Contents
1.1
Purpose of the Report
1.2
Structure of the Report
2.1
Background
2.2
General Site Description
2.3
Major Activities Undertaken
2.4
Project Organisation and Management Structure
2.5
Status of Environmental Approval Documents
3
Environmental Monitoring and Audit Requirements
3.1
Environmental Monitoring
3.1.1
Air Quality
3.1.2
Odour
3.2
Site Audit
3.2.1
Water Quality
3.2.2
Landscape and Visual
4.1
Air Quality
4.1.1
Operation Phase Monitoring
4.2
Odour
4.2.1
Operation Phase Monitoring
4.3
Water Quality
4.3.1
Operation Phase Monitoring
4.4
Waste Management
4.4.1
Operation Phase Monitoring
5.1
Environmental Site Audit
5.1.1
Operation Phase
5.2
Landscape and Visual Audit
6
Environmental Non-conformance
6.1
Summary of Environmental Non-Compliance
6.2
Summary of Environmental Complaint
6.3
Summary of Environmental Summon and Successful
Prosecution
7.1
Key Issues for the Coming Reporting Period
LIST OF TABLES
Table 2.1
Summary of Activities Undertaken in the
Reporting Period
Table 2.2
Summary of Environmental Licensing,
Notification and Permit Status
Table 3.1
Sampling and Laboratory Analysis Methodology
Table 3.2
Emission Limit for CAPCS Stack
Table 3.3
Emission Limit for CHP Stack
Table 3.4
Emission Limit for ASP Stack
Table 3.5
Emission Limit for Standby Flaring Gas Unit
Table 3.6
Odour Intensity Level
Table 3.7
Action and Limit Levels for Odour Nuisance
Table 3.8
Event and Action Plan for Odour Monitoring
Table 4.1
Hourly Average of Parameters Recorded for CAPCS
Table 4.2
Hourly Average of Parameters Recorded for CHP 1
Table 4.3
Hourly Average of Parameters Recorded for CHP 2
Table 4.4
Hourly Average of Parameters Recorded for CHP 3
Table 4.5
Hourly Average of Parameters Recorded for ASP
Table 4.6
Hourly Average of Parameters Recorded for the
Standby Flaring Gas Unit
Table 4.10
Results of the Discharge Sample from the Petrol
Interceptor 1 on 8 December 2022
Table 4.11
Results of the Discharge Sample from the Petrol
Interceptor 1 on 23 February 2023
Table 4.12
Results of the Discharge Sample from the Petrol
Interceptor 2 on 8 December 2022
Table 4.13
Results of the Discharge Sample from the Petrol
Interceptor 2 on 23 February 2023
Table 4.14
Quantities of Waste Generated from the
Operation of the Project
Table 8.1
Exceedances for Stack Emissions
Table 8.2
Exceedances for Petrol Interceptor 1 and 2
LIST OF ANNEXES
Annex E Environmental complaint, Environmental
Summons and Prosecution Log |
|
|
|
The construction works of No.
EP/SP/61/10 Organic Resources Recovery Centre Phase 1 (the
Project) commenced on 21 May 2015. This is
the 31st Quarterly Environmental Monitoring and Audit (EM&A)
Report presenting the EM&A works carried out during the period from 1
December 2022 to 28 February 2023 in accordance with the EM&A Manual.
Substantial completion of the construction works was confirmed on 3 December
2018. In the meantime, the operation phase EM&A programme had commenced in
March 2019. Substantial Completion in respect of substantial part of the Works
was confirmed on 24 February 2020. The construction phase EM&A programme
was completed in the end of February 2020.
Summary of Works undertaken during
the Reporting Period
Works undertaken in the reporting
period included:
·
Operation of the Project, including organic
waste reception, and operation of the pre-treatment facilities, anaerobic
digesters, composting facilities, air pollution control systems, on-line
emission monitoring system for the Centralised Air Pollution Control Unit
(CAPCS), Co-generation Units (CHP)s and Ammonia Stripping Plant (ASP), and the
wastewater treatment plant;
· Setting adjustments of the CHP 2 engine to fine tune and return the
maximum loading of the engine to 1,500 kW;
· Biogas bypass trials for preparing the Biogas Holder replacement works;
· Replacement works of biogas holder from 9 to 12 January 2023, with flare
operated during the replacement works;
· Fine tuning of the CHP temperature curves and PM; and
· Repair of the VOC sensor for CAPCS.
Environmental Monitoring and Audit Progress
Air Quality Monitoring
Non-compliance of emission limits of
SO2 and NOx from the CHPs, HCl from CHP 2, NOx,
SO2 and NH3 from ASP and CO, NOx, SO2,
VOCs, HCl, and HF from Standby Flaring Gas Unit were recorded during December
2022. The exceedances of SO2 from CHPs and the ASP occurred due to
tripping of the de-sulphurisation system caused by the failure of one of the
columns of the system. The exceedances of HCl from CHP 2 in mid-December
occurred due to system instability. The exceedances of NOx and NH3
from CHPs and ASP occurred due to system instability caused by the ongoing
performance optimisation of the ASP and CHPs, resulting in a lowered
temperature of the system and the incomplete combustion of biogas. The
exceedances of CO, NOx, SO2, VOCs, HCl, and HF from
Standby Flaring Gas Unit occurred due to the biogas bypass trial.
Non-compliance of emission limits of
NOx and SO2 from the CHPs, NOx, SO2 and NH3 from ASP and CO, VOCs, HCl and HF
from Standby Flaring Gas Unit were recorded during January 2023. The
exceedances of SO2 from CHPs and the ASP occurred due to tripping of the
de-sulphurisation system resulted from the residue of sulphur accumulated at
the exhaust heat exchangers. The exceedances of NOx and NH3 from the CHPs
and ASP occurred due to system instability caused by prolonged usage of the
CHPs and the ongoing performance optimisation of the ASP, resulting in a
lowered temperature of the system and the incomplete combustion of
biogas. The exceedances of CO, VOCs, HCl and HF from Standby Flaring Gas
Unit occurred due to biogas bypass trial.
Non-compliance of emission limits of
NOx and SO2 from the CHPs, HCl from CHP 1 and NOx,
SO2, and NH3 from ASP were recorded during February 2023.
The exceedances of SO2 from CHPs and the ASP occurred due to
tripping of the de-sulphurisation system caused by the failure of one of the
columns of the system. The exceedances of NOx, NH3, and HCl from ASP
occurred due to system instability caused by the ongoing performance
optimisation of the CHP 1 and ASP, resulting in a lowered temperature of the
system and the incomplete combustion of biogas.
As similar issues have re-occurred
in multiple reporting periods, the Contractor is advised to undertake a
comprehensive review of the operation of the concerned systems and the
effectiveness of the existing mitigation measures and proposed further measures
to avoid the exceedance.
No odour patrols were required to be
conducted during the reporting period.
Non-compliance of discharge limits
of Suspended Solids and Chemical Oxygen Demand from Petrol Interceptor 1 and
Chemical Oxygen Demand from Petrol Interceptor 2 were recorded during February
2023. The exceedances of Suspended Solids and Chemical Oxygen Demand occurred
due to the dry season with less rainfall, resulting in the discharge water
containing higher concentrations for the exceeded parameters.
Waste generated from the operation
of the Project includes chemical waste, waste generated from pre-treatment
process and general refuse.
6,740 L of chemical waste was
collected during the reporting period by licenced waste collector from the
operation of the Project.
1891.72 tonnes of waste generated
from pre-treatment process from the operation of the Project was disposed of at
landfill. Among the recyclable waste generated from pre-treatment process from
the operation of the Project, 0.969 tonnes of metals, 0.360 tonnes of
papers/cardboard packing, and 0.021 tonnes of plastics were sent to recyclers
for recycling during the reporting period.
