), 25 (24), 26 (24),
27 (24), 28 (16), 29 (24) and 30 (14) November 2022. (d)
Dates with exceedances on SO2 (number of
exceedance on the day) were identified on 3
(1), 8 (1), 10 (3), 11 (11), 12 (8), 15 (17), 16 (17), 17 (22), 18 (13), 19
(14) and 26 (1) October 2022; 1 (5), 5 (9), 6 (11), 7 (13), 8 (5), 9 (6), 10
(3), 11 (1), 15 (8), 16 (8), 17 (24), 18 (19), 19 (4), 20 (2), 21 (12), 22
(6), 23 (10), 24 (23), 25 (23), 26 (24), 27 (24), 28 (16), 29 (23) and 30
(17) November 2022. (e)
Dates with exceedances
on HCl (number of exceedance on the day) were
identified on 24 (1) November 2022. |
Table 4.4 Hourly
Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 6 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 230 |
650 |
Nil |
Nil |
NOx |
0 – 483 |
300 |
Identified
(c) |
System
unstable (e.g. low efficiency, unstable column
temperature) |
SO2 |
0 – 184 |
50 |
Identified
(d) |
De-sulphurisation
system tripped / Under Maintenance |
VOCs
(including methane) (b) |
0 – 953 |
1,500 |
Nil |
Nil |
HCl |
0 – 5 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6% and dry
basis. (b)
The VOCs emission limit include methane as biogas is adopted as fuel
in the combustion process. (c)
Dates with exceedances on NOx (number of exceedances on
the day) were identified on 15
(3), 16 (1), 17 (5), 18 (3), 19 (7), 20 (9) and 31 (13) October 2022; 1 (22),
2 (15), 4 (5), 10 (5), 14 (3), 15 (1) and 16 (7) November 2022. (d)
Date with exceedances on SO2 (number of exceedance on the day) was identified on 15
(3), 16 (1), 17 (6), 18 (3), 19 (8) and 20 (9) October 2022; 1 (3), 10 (1)
and 16 (5) November 2022. |
Table 4.5 Hourly
Average of Parameters Recorded for ASP
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 5 |
5 |
Nil |
Nil |
Carbon Monoxide |
0 – 79 |
100 |
Nil |
Nil |
NOx |
0
– 228 |
200 |
Identified
(c) |
System
unstable (e.g. low efficiency, unstable column
temperature) |
SO2 |
0
– 50 |
50 |
Nil |
Nil |
VOCs
(including methane) (b) |
0
– 13 |
20 |
Nil |
Nil |
NH3 |
0
– 50 |
35 |
Identified
(d) |
System
unstable (e.g. low efficiency, unstable column
temperature) |
HCl |
0
– 7 |
10 |
Nil |
Nil |
HF |
0
– 1 |
1 |
Nil |
Nil |
Notes:
(a) All values
refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) The VOCs
emission limit include methane as biogas is adopted as fuel in the combustion
process. (c) Date with
exceedances on NOx (number of exceedances on the day) were
identified on 9 (1) October 2022. (d) Dates with
exceedances on NH3 (number of exceedances on the day) were
identified on 2 (1) and 3 (4) October 2022. |
Table 4.6 Hourly Average of
Parameters Recorded for the Standby Flaring Gas Unit
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a)(c) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust
(or TSP) |
0 – 0 |
5 |
Nil |
Nil |
Carbon
Monoxide (d) |
0 – 0 |
100 |
Nil |
Nil |
NOx |
0 – 67 |
200 |
Nil |
Nil |
SO2 |
0 – 0 |
50 |
Nil |
Nil |
VOCs (including methane) (b)
(d) |
0 – 0 |
20 |
Nil |
Nil |
HCl |
0 – 0 |
10 |
Nil |
Nil |
HF (d) |
0 – 0 |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust
gas of 11% and dry basis. (b)
The VOCs emission limit include methane as biogas is
adopted as fuel in the combustion process. (c)
During the reporting period, the standby flare
operated on 31 October 2022. (d)
During this reporting period, several flare test
trials were conducted for preparing the biogas booster replacement. The
exceedances recorded under interference of the test trials were disregarded. |
Odour patrols were
conducted by the independent odour patrol team of ALS Technichem
(HK) Pty Ltd on 9 and 22 September 2022. According to the EM&A Manual and
EP requirements, it is considered an exceedance if the odour intensity recorded
by the panellists is Level 2 or above. During this reporting period, no Level 2
Odour Intensity was recorded. The
odour patrol result is shown in Annex
G.