Around 8.98 tonnes of general refuse
from the operation of the Project were disposed of at landfill. Among the
recycled general refuse from the operation of the Project, 0.004 tonnes of
metals, 0.044 tonnes of papers/cardboard packing and 0.065 tonnes of plastics
were sent to recyclers for recycling during the reporting period.
Findings of Environmental Site Audit
A summary of the monitoring activities undertaken in this reporting
period is listed below:
· Joint Environmental Site Inspections |
3 times |
Monthly joint environmental site inspections were carried out. The
environmental control/mitigation measures (related to air quality, water
quality, waste (including land contamination prevention), hazard-to-life, and
landscape and visual) recommended in the approved EIA Report and the EM&A
Manual were properly implemented by the Contractor during the reporting month.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
Exceedances for the air emission limits for the CHP, ASP stacks and
Standby Flaring Gas Unit were recorded during the reporting period.
No complaint/ summon/prosecution was
received in this reporting period.
Future Key Issues
Activities to be undertaken in the
next reporting period include:
·
Operation of the Project; and
·
SBR Cleaning and Diffuser Replacement works.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR Bioenergy Joint
Venture (the Contractor) as the Environmental Team (ET) to undertake the
construction Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I, which
the project name has been updated to Organic Resources Recovery Centre
(Phase I) (the Project) since November 2017. ERM was also appointed by the
Contractor to undertake the operation EM&A programme starting 1 March 2019.
This is the 31st Quarterly EM&A report which summarises
the monitoring results and audit findings for the EM&A programme during the
reporting period from 1 December 2022 to 28 February 2023.
The structure of the report is as follows:
Section
1: Introduction
It details the scope and structure
of the report.
Section 2: Project Information
It summarises the background and scope of the
Project, site description, project organisation and status of the Environmental
Permits (EP)/licences.
Section 3: Environmental
Monitoring and Audit Requirements
It summarises the environmental
monitoring requirements including monitoring parameters, programmes,
methodologies, frequency, locations, Action and Limit Levels, Event/Action
Plans, as well as environmental audit requirements as recommended in the EM&A
Manual and approved EIA report.
Section 4: Monitoring
Results
It summarises monitoring results of
the reporting period.
Section 5: Site Audit
It summarises the audit findings of
the environmental as well as landscape and visual site audits undertaken within
the reporting period.
Section 6: Environmental
Non-conformance
It summarises any exceedance of
environmental performance standard, environmental complaints and summons
received within the reporting period.
Section 7: Further Key
Issues
It summarises the impact forecast
for the next reporting month.
Section 8: Conclusions
The Organic Resources Recovery Centre (ORRC) Phase I development
(hereinafter referred to as “the Project”) is to design, construct and operate
a biological treatment facility with a capacity of about 200 tonnes per day and
convert source-separated organic waste from commercial and industrial sectors
(mostly food waste) into compost and biogas through proven biological treatment
technologies. The location of the Project site is shown in Annex A.
The environmental acceptability of the construction
and operation of the Project had been confirmed by findings of the associated
Environmental Impact Assessment (EIA) Study completed in 2009. The Director of
Environmental Protection (DEP) approved this EIA Report under the Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register
No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report).
Subsequent Report on Re-assessment on Environmental Implications and Report on
Re-assessment on Hazard to Life Implications were completed in 2013,
respectively.
An Environmental Permit (EP) (No. EP-395/2010)
was issued by the DEP to the EPD (Project Team), the Permit Holder, on 21 June
2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No.
EP-395/2010/B), respectively. The Design Build and Operate Contract for the
ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre (Phase
1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering
Limited and Ros-Roca, Sociedad Anonima jointly
trading as the OSCAR Bioenergy Joint Venture (OSCAR or the Contractor). A
Further EP (No. FEP-01/395/2010/B) was issued by the DEP to the OSCAR on 16
February 2015. Variation to both EPs (Nos. EP-395/2010/B and FEP-01/395/2010/B)
were made in December 2015. The latest EPs, Nos. EP-395/2010/C and
FEP-01/395/2010/C, were issued by the DEP on 21 December 2015.
Under the requirements of Condition 5 of the EP (No.
FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme
as set out in the approved EM&A Manual (hereinafter referred to as EM&A
Manual) is required to be implemented during the construction and operation of
the Project. ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the
Environmental Team (ET) for the construction phase EM&A programme and the
Monitoring Team (MT) for the operation phase EM&A programme for the
implementation of the EM&A programme in accordance with the requirements of the EP and the approved
EM&A Manual.
The construction works commenced on
21 May 2015. The operation phase of the EM&A programme commenced on 1 March
2019 ([1]).
The construction phase EM&A programme was completed in the end of February
2020.
The Project Site is located at Siu Ho Wan in North Lantau with an area
of about 2 hectares. The layout of the Project Site is illustrated in Annex A. The
facility received an average of 114.28 to 135.14 tonnes and treated an average
of 95.48 to 112.14 tonnes of source separated organic waste per day during the
reporting period.
A summary of the major activities undertaken in the reporting period is
shown in Table 2.1.
Table 2.1
Summary of Activities Undertaken in the Reporting Period
Activities Undertaken in the
Reporting Period |
·
Systems being operated – waste reception, pre-treatment, CAPCS
extraction, the digesters, the centrifuge, the composting tunnels, the
desulphurisation, the emergency flare, the CHPs, the ASP and the biological
waste water treatment plant (about 114.28 – 135.14 t/d SSOW input); ·
Setting adjustments of the CHP 2 engine to fine tune and return the
maximum loading of the engine to 1,500 kW; ·
Biogas bypass trials for preparing the Biogas Holder replacement
works; ·
Replacement works of biogas holder from 9 to 12 January 2023, with
flare operated during the replacement works; ·
Fine tuning of the CHPs temperature curves and PM; and ·
Repair of VOC sensor for CAPCS. |
The project organisation chart and contact details are shown in Annex B.
A summary of the valid permits, licences, and/or notifications on
environmental protection for this Project is presented in Table 2.2.
Table 2.2
Summary of Environmental Licensing, Notification and Permit Status
Permit/
Licences/ Notification |
Reference |
Validity
Period |
Remarks |
Environmental
Permit |
FEP-01/395/2010/C |
Throughout
the Contract |
Permit
granted on 21 December 2015 |
Effluent
Discharge License |
WT00038391-2021 |
7 July 2021
– 30 June 2026 |
Approved on
7 July 2021 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-02 |
Throughout the implementation of the Project |
Approved on 10 November 2017 |
Waste
Disposal Billing Account |
Account
number: 702310 |
Throughout
the Contract |
- |
The air quality (including odour) monitoring to
be carried out during the operation phase of the Project are described below.
Although water quality monitoring is not required for the operation phase under
the EM&A programme, there are water quality monitoring requirement under
the Water Discharge Licence of the plant under the Water Pollution Control
Ordinance (WPCO). As part of this EM&A programme, the monitoring
results will be reviewed to check the compliance with the WPCO requirements.
According to the EM&A Manual and EP requirements, stack monitoring
are required during the operation phase of the Project.
On-line monitoring (using continuous environmental monitoring system
(CEMS) shall be carried out for the centralised air pollution unit (CAPCS),
cogeneration units (CHP) and the ammonia stripping plant (ASP) during the
operation phase. Calibration was carried out in January 2023.
The monitoring data is transmitted instantaneously to EPD (Regional
Office) by telemetry system.
When the on-line monitoring for certain parameter cannot be undertaken,
monitoring will be carried out using the following methodology approved by the
EPD.