Effluent discharge was sampled from the outlet chamber
of the Effluent Storage Tank monthly and from the Petrol Interceptor(s)
bi-monthly as stipulated in the operation phase discharge licence. The results
of the discharge samples from the Effluent Storage Tank are recorded in Table 4.7 to 4.9. The results of the
discharge samples from the Petrol Interceptors are recorded in Table 4.10 to 4.12.
Table 4.7 Results
of the Discharge Sample Collected from the Outlet Chamber of the Effluent
Storage Tank in September 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow Rate (m3/day)
(a) |
0
- 228 (e) |
645 |
Yes |
pH (pH units)
(b) |
7.64
– 8.04 (e) |
6-10 (c) |
Yes |
Suspended
Solids (b) (d) |
114
(d) |
800 |
Yes |
Biochemical
Oxygen Demand (5 days, 20°) (b) (d) |
65
(d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
775
(d) |
2,000 |
Yes |
Oil &
Grease (b) (d) |
<5
(d) |
40 |
Yes |
Total Nitrogen (b)
(d) |
102
(d) |
200 |
Yes |
Total
Phosphorus (b) (d) |
34.2
(d) |
50 |
Yes
|
Surfactants
(total) (b) (d) |
1.4
(d) |
25 |
Yes |
Notes:
(a) Parameter not required to
be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO.
(b) Parameters required to be
reported in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. (c) Daily Range. (d) Effluent sample collected
on 8 September 2022. (e) Data collected daily in the
reporting period. |
Table 4.8 Results
of the Discharge Sample Collected from the Effluent Storage Tank in October
2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow Rate (m3/day)
(a) |
11
– 225 (e) |
645 |
Yes |
pH (pH units)
(b) |
6.82
– 8.1 (e) |
6-10 (c) |
Yes |
Suspended
Solids (b) (d) |
143
(d) |
800 |
Yes |
Biochemical
Oxygen Demand (5 days, 20°) (b) (d) |
47
(d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
867
(d) |
2,000 |
Yes |
Oil &
Grease (b) (d) |
<5
(d) |
40 |
Yes |
Total Nitrogen (b)
(d) |
64.3
(d) |
200 |
Yes |
Total
Phosphorus (b) (d) |
33.4
(d) |
50 |
Yes
|
Surfactants (total)
(b) (d) |
1.4
(d) |
25 |
Yes |
Notes:
(a) Parameter not required to
be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO.
(b) Parameters required to be
reported in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. (c) Daily Range. (d) Effluent sample collected
on 7 October 2022. (e) Data collected daily in the
reporting month. |
Table 4.9 Results
of the Discharge Sample Collected from
the Effluent Storage Tank in November 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow Rate (m3/day)
(a) |
0 - 182 (e) |
645 |
Yes |
pH (pH units)
(b) |
7.39 – 8.5 (e) |
6-10 (c) |
Yes |
Suspended
Solids (b) (d) |
83 (d) |
800 |
Yes |
Biochemical
Oxygen Demand (5 days, 20°) (b) (d) |
19 (d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
693 (d) |
2,000 |
Yes |
Oil &
Grease (b) (d) |
<5
(d) |
40 |
Yes |
Total Nitrogen (b)
(d) |
68.8 (d) |
200 |
Yes |
Total
Phosphorus (b) (d) |
20.5 (d) |
50 |
Yes
|
Surfactants (total)
(b) (d) |
<1.0 (d) |
25 |
Yes |
Notes:
(a) Parameter not required to
be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO.
(b) Parameters required to be
reported in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. (c) Daily Range. (d) Effluent sample collected
on 10 November 2022. (e) Data collected daily in the
reporting month. |
Table 4.10 Results
of the Discharge Sample from the Petrol Interceptor 1 on 19 October 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
26 (a) |
30 |
Yes |
Chemical Oxygen Demand (c) |
72 (a) |
80 |
Yes |
Oil & Grease (c) |
<5 (a) |
20 |
Yes |
Surfactants (total)
(b) |
<1.0 (a) |
15 |
Yes |
Notes: (a) Effluent sample collected
on 19 October 2022. (b) Parameter not required to
be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO.
(c) Parameters required to be
reported in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. |
Table
4.11 Results of the Discharge Sample from the
Petrol Interceptor 2 on 1 September 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
6 (a) |
30 |
Yes |
Chemical Oxygen Demand (c) |
36 (a) |
80 |
Yes |
Oil & Grease (c) |
<5 (a) |
20 |
Yes |
Surfactants (total)
(b) |
<1.0 (a) |
15 |
Yes |
Notes: (a) Effluent sample collected
on 1 September 2022. (b) Parameter not required to
be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO.