Table 3.1
Sampling and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be
Monitored |
Gaseous and vaporous
organic substances (including methane) |
USEPA Method 18 |
· CAPCS · CHP · ASP |
Particulate |
USEPA Method 5 |
· CAPCS · CHP · ASP |
Carbon monoxide (CO) |
USEPA
Method 10 |
· CHP · ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
· CHP · ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
· CHP · ASP |
Hydrogen chloride
(HCl) |
USEPA Method 26A |
· CHP · ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
· CHP · ASP |
Oxygen (O2); |
USEPA Method 3A |
· CAPCS · CHP · ASP |
Velocity and
Volumetric Flow |
USEPA Method 2 |
· CAPCS · CHP · ASP |
Ammonia (NH3) |
USEPA CTM 027 |
· ASP |
Odour (including NH3
and H2S) |
EN 13725 |
· CAPCS |
Water vapour content
(continuous measurement of the water vapour content should not be required if
the sample exhaust gas is dried before the emissions are analysed) |
USEPA Method 4 |
· CAPCS · CHP · ASP |
Temperature |
USEPA Method 4 |
· CAPCS · CHP · ASP |
With reference to the EM&A Manual, the air emission of the stacks
shall meet the following emission limits as presented in Tables 3.2 to
3.5.
Table 3.2
Emission Limit for CAPCS Stack
Parameter |
Emission Level
(mg/Nm3) (a) |
VOCs (including
methane) |
680 |
Dust (or Total Suspended
Particulates (TSP)) |
6 |
Odour (including NH3
& H2S) |
220 (b) |
Notes: (a) Hourly average concentration (b) The odour unit is OU/Nm3 |
Table 3.3
Emission Limit for CHP Stack
Parameter |
Maximum Emission
Level (mg/Nm3) (a) (b) |
Dust (or Total
Suspended Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs
(c) |
150 |
VOCs
(including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer
to an oxygen content in the exhaust gas of 6% and dry basis. (b) Hourly average
concentration (c) NMVOCs should be
monitored by gas sampling and laboratory analysis at an agreed interval. For
the first 12 months (starting from August 2019), monitoring should be carried
out at quarterly intervals. The monitoring frequency should then be reduced
to half-yearly for next 12 months (starting from August 2020). (d) The VOCs emission
limit include methane as biogas is adopted as fuel in the combustion process. |
Table 3.4
Emission Limit for ASP Stack
Parameter |
Maximum Emission Level
(mg/Nm3) (a) (b) |
Dust (or Total Suspended
Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs
(including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen
content in the exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include
methane as biogas is adopted as fuel in the combustion process. |
Table
3.5 Emission Limit for Standby
Flaring Gas Unit ([2])
Parameter |
Maximum Emission
level (mg/Nm3) (a) (b) |
Dust (or Total
Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including
methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the
exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include
methane as biogas is adopted as fuel in the combustion process. |
To determine the effectiveness of
the proposed odour mitigation measures and to ensure that the operation of the
ORRC1 will not cause adverse odour impacts, odour monitoring of the CAPCS stack
(see Section 3.1.1) and odour patrol will be carried out.
Odour patrol shall be conducted by independent trained personnel/
competent persons in summer months (i.e., from July to September) for the first
two operational years of ORRC1 at monthly intervals along an odour patrol route
at the Project Site boundary as shown in Annex A.
The perceived odour intensity is divided into 5 levels. Table 3.6
describes the odour intensity for different levels.
Table 3.6
Odour Intensity Level
Level |
Odour
Intensity |
0 |
Not detected. No odour perceived or an odour so weak that it
cannot be easily characterised
or described |
1 |
Slight identifiable
odour, and slight
chance to have odour
nuisance |
2 |
Moderate identifiable
odour, and moderate chance to have odour nuisance |
3 |
Strong identifiable,
likely to have odour nuisance |
4 |
Extreme severe
odour, and unacceptable odour level |
Table 3.7 shows the action level and limit level to be
used for odour patrol. Should any exceedance of the action and limit levels
occurs, actions in accordance with the event and action plan in Table 3.8
should be carried out.
Table 3.7
Action and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from
odour patrol) |
When one documented
compliant is received (a), or Odour
Intensity of 2 is measured from odour patrol. |
Two or more documented complaints
are received (a) within a week; or Odour intensity of 3 or above is measured
from odour patrol. |
Note: (a) Once the complaint is received by
the Project Proponent (EPD), the Project Proponent would investigate and
verify the complaint whether it is related to the potential odour emission
from the ORRC1 and its on-site wastewater treatment unit. |
Table 3.8
Event and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project Proponent (a) |
Action Level |
|
|
Exceedance of action
level (Odour Patrol) |
1. Identify
source/reason of exceedance; 2. Repeat odour patrol
to confirm finding. |
1. Carry out
investigation to identify the source/reason of exceedance.
Investigation should be completed within 2 weeks; 2. Rectify any
unacceptable practice; 3. Implement more
mitigation measures if necessary; 4. Inform Drainage
Services Department (DSD) or the operator of the Siu Ho Wan Sewage Treatment
Works (SHWSTW) if exceedance is considered to be caused by the operation of
the SHWSTW; and 5. Inform North Lantau
Refuse Transfer Station (NLTS) operator if exceedance is considered to be
caused by the operation of NLTS. |
Exceedance of action
level (Odour Complaints) |
1. Identify
source/reason of exceedance; 2. Carry out odour
patrol to determinate odour intensity. |
1. Carry out
investigation and verify the complaint whether it is related to potential
odour emission from the nearby SHWSTW; 2. Carry out
investigation to identify the source/reason of exceedance. Investigation
should be completed within 2 weeks; 3. Rectify any
unacceptable practice; 4. Implement more
mitigation measures if necessary; 5. Inform DSD or the
operator of the SHWSTW if exceedance is considered to be caused by the
operation of the SHWSTW; and 6. Inform NLTS
operator if exceedance is considered to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit level |
1. Identify
source/reason of exceedance; 2. Inform EPD; 3. Repeat odour
patrol to confirm findings; 4. Increase odour
patrol frequency to bi-weekly; 5. Assess
effectiveness of remedial action and keep EPD informed of the results; 6. If exceedance
stops, cease additional odour patrol. |
1. Carry out
investigation to identify the source/reason of exceedance. Investigation
should be completed within 2 week; 2. Rectify any
unacceptable practice; 3. Formulate remedial
actions; 4. Ensure remedial
actions properly implemented; 5. If exceedance
continues, consider what more/enhanced mitigation measures should be
implemented; and 6. Inform DSD or the
operator of the SHWSTW if exceedance is considered to be caused by the
operation of the SHWSTW. |
Note: (a) Project Proponent shall identify an
implementation agent. |
Environmental mitigation measures (related to air quality, water
quality, waste, land contamination, hazard-to-life, and landscape and visual)
to be implemented during the operation phase of the Project are recommended in
the approved EIA Report and EM&A Manual and are summarised in Annex C. Monthly site audits
for operation phase will be carried out to check the implementation of these
measures.
Compliance audits are to be undertaken to ensure that a valid discharge
licence has been issued by EPD prior to the discharge of effluent from the
operation of the Project site. Under Effluent Discharge Licence WT00038391-2021
(effective from July 2021), the effluent quality shall meet the discharge
limits as described in Table 3.9 and Table 3.10.
Table 3.9
Discharge Limits for Effluent from the Effluent Storage Tank (as stipulated in
WT00038391-2021)
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day)
(a) |
645 |
pH (pH units) (b) |
6-10 (c) |
Suspended Solids
(b) |
800 |
Biochemical Oxygen
Demand (5 days, 20°) (b) |
800 |
Chemical Oxygen Demand
(b) |
2,000 |
Oil & Grease
(b) |
40 |
Total Nitrogen
(b) |
200 |
Total Phosphorus
(b) |
50 |
Surfactants (total)
(b) |
25 |
Notes: (a) Flow rate is not a parameter required to be
monitored and reported by the Contractor in accordance with Section B2 of the
Effluent Discharge Licence under the WPCO. (b) Parameters required to be monitored and
reported by the Contractor in accordance with Section B2 of the Effluent
Discharge Licence under the WPCO. (c) Range. |
Table 3.10
Discharge Limits for Effluent from the Petrol Interceptor(s) (as stipulated in
TW00038391-2021)
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day)
(a) |
245 (a) |
Suspended Solids
(b) |
30 |
Chemical Oxygen Demand
(c) |
80 |
Oil & Grease
(c) |
20 |
Surfactants (total)
(b) |
15 |
Notes: (a) The surface runoff flow rate limit was estimated
by the overall yearly rainfall data. As the actual flowrate from the petrol
interceptors depends on the weather condition instead of the performance of
the petrol interceptor, monitoring and reporting of this parameter is not
required. Hence this parameter is not reported in Table 4.10 and Table
4.11. (b) Parameter not required to be reported in accordance
with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Parameters required to be reported
in accordance with Section B2 of the Effluent Discharge Licence under the
WPCO. |
In accordance with EM&A Manual, the landscape and visual mitigation
measures shall be implemented.
For operation phase, site inspection shall be conducted once a month for
the first year of operation of the Project. All measures as stated in the
implementation schedule of the EM&A Manual (see Annex C), including
compensatory planting, undertaken by both the Contractor and the specialist
Landscape Sub-Contractor during the first year of the operation phase shall be
audited by a Registered Landscape Architect (RLA) to ensure compliance with the
intended aims of the measures and the effectiveness of the mitigation measures.
The concentrations of concerned air pollutants emitted from the stacks
of the CAPCS, CHP, and ASP during the reporting period are monitored on-line by
the continuous environmental monitoring system (CEMS). During the reporting
period, the standby flare operated on 2, 8, 13, 14, 15, 16, 19, 21, 23, and 30
December 2022, as well as on 5, 6, 9, 10, 11, and 12 January 2023. The standby
flare did not operate during February 2023.
With reference to the emission limits shown in Tables 3.2, 3.3, 3.4 and
3.5, the hourly average concentrations and the number of exceedances of the
concerned air emissions monitored for the CAPCS, CHP and ASP during this
reporting period are presented in Tables 4.1 to 4.6.
It should be noted that measurements recorded under abnormal operating
conditions, e.g., start up and stopping of stacks and unstable operation, as
well as test runs and interference of sensor, are disregarded.
Table 4.1
Hourly Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) |
Emission Limit
(mg/Nm3) |
Exceedance
Identified |
Remarks |
VOCs (including
methane) |
0.00 – 679.50 |
680 |
Nil |
Nil |
Dust (or TSP) |
0.00 – 0.40 |
6 |
Nil |
Nil |
Odour (including NH3
& H2S) (a) |
0.00 – 107.90 |
220 |
Nil |
Nil |
Note: (a) The odour unit is OU/Nm3. (b) The CEMS was under maintenance on 16 December
2022. |
Table 4.2
Hourly Average of Parameters Recorded for CHP 1
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust
(or TSP) |
0 - 15 |
15 |
Nil |
Nil |
Carbon
Monoxide |
0 - 135 |
650 |
Nil |
Nil |
NOx |
0 – 565 |
300 |
Identified
(c) |
System
unstable (e.g., low efficiency, unstable column temperature) |
SO2 |
0 – 353 |
50 |
Identified (d) |
De-sulphurisation
system tripped / Under Maintenance |
VOCs
(including methane) |
0 - 1,318 |
1,500 |
Nil |
Nil |
HCl |
0 - 16 |
10 |
Identified (e) |
System unstable (e.g.,
low efficiency, unstable column temperature) |
HF |
0 - 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust
gas of 6% and
dry basis. (b) The VOCs emission limit includes methane as
biogas is adopted as fuel in the combustion process. (c) Dates with NOx
exceedances (number of exceedances on the day) were identified on 14 (11), 15
(22), 16 (24), 17 (4), 28 (11), 29 (10), and 30 (11) December 2022; 2 (2), 3
(1), 4 (1), 5 (2), 7 (2), 8 (13), 9 (13), 10 (14), 11 (15), 12 (1), 13 (19),
14 (13), 27 (8), 28 (24), 29 (24), 30 (24), and 31 (11) January 2023; 1 (11),
2 (7), 3 (3), 9 (1), 10 (2), 11 (12), 12 (24), 13 (24), 14 (24), 15 (24), 16
(19), 18 (19), 19 (23), 20 (16), 21 (11), 22 (24), 23 (14), 24 (24), 25 (10),
26 (14), 27 (24), and 28 (19) February 2023. (d) Dates with SO2 exceedances (number
of exceedances on the day) were identified on 15 (1), 17 (2), 28 (8), 29 (13)
and 30 (9) December 2022; 27 (4), 28 (11), 29 (15),
30 (24), and 31 (13) January 2023; 1 (11), 2 (7), 3 (3), 9 (1),
10 (1), 11 (6), 12 (9), 13 (8), 14 (2), 15 (11), 16 (8), 21 (6), 22 (24), 23
(13), 24 (21), 25 (8), 26 (6), 27 (11), and 28 (18) February 2023. (e) Date with HCl exceedance (number of
exceedances on that day) was identified on 13 (1) February 2023. |
Table 4.3
Hourly Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) (a) |
Max. Emission
Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 13 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 405 |
650 |
Nil |
Nil |
NOx |
0 – 543 |
300 |
Identified (c) |
System unstable (e.g.,
low efficiency, unstable column temperature) |
SO2 |
0 – 345 |
50 |
Identified (d) |
De-sulphurisation
system tripped / Under Maintenance |
VOCs
(including methane) (b) |
0 – 989 |
1,500 |
Nil |
Nil |
HCl |
0 – 28 |
10 |
Identified (e) |
System unstable (e.g.,
low efficiency, unstable column temperature) |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust
gas of 6% and
dry basis. (b) The VOCs emission limit includes methane as
biogas is adopted as fuel in the combustion process. (c) Dates with NOx
exceedances (number of exceedances on the day) were identified on 1 (10), 2
(18), 3 (24), 4 (23), 5 (11), 6 (19), 7 (15), 8 (9), 9 (10), 10 (8), 11 (24),
12 (2), 13 (4), 17 (15), 18 (24), 19 (15), 20 (11), 21 (7), 22 (11), 23 (9),
25 (4), 26 (3), 27 (24), 28 (8) and 30 (3) December 2022; 1 (24), 2 (24), 3
(24), 4 (19), 5 (24), 6 (19), 7 (24), 8 (24), 9 (12), 10 (3), 11 (1), 12
(13), 13 (2), 16 (7), 17 (24), 18 (24), 19 (24), 20 (24), 21 (14), 23 (20),
24 (24), 25 (24), 26 (24), 27 (14), 29 (1), and 31 (6) January 2023; 3 (19),