(c) Parameters required to be
reported in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. |
Table 4.12 Results of the Discharge Sample from the
Petrol Interceptor 2 on 19 October 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
7 (a) |
30 |
Yes |
Chemical Oxygen Demand (c) |
22 (a) |
80 |
Yes |
Oil & Grease (c) |
<5 (a) |
20 |
Yes |
Surfactants (total)
(b) |
<1.0 (a) |
15 |
Yes |
Notes: (a) Effluent sample collected
on 19 October 2022. (b) Parameter not required to
be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO.
(c) Parameters required to be
reported in accordance to Section B2 of the Effluent
Discharge Licence under the WPCO. |
No exceedance of discharge limit was recorded during
the reporting period.
Wastes generated from the operation of the Project
include chemical waste, wastes generated from pre-treatment process and general
refuse ([3]). Reference has been made to the Monthly
Summary Waste Flow Table prepared by the Contractor (see Annex D). With reference to the relevant handling
records and trip tickets of this Project, the quantities of different types of
waste generated from the operation of the Project in the reporting period are
summarised in Table 4.13.
Table 4.13 Quantities of Waste Generated from the Operation
of the Project
Month
/ Year |
Chemical
Waste |
Waste Generated from |
General
Refuse |
||||
|
Disposal
of at CWTC (e) |
Disposed of
at Landfill (a) |
Recycled (b) |
Disposed of
at Landfill (a) (c) |
Recycled (d) |
||
September 2022 |
0 L |
476.92 tonnes |
0.00 tonnes |
2.42 tonnes |
0.000 tonne |
||
October 2022 |
0 L |
615.87 tonnes |
0.00 tonnes |
2.76 tonnes |
0.000 tonne |
||
November 2022 |
0 L |
585.38 tonnes |
0.00 tonnes |
3.00 tonnes |
0.075 tonne |
||
Notes: (a)
Waste generated from pre-treatment process and general refuse other than
chemical waste and recyclables were disposed of at NENT landfill by
sub-contractors. (b)
Among waste generated from pre-treatment process, 0.000
tonne of metals, 0.000 tonne
of papers/ cardboard packing and 0.000 tonne of plastics were sent to recyclers for recycling during the
reporting period. (c)
It was assumed that four 240-litre bins filled with
80% of general refuse were collected at each collection. The general refuse density was assumed to
be around 0.15 kg/L. (d)
Among general refuse, 0.020 tonnes of metals, 0.035 tonnes
of papers/ cardboard packing and 0.020 tonnes of plastics were sent to recyclers for recycling during the
reporting period. (e)
No chemical waste was generated in this reporting
period. |
|||||||
The monthly inspections of the operation phase of the
Project covered the operation phase environmental site inspections. The inspections checked the implementation of
the recommended mitigation measures for air quality, landscape and visual,
water quality, waste (land contamination) and hazard-to-life stated in the
Implementation Schedule (see Annex C).
Follow-up actions resulting
from the site inspections were generally taken as reported by the
Contractor. The Contractor
has implemented environmental mitigation measures recommended in the approved
EIA Report and EM&A Manual.
September
2022
The monthly inspection of the operation phase of the
Project on 27 September 2022 covered the operation phase environmental site
audit. Joint site inspections was conducted by representatives of the Contractor, IEC and
the MT on 27 September 2022 as required for the operation of the Project.
October
2022
The monthly inspection of the operation phase of the
Project on 26 October 2022 covered the operation
phase environmental site audit. Joint
site inspections was conducted by representatives of
the Contractor, IEC and the MT on 26 October 2022 as
required for the operation of the Project.
November
2022
The monthly inspection of the operation phase of the
Project on 29 November 2022 covered the operation
phase environmental site audit. Joint
site inspection was conducted by representatives of the Contractor, IEC and the
MT on 29 November 2022 as required for
the operation of the Project.
It was confirmed that the necessary landscape and visual mitigation measures
during the operation phase as summarised in Annex C were generally implemented by the
Contractor. No
non-compliance in relation to the landscape and visual mitigation measures was identified
during the site audits in this reporting period and therefore no further
actions are required. The ET/MT will
keep track of the EM&A programme to check compliance with environmental
requirements and the proper implementation of all necessary mitigation
measures.
September 2022
Monthly inspection of the
landscape and visual mitigation measures for the operation phase of the Project
was performed on 27 September 2022.
October 2022
Monthly inspection of the
landscape and visual mitigation measures for the operation phase of the Project
was performed on 26 October 2022.