4 (24), 5 (24), 6 (24), 7 (22), 8 (24), 9 (24), 10 (24), 11 (13), 16 (4), 17
(24), 18 (21), 19 (18), 20 (23), 21 (19), 23 (12), and 24 (1) February 2023. (d) Dates with SO2 exceedances (number
of exceedance on the day) were identified on 1 (18), 2 (15), 3 (15), 4 (12),
5 (1), 13 (2), 17 (15), 18 (17), 19 (7), 20 (5), 21 (5), 22 (9), 23 (9), 25
(14), 26 (4), 27 (24), 28 (8), 30 (11), and 31 (24) December 2022; 1 (24), 2
(24), 3 (24), 4 (19), 5 (24), 6 (14), 7 (12), 8 (17), 9 (11), 10 (3), 11 (1),
12 (9), 16 (7), 17 (24), 18 (22), 19 (18), 20 (13), 23 (20), 24 (24), 25
(24), 26 (24), 27 (14), 29 (1), and 31 (6) January 2023; 3 (19), 4 (24), 5
(24), 6 (24), 7 (24), 8 (23), 9 (24), 10 (23), 11 (14), 16 (2), 17 (10), 18
(7), 20 (15), 21 (22), 23 (6), and 24 (1) February 2023. (e) Date with HCl exceedance (number of
exceedances on that day) was identified on 19 (4) December 2022. |
Table 4.4
Hourly Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) (a) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 7 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 81 |
650 |
Nil |
Nil |
NOx |
0 – 592 |
300 |
Identified (c) |
System unstable (e.g.,
low efficiency, unstable column temperature) |
SO2 |
0 – 203 |
50 |
Identified (d) |
Desulphurisation
system tripped / Under Maintenance |
VOCs
(including methane) (b) |
0 – 1,018 |
1,500 |
Nil |
Nil |
HCl |
0 – 9 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an
oxygen content in the exhaust gas of 6% and dry basis. (b) The VOCs emission
limit includes methane as biogas is adopted as fuel in the combustion
process. (c) Dates with NOx exceedances (number of exceedances on the day) were identified on 20
(2), 21 (5), 22 (11), 23 (10), 24 (14), 25 (8), 26 (6), 28 (1), 29 (6), and
30 (6) December 2022; 14 (8), 15 (24), 16 (11), 21 (7), and 22 (16) January
2023; 12 (1), 13 (10), 14 (19), 15 (21), 16 (7), 17 (2), 22 (2), 24 (1), 25
(4), 27 (3), and 28 (4) February 2023. (d)
Dates with SO2 exceedances (number of exceedance on the day) was identified on 20
(4), 21 (3), 22 (8), 23 (2), 24 (21), 25 (14), 26 (21), 28 (2), 29 (10), and
30 (6) December 2022; 14 (3), 15 (18), 16 (6) and, 22 (1) January 2023; 11
(4), 12 (3), 13 (7), 14 (4), 15 (10), 16 (4), 17 (2), 22 (3), 24 (1), 25 (8),
and 28 (4) February 2023. |
Table 4.5
Hourly Average of Parameters Recorded for ASP
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 2 |
5 |
Nil |
Nil |
Carbon Monoxide |
0 – 94 |
100 |
Nil |
Nil |
NOx |
0 – 641 |
200 |
Identified (c)
|
System unstable (e.g.,
low efficiency, unstable column temperature) |
SO2 |
0 – 440 |
50 |
Identified (d)
|
Desulphurisation
system tripped |
VOCs
(including methane) (b) |
0 – 20 |
20 |
Nil |
Nil |
NH3 |
0 – 326 |
35 |
Identified (e)
|
System unstable (e.g.,
low efficiency, unstable column temperature) |
HCl |
0 – 2 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the
exhaust gas of 11% and dry basis. (b) The VOCs emission limit include methane as biogas
is adopted as fuel in the combustion process. (c) Dates with NOx exceedances (number of exceedances on the day) were identified on 2
(2), 3 (9), 4 (11), 5 (3), 6 (4), 8 (6), 9 (2), 10 (1), 12 (2), 13 (1), 14
(2), 16 (3), 17 (3), 18 (4), 19 (1), 21 (6), 22 (1), 27 (1), 28 (1), and 31
(1) December 2022; 2 (2), 3 (1), 6 (2), 8 (2), 12 (3), 13 (10), 14 (13), 15
(6), 16 (2), 18 (2), 20 (1), 22 (6), 23 (13), 24 (4), 25 (2), 26 (12), 27
(12), 28 (9), 29 (7), 30 (23), and 31 (17) January 2023; 1 (1), 2 (7), 3
(18), 6 (5), 7 (1), 12 (3), 13 (4), 14 (6), 15 (3), 16 (11), 22 (2), 23 (1),
24 (3), 25 (3), 26 (11), 27 (4) and 28 (1) February 2023. (d) Dates with SO2 exceedances (number
of exceedances on the day) were identified on 8 (1), 20 (4), 29 (4), and 31
(2) December 2022; 6 (1), 28 (8), 29 (18), 30 (24), and 31 (20) January 2023;
1 (10), 10 (1), 12 (1), 25 (1), and 26 (1) February 2023. (e) Dates with NH3 exceedances (number
of exceedances on the day) were identified on 1 (6), 3 (1), 5 (3), 6 (1), 8
(1), 9 (1), 10 (4), 13 (1), 14 (1), 15 (1), 18 (3), 19 (3), 21 (4), 23 (2),
24 (4), 25 (5), 26 (1), 27 (4), and 29 (2) December 2022; 1 (7), 2 (4), 3
(5), 4 (11), 5 (10), 6 (21), 7 (12), 9 (14), 10 (6), 11 (11), 12 (5), 13 (1),
19 (1), 20 (5), 23 (2), 27 (2), and 31 (1) January 2023; 1 (3), 2 (1), 7 (2),
8 (6), 9 (7), 10 (14), 11 (18), 12 (3), 13 (12), 14 (6), 15 (1), 16 (11), 17
(24), 18 (24), 19 (23), 20 (24), 21 (19), 22 (24), 23 (16), 24 (21), 25 (21),
26 (14), 27 (21), and 28 (11) February 2023. |
Table
4.6 Hourly Average of
Parameters Recorded for the Standby Flaring Gas Unit
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a)(c) |
Max. Emission
Limit (mg/Nm3) |
Exceedances Identified |
Remarks (d) |
Dust (or TSP) |
0 – 0 |
5 |
Nil |
Nil |
Carbon Monoxide |
0 – 1,217 |
100 |
Identified (e) |
Nil |
NOx |
0 – 581 |
200 |
Identified (f) |
Nil |
SO2 |
0 – 271 |
50 |
Identified (g)
|
Nil |
VOCs
(including methane) (b) |
0 – 3,758 |
20 |
Identified (h) |
Nil |
HCl |
0 – 50 |
10 |
Identified (i) |
Nil |
HF |
0 – 6 |
1 |
Identified (j) |
Nil |
Notes: (a) All values refer to an oxygen content in the
exhaust gas of 11% and dry basis. (b) The VOCs emission limit include methane as
biogas is adopted as fuel in the combustion process. (c) During the reporting period, the
standby flare operated on 2, 8, 13, 14, 15, 16, 19, 21, 23, and 30 December
2022, as well as on 5, 6, 9, 10, 11, and 12 January 2023. (d) All exceedances of the parameters on 2, 8,
13, 14, 15, 16, 19, 21, 23, and 30 December 2022, as well as on 5, 6, 9, 10,
11, and 12 January 2023 were caused by the biogas bypass trial conducted
during this reporting period. (e) Dates with Carbon Monoxide exceedances
(number of exceedances on the day) were identified on 8 (2), 13 (2), 14 (1),
15 (2), 16 (2), 19 (1), and 21 (2) December 2022; 5 (3), 9 (2), and 11 (1)
January 2023. (f) Dates with NOx
exceedances (number of exceedances on the day) were identified on 21 (1)
2022. (g) Date with SO2 exceedances (number
of exceedances on the day) were identified on 13 (1), 14 (1), 15 (2), 16 (1),
19 (1) and 21 (2) December 2022. (h) Date with VOCs exceedances (including
methane) (number of exceedances on the day) were identified on 8 (2), 13 (2),
14 (1), 15 (2), 16 (2), 19 (1), 21 (2), and 30 (1) December 2022; 5 (3), 9
(8), 10 (20), 11 (21), and 12 (8) January 2023. (i) Date with HCl exceedances (number
of exceedances on the day) were identified on 13 (1), 14 (1), 15 (2), 16 (1),
and 21 (2) December 2022; 5 (1) January 2023. (j) Date with HF exceedances (number
of exceedances on the day) were identified on 2 (2), 8 (2), 13 (2), 14 (1),
15 (2), 16 (2), 19 (1), 21 (2), and 30 (2) December 2022; 5 (3), 9 (5), 11
(1), and 12 (2) January 2023. |
No odour patrol was required to be conducted for this reporting period.
Effluent discharge was sampled monthly from the outlet chamber of the
Effluent Storage Tank as stipulated in the operation phase discharge licence.
Discharge from the Petrol Interceptors were sampled bi-monthly since July 2021
as stipulated in the operation phase discharge licence. The results of the
discharge samples from the outlet chamber of the Effluent Storage Tank are
recorded in Table 4.7 to 4.9. The results of the discharge
samples from the Petrol Interceptors are recorded in Table 4.10 to
4.13.
Table 4.7
Results of the Discharge Sample Collected from the Outlet Chamber of the
Effluent Storage Tank in December 2022
Parameters |
Discharged
Effluent Concentration (mg/L) |
Discharge Limit
(mg/L) |
Compliance with
Discharge Limit |
Flow Rate (m3/day)
(a) |
56 - 255 (e) |
645 |
Yes |
pH (pH units) (b) |
7.89 – 9.13 (e) |
6-10 (c) |
Yes |
Suspended Solids (b)
(d) |
114 (d) |
800 |
Yes |
Biochemical Oxygen
Demand (5 days, 20°) (b) (d) |
23 (d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
795 (d) |
2,000 |
Yes |
Oil & Grease (b)
(d) |
<5 (d) |
40 |
Yes |
Total Nitrogen (b)
(d) |
67.70 (d) |
200 |
Yes |
Total Phosphorus (b)
(d) |
15.80 (d) |
50 |
Yes |
Surfactants (total)
(b) (d) |
<1.00 (d) |
25 |
Yes |
Notes: (a) Parameter not required to be reported in accordance
with Section B2 of the Effluent Discharge Licence under the WPCO. (b) Parameters required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Daily Range. (d) Effluent sample collected on 8 December 2022. (e) Data collected daily in the reporting month. |
Table 4.8
Results of the Discharge Sample Collected from the Outlet Chamber of the
Effluent Storage Tank in January 2023
Parameters |
Discharged
Effluent Concentration (mg/L) |
Discharge Limit
(mg/L) |
Compliance with
Discharge Limit |
Flow Rate (m3/day)
(a) |
58 - 218 (e) |
645 |
Yes |
pH (pH units) (b) |
7.59 – 8.36 (e) |
6-10 (c) |
Yes |
Suspended Solids (b)
(d) |
111 (d) |
800 |
Yes |
Biochemical Oxygen
Demand (5 days, 20°) (b) (d) |
72 (d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
976 (d) |
2,000 |
Yes |
Oil & Grease (b)
(d) |
<5 (d) |
40 |
Yes |
Total Nitrogen (b)
(d) |
66.9 (d) |
200 |
Yes |
Total Phosphorus (b)
(d) |
10.5 (d) |
50 |
Yes |
Surfactants (total)
(b) (d) |
1.9 (d) |
25 |
Yes |
Notes: (a) Parameter not required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (b) Parameters required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Daily Range. (d) Effluent sample collected on 19 January 2023. (e) Data collected daily in the reporting month. |
Table 4.9
Results of the Discharge Sample Collected from the Outlet Chamber of the
Effluent Storage Tank in February 2023
Parameters |
Discharged
Effluent Concentration (mg/L) |
Discharge Limit
(mg/L) |
Compliance with
Discharge Limit |
Flow Rate (m3/day)
(a) |
63 – 266 (e) |
645 |
Yes |
pH (pH units) (b) |
8.04 – 8.76 (e) |
6-10 (c) |
Yes |
Suspended Solids (b)
(d) |
62 (d) |
800 |
Yes |
Biochemical Oxygen
Demand (5 days, 20°) (b) (d) |
16 (d) |
800 |
Yes |
Chemical Oxygen Demand (b) (d) |
889 (d) |
2,000 |
Yes |
Oil & Grease (b)
(d) |
<5 (d) |
40 |
Yes |
Total Nitrogen (b)
(d) |
75.30 (d) |
200 |
Yes |
Total Phosphorus (b)
(d) |
10.90 (d) |
50 |
Yes |
Surfactants (total)
(b) (d) |
<1.0 (d) |
25 |
Yes |
Notes: (a) Parameter not required to be reported in accordance
with Section B2 of the Effluent Discharge Licence under the WPCO. (b) Parameters required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Daily Range. (d) Effluent sample collected on 28 February
2023. (e) Data collected daily in the reporting month. |
Table 4.10
Results of the Discharge Sample from the Petrol Interceptor 1 on 8 December
2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended
Solids (b) |
8 (a) |
30 |
Yes |
Chemical
Oxygen Demand (c) |
14 (a) |
80 |
Yes |
Oil
& Grease (c) |
<5
(a) |
20 |
Yes |
Surfactants
(total) (b) |
<1.0
(a) |
15 |
Yes |
Notes: (a) Effluent sample collected on 8 December 2022. (b) Parameter not required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Parameters required to be reported
in accordance with Section B2 of the Effluent Discharge Licence under the
WPCO. |
Table 4.11
Results of the Discharge Sample from the Petrol Interceptor 1 on 23 February
2023
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended
Solids (b) |
46 (a) |
30 |
No |
Chemical
Oxygen Demand (c) |
102 (a) |
80 |
No |
Oil
& Grease (c) |
6
(a) |
20 |
Yes |
Surfactants
(total) (b) |
<1.0
(a) |
15 |
Yes |
Notes: (a) Effluent sample collected on 23 February
2023. (b) Parameter not required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Parameters required to be reported
in accordance with Section B2 of the Effluent Discharge Licence under the
WPCO. |
Table 4.12
Results of the Discharge Sample from the Petrol Interceptor 2 on 8 December
2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended
Solids (b) |
4
(a) |
30 |
Yes |
Chemical
Oxygen Demand (c) |
22
(a) |
80 |
Yes |
Oil
& Grease (c) |
<5
(a) |
20 |
Yes |
Surfactants
(total) (b) |
<1.0
(a) |
15 |
Yes |
Notes: (a) Effluent sample collected on 8 December 2022. (b) Parameter not required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Parameters required to be reported
in accordance with Section B2 of the Effluent Discharge Licence under the
WPCO. |
Table 4.13
Results of the Discharge Sample from the Petrol Interceptor 2 on 23 February
2023
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended
Solids (b) |
17
(a) |
30 |
Yes |
Chemical
Oxygen Demand (c) |
297
(a) |
80 |
No |
Oil
& Grease (c) |
<5
(a) |
20 |
Yes |
Surfactants
(total) (b) |
2.0
(a) |
15 |
Yes |
Notes: (a) Effluent sample collected on 23 February
2023. (b) Parameter not required to be reported in
accordance with Section B2 of the Effluent Discharge Licence under the WPCO. (c) Parameters required to be reported
in accordance with Section B2 of the Effluent Discharge Licence under the
WPCO. |
Non-compliance of discharge limits of Suspended Solids and Chemical
Oxygen Demand from Petrol Interceptor 1 and Chemical Oxygen Demand from Petrol
Interceptor 2 were recorded during the reporting period. The exceedances of
Suspended Solids and Chemical Oxygen Demand occurred due to the dry season with
less rainfall, resulting in discharge water containing higher concentrations
for the exceeded parameters.