November 2022
Monthly inspection of the
landscape and visual mitigation measures for the operation phase of the Project
was performed on 29 November 2022.
September 2022
No non-compliance and deficiencies
were recorded in September 2022.
Non-compliance
of emission limits of NOx and SO2 from the CHPs and NOx
and NH3 from ASP were recorded in October 2022.
The Contractor
has reviewed the organic waste treatment processes (i.e.
waste reception, waste pre-treatment, anaerobic digesters, and composting processes)
and found that they were operated normally during the reporting period. The
Contractor has investigated the de-sulphurisation system, CHPs and the ASP, the
potential causes for the exceedance were identified.
The
investigation reports of the above exceedance are presented in Annex F.
November 2022
Non-compliance
of emission limits of SO2, NOx and HCI from the CHPs were
recorded in November 2022.
The Contractor
has reviewed the organic waste treatment processes (i.e.
waste reception, waste pre-treatment, anaerobic digesters, and composting processes)
and found that they were operated normally during the reporting period. The
Contractor has investigated the de-sulphurisation system, CHPs and the ASP, the
potential causes for the exceedance were identified.
The
Investigation Reports of the above exceedances are presented in Annex F.
Activities to be undertaken for the coming reporting
period are:
·
Operation of the Project;
·
Additional
setting adjustments of CHP2; and
·
Further
testing in preparation of the Biogas Holder replacement works.
This EM&A Report presents the EM&A programme undertaken
during the reporting period from 1 September
2022 to 30 November 2022 in
accordance with EM&A Manual (Version F) and requirements of EP (FEP-01/395/2010/C).
For the operation phase, exceedances of the emission
limits for stack monitoring (including CHPs and ASP stacks) were recorded under
normal operating conditions during the reporting period (see Table 8.1).
Table 8.1 Exceedances for Stack Emissions
Stack |
Exceedances During the Reporting Period |
Cogeneration
Unit 1 (CHP1) |
· Exceeded
emission limit of NOx on 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 ,
11 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 and
28 October 2022; 3 , 4 , 5 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 ,
18 , 19 , 20 , 21 , 22 , 23 , 24 and 25
November 2022. · Exceeded
emission limit of SO2 on 17 and 18 October 2022; 16 and 18
November 2022. |
Cogeneration
Unit 2 (CHP2) |
· Exceeded
emission limit of NOx on 17, 18, 19, 22, 26, 27, 28, 29, 30, and
31 October 2022; 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14. 15. 16. 17, 18,
19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29 and 30 November 2022 · Exceeded
emission limit of SO2 on 3, 8, 10, 11, 12, 15, 16, 17, 18, 19 and 26
October 2022; 1, 5 , 6 , 7 , 8 , 9 , 10 , 11 , 15 ,
16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27, 28, 29 and 30
November 2022. |
Cogeneration
Unit 3 (CHP3) |
· Exceeded
emission limit of NOx on 15, 16, 17, 18, 19 and 20 October 2022;
1, 2, 4, 10, 14, 15 and 16 November 2022. · Exceeded emission
limit of SO2 on 15, 16, 17, 18, 19 and 20 October 2022; 1, 10 and
16 November 2022. |
Ammonia
Stripping Plant (ASP) |
· Exceeded
emission limit of NOx on 9 October 2022. · Exceeded
emission limit of NH3 on 2 and 3 October 2022. |
The exceedances of SO2
from CHPs occurred due to tripping of the de-sulphurisation system caused by
the failure of one of the columns of the system. The exceedances of NOx from
CHPs occurred due to insufficient feedstock and system unstability.
The exceedance of HCl from CHP 2 occurred due to system instability caused by
the ongoing performance optimisation of the CHP 2, resulting in a lowered
temperature of the system and the incomplete combustion of biogas. The exceedance of NH3 and NOx from ASP
occurred due to system instability caused by the ongoing performance optimisation of the ASP, resulting in a lowered temperature
of the system and the incomplete combustion of biogas.
No
non-compliance to the effluent discharge limit was recorded during this
reporting period.
The
environmental control /mitigation measures related to air quality, water
quality, waste (including land contamination prevention), hazard-to-life and
landscape and visual recommended in the approved EIA Report and the EM&A
Manual were properly implemented by the Contractor during the reporting period.
Monthly
landscape and visual monitoring were conducted in the reporting period. The necessary landscape and visual mitigation
measures recommended in the approved EIA Report were generally implemented by
the Contractor.
No complaint/summon/prosecution was received.
([1])
As some of the minor items are yet to be
closed out in March 2019, the construction phase EM&A programme and
Operation Phase EM&A programme were undertaking in parallel in March 2019.