Wastes generated from the operation of the Project include chemical
waste, wastes generated from pre-treatment process and general refuse ([3]).
Reference has been made to the Monthly Summary Waste Flow Tables prepared by
the Contractor (see Annex D).
With reference to the relevant handling records and trip tickets of this
Project, the quantities of different types of waste generated from the
operation of the Project in the reporting period are summarised in Table
4.14.
Table 4.14
Quantities of Waste Generated from the Operation of the Project
Month / Year |
Chemical Waste |
Waste Generated from |
General Refuse |
||
|
Disposal of at CWTC |
Disposed of at Landfill (a) |
Recycled (b) |
Disposed of at Landfill (a) (e) |
Recycled (c) |
December 2022 |
0 L |
666.42 tonnes |
0.00 tonnes |
3.57 tonnes |
0.091 tonnes |
January 2023 |
1,200 L (d) |
581.55 tonnes |
0.99 tonnes |
2.65 tonnes |
0.004 tonnes |
February 2023 |
5,540 L (d) |
643.75 tonnes |
0.36 tonnes |
2.76 tonnes |
0.018 tonnes |
Notes: (a) Waste generated from pre-treatment
process and general refuse other than chemical waste and recyclables were
disposed of at NENT landfill by sub-contractors. (b) Among waste generated from pre-treatment
process, 0.969 tonnes of metals, 0.360 tonnes of papers/ cardboard packing
and 0.021 tonnes of plastics were sent to recyclers for recycling during the
reporting period. (c) Among general refuse, 0.004 tonnes
of metals, 0.044 tonnes of papers/ cardboard packing and 0.065 tonnes of
plastics were sent to recyclers for recycling during the reporting period. (d) 1,200 L of spent lube oil were disposed of at
CWTC in January 2023, and 5,540 L of chemical waste was disposed of at CWTC
in February 2023. (e) It was assumed that four 240-litre bins
filled with 80% of general refuse were collected at each collection. The
general refuse density was assumed to be around 0.15 kg/L. |
The monthly inspections of the
operation phase of the Project covered the operation phase environmental site
inspections. The inspections checked the implementation of the recommended
mitigation measures for air quality, landscape and visual, water quality, waste
(land contamination) and hazard-to-life stated in the Implementation Schedule
(see Annex C).
Follow-up actions resulting from the
site inspections were generally taken as reported by the Contractor. The
Contractor has implemented environmental mitigation measures recommended in the
approved EIA Report and EM&A Manual.
December 2022
The monthly inspection of the
operation phase of the Project on 21 December 2022 covered the operation phase
environmental site audit. Joint site inspections were conducted by
representatives of the Contractor, IEC and the MT on 21 December 2022 as required
for the operation of the Project.
January 2023
The monthly inspection of the
operation phase of the Project on 30 January 2023 covered the operation phase
environmental site audit. Joint site inspections were conducted by
representatives of the Contractor, IEC and the MT on 30 January 2023 as
required for the operation of the Project.
February 2023
The monthly inspection of the
operation phase of the Project on 28 February 2023 covered the operation phase environmental
site audit. Joint site inspections were conducted by representatives of the
Contractor, IEC and the MT on 28 February 2023 as required for the operation of
the Project.
It was confirmed that the necessary landscape and visual mitigation
measures during the operation phase as summarised in Annex C were generally
implemented by the Contractor. No non-compliance in relation to the landscape
and visual mitigation measures was identified during the site audits in this
reporting period and therefore no further actions are required. The ET/MT will
keep track of the EM&A programme to check compliance with environmental
requirements and the proper implementation of all necessary mitigation
measures.
December 2022
Monthly inspection of
the landscape and visual mitigation measures for the operation phase of the
Project was performed on 21 December 2022.
January 2023
Monthly inspection of
the landscape and visual mitigation measures for the operation phase of the
Project was performed on 30 January 2023.
February 2023
Monthly inspection of
the landscape and visual mitigation measures for the operation phase of the
Project was performed on 28 February 2023.
December 2022
Non-compliance of
emission limits of SO2 and NOx from the CHPs; HCl from
CHP2; NOx, SO2 and NH3 from ASP; and CO, NOx,
SO2, VOCs, HCl, and HF from Standby Flaring Gas Unit were recorded
during the reporting period.
The Contractor has
reviewed the organic waste treatment processes (i.e., waste reception, waste
pre-treatment, anaerobic digesters, and composting processes) and found that
they were operated normally during the reporting period. The Contractor has
investigated the CHPs, the de-sulphurisation system and the ASP, the potential
causes for the exceedance were identified.
The investigation
reports of the above exceedances are presented in Annex F.
January 2023
Non-compliance of
emission limits of NOx and SO2 from the CHPs; NOx,
SO2 and NH3 from ASP; and CO, VOCs, HCl and HF from
Standby Flaring Gas Unit were recorded during the reporting period.
The Contractor has
reviewed the organic waste treatment processes (i.e., waste reception, waste
pre-treatment, anaerobic digesters, and composting processes) and found that
they were operated normally during the reporting period. The Contractor has
investigated the CHPs, the de-sulphurisation system and the ASP, the potential
causes for the exceedance were identified.
The investigation
reports of the above exceedances are presented in Annex F.
February 2023
Non-compliance of
emission limits of NOx and SO2 from the CHPs; HCl from
CHP 1; NOx, SO2 and NH3 from ASP, and
non-compliance of discharge limits of Suspended Solids and Chemical Oxygen
Demand from Petrol Interceptor 1 and Chemical Oxygen Demand from Petrol
Interceptor 2 were recorded during the reporting period.
The Contractor has
reviewed the organic waste treatment processes (i.e., waste reception, waste
pre-treatment, anaerobic digesters, and composting processes) and found that
they were operated normally during the reporting period. The Contractor has
investigated the de-sulphurisation system, CHPs and the ASP, the potential
causes for the exceedance were identified.
The Contractor has
also carried out checking on the relevant Petrol Interceptors and suspected
that the exceedances of Suspended Solids and Chemical Oxygen Demand may have
occurred due to the dry season with less rainfall, resulting in discharge water
containing higher concentrations for the exceeded parameters.
The investigation
reports of the above exceedances are presented in Annex F.
Activities to be undertaken for the coming reporting period are:
·
Operation of the
Project; and
·
SBR Cleaning and
Diffuser replacement works.
This EM&A Report presents the EM&A programme undertaken during
the reporting period from December 2022 to February 2023 in
accordance with EM&A Manual (Version F) and requirements of EP
(FEP-01/395/2010/C).
For the operation phase, exceedances of the emission limits for stack
monitoring (including CAPCS, CHP, ASP and Standby Flaring Gas Unit stacks) were
recorded under normal operating conditions during the reporting period (see
Table 8.1).
Table 8.1
Exceedances for Stack Emissions
Stack |
Exceedances During
the Reporting Period |
Centralised Air
Pollution Control Unit (CAPCS) |
· Nil |
Cogeneration Unit
(CHP) 1 |
· Exceeded emission limit of NOx on 14,
15, 16, 17, 28, 29, and 30 December 2022; 2, 3, 4, 5, 7, 8, 9, 10, 11, 12,
13, 14, 27, 28, 29, 30, and 31 January 2023; 1, 2, 3, 9, 10, 11, 12, 13, 14,
15, 16, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, and 28 February 2023. · Exceeded emission limit of SO2 on
15, 17, 28, 29, and 30 December 2022; 27, 28, 29, 30, and 31 January 2023; 1,
2, 3, 9, 10, 11, 12, 13, 14, 15, 16, 21, 22, 23 24, 25, 27, and 28 February
2023. · Exceeded emission limit of HCl on 13 February
2023. |
Cogeneration Unit
(CHP) 2 |
· Exceeded emission limit of NOx
on 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 17, 18, 19, 20, 21, 22, 23, 25,
26, 27, 28, and 30 December 2022; 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13,
16, 17, 18, 19, 20, 21, 23, 24, 25, 26, 27, 29, and 31 January 2023; 3, 4, 5,
6, 7, 8, 9, 10, 11, 16, 17, 18, 19, 20, 21, 23, and 24 February 2023. · Exceeded emission limit of SO2
on 1, 2, 3, 4, 5, 13, 17, 18, 19, 20, 21, 22, 23, 25, 26, 27, 28, 30, and 31
December 2022; 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 16, 17, 18, 19, 20, 23,
24, 25, 26, 27, 29, and 31 January 2023; 3, 4, 5, 6, 7, 8, 9, 10, 11, 16, 17,
18, 20, 21, 23, and 24 February 2023. · Exceeded emission limit of HCl on
19 December 2022. |
Cogeneration Unit
(CHP) 3 |
· Exceeded emission limit of NOx on
20, 21, 22, 23, 24, 25, 26, 28, 29, and 30 December 2022; 14, 15, 16, 21, and 22 January 2023; 12, 13, 14, 15, 16,
17, 22, 24, 25, 27, and 28 February 2023. · Exceeded emission limit of SO2 on
20, 21, 22, 23, 24, 25, 26, 28, 29 and 30 December 2022; 14, 15, 16 and 22 January 2023; on 11, 12, 13, 14, 15,
16, 17, 22, 24, 25, and 28 February 2023. |
Ammonia Stripping
Plant (ASP) |
· Exceeded emission limit of NOx on
2, 3, 4, 5, 6, 8, 9, 10, 12, 13, 14, 16, 17, 18, 19, 21, 22, 27, 28, and 31
December 2022; 2, 3, 6, 8, 12, 13, 14, 15, 16, 18,
20, 22, 23, 24, 25, 26, 27, 28, 29, 30, and 31 January 2023; 1, 2, 3,
6, 7, 12, 13, 14, 15, 16, 22, 23, 24, 25, 26, 27, and 28 February 2023. · Exceeded emission limit of SO2 on
8, 20, 29, and 31 December 2022; 6, 28, 29, 30, and 31 January 2023; 1, 10,
12, 25, and 26 February 2023. · Exceeded emission limit of NH3 on 1,
3, 5, 6, 8, 9, 10, 13, 14, 15, 18, 19, 21, 23, 24, 25, 26, 27, and 29
December 2022; 1, 2, 3, 4, 5, 6, 7, 9, 10, 11, 12, 13, 19, 20, 23, 27, and 31
January 2023; 1, 2, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21,
22, 23, 24, 25, 26, 27, and 28 February 2023. |
Standby Flaring Gas
Unit |
· Exceeded emission limit of Carbon Monoxide on
8, 13, 14, 15, 16, 19, and 21 December 2022; 5, 9, and 11 January 2023. · Exceeded emission limit of NOx on 21 December
2022; · Exceeded emission limit of SO2 on
13, 14, 15, 16, 19, and 21 December 2022; · Exceeded emission limit of VOCs on 8, 13, 14,
15, 16, 19, 21, and 30 December 2022; 5, 9, 10, 11, and 12 January 2023. · Exceeded emission limit of HCL on 13, 14, 15,
16, and 21 December 2022; 5 January 2023. · Exceeded emission limit of HF on 2, 8, 13,
14, 15, 16, 19, 21, and 30 December 2022; 5, 9, 11, and 12 January 2023. |
Non-compliance of emission limits of SO2 and NOx
from the CHPs, HCl from CHP2, NOx, SO2 and NH3
from ASP and CO, NOx, SO2, VOCs, HCl and HF from Standby
Flaring Gas Unit were recorded during December 2022. The exceedances of SO2
from CHPs and the ASP occurred due to tripping of the de-sulphurisation system
caused by the failure of one of the columns of the system. The exceedances of
HCl from CHP 2 in mid-December occurred due to system instability. The
exceedance of NOx and NH3 from CHPs and ASP occurred due
to system instability caused by the ongoing performance optimisation of the ASP
and CHPs, resulting in a lowered temperature of the system and the incomplete
combustion of biogas. The exceedances of CO, NOx, SO2,
VOCs, HCl and HF from Standby Flaring Gas Unit occurred due to the biogas
bypass trial.
Non-compliance of emission limits of NOx
and SO2 from the CHPs, NOx, SO2, NH3
from ASP and CO, VOCs, HCl and HF from Standby Flaring Gas Unit were recorded
during January 2023. The exceedances of SO2 from CHPs and the ASP
occurred due to tripping of the de-sulphurisation system caused by the failure
of one of the columns of the system. The exceedances of NOx from
CHPs in January 2023 occurred due to insufficient feedstock. The exceedance of
NOx and NH3 from ASP occurred due to system instability
caused by the ongoing performance optimisation of the ASP, resulting in a
lowered temperature of the system and the incomplete combustion of biogas. The
exceedances of CO, VOCs, HCl and HF from Standby Flaring Gas Unit occurred due
to biogas bypass trial.
Non-compliance of emission limits of NOx
and SO2 from the CHPs, HCl from CHP 1 and NOx, SO2
and NH3 from ASP were recorded during February 2023. The exceedances
of SO2 from CHPs and the ASP occurred due to tripping of the
de-sulphurisation system caused by the failure of one of the columns of the
system. The exceedance of NOx, NH3 and HCl from ASP occurred due to
system instability caused by the ongoing performance optimisation of the CHP 1
and ASP, resulting in a lowered temperature of the system and the incomplete
combustion of biogas.
Table 8.2
Exceedances for Petrol Interceptor 1 and 2
Effluent Discharge
Point |
Exceedances During
the Reporting Period |
Petrol Interceptor 1 |
· Exceeded discharge limit of Suspended Solid
on 23 February 2023. · Exceeded discharge limit of Chemical Oxygen
Demand on 23 February 2023. |
Petrol Interceptor 2 |
· Exceeded discharge limit of Chemical Oxygen
Demand on 23 February 2023. |
There were no exceedances recorded
during December 2022. However, non-compliance of discharge limit of Suspended
Solids and Chemical Oxygen Demand from Petrol Interceptor 1 and Chemical Oxygen
Demand from Petrol Interceptor 2 were recorded during February 2023. The Contractor
suspected that the reason for the exceedances of the parameters was due to a
lack of rainfall during the dry season, leading to an increase in the level of
the exceeded parameters. The Contractor will further arrange a clean-up of the
interceptors to make sure the discharge effluents comply with the discharge
limit.
The environmental control /mitigation measures related to air quality,
water quality, waste (including land contamination prevention), hazard-to-life
and landscape and visual recommended in the approved EIA Report and the
EM&A Manual were properly implemented by the Contractor during the
reporting period.
Monthly landscape and visual monitoring were conducted in the reporting
period. The necessary landscape and visual mitigation measures recommended in
the approved EIA Report were generally implemented by the Contractor.
No complaint/summon/prosecution was received.
([1])
As some of the minor items are yet to be closed out in
March 2019, the construction phase EM&A programme and Operation Phase
EM&A programme were undertaking in parallel in March 2019.