Contents
Executive Summary
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Major Activities Undertaken
2.4 Project Organisation and Management Structure
2.5 Status of Environmental Approval Documents
3 Environmental Monitoring and Audit Requirements
3.1 Environmental Monitoring
3.1.1 Air Quality
3.1.2 Odour
3.2 Site Audit
3.2.1 Water Quality
3.2.2 Landscape and Visual
4.1 Air Quality
4.1.1 Commissioning Phase Monitoring
4.1.2 Operation Phase Monitoring
4.2 Odour
4.2.1 Commissioning Phase Monitoring
4.2.2 Operation Phase Monitoring
4.3 Water Quality
4.3.1 Construction Phase Monitoring
4.3.2 Operation Phase Monitoring
4.4 Waste Management
4.4.1 Construction Phase Monitoring
4.4.2 Operation Phase Monitoring
5.1 Environmental Site Audit
5.1.1 Construction Phase
5.1.2 Operation Phase
5.2 Landscape and Visual Audit
6 Environmental Non-conformance
6.1 Summary of Environmental Non-Compliance
6.2 Summary of Environmental Complaint
6.3 Summary of Environmental Summon and Successful Prosecution
7.1 Key Issues for the Coming Reporting Period
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
|
Annex F |
|
Annex G |
|
Annex H |
|
Annex I |
Environmental complaint, Environmental Summons and Prosecution Log |
Annex J |
EXECUTIVE SUMMARY
The construction works of No. EP/SP/61/10 Organic Resources Recovery Centre Phase 1 (the Project) commenced on 21 May 2015. This is the 19th quarterly Environmental Monitoring and Audit (EM&A) report presenting the EM&A works carried out during the period from 1 December 2019 to 29 February 2020 in accordance with the EM&A Manual. Substantial completion of the construction works was confirmed on 3 December 2018. In the meantime, the operation phase EM&A programme had commenced in March 2019. Substantial Completion in respect of substantial part of the Works was confirmed on 24 February 2020. The construction phase EM&A programme was completed in the end of February 2020.
Summary of Works undertaken during the Reporting Month
Works undertaken in the reporting month included:
· Operation of the Project, including organic waste reception, and operation of the pre-treatment facilities, anaerobic digesters, composting facilities, air pollution control systems, on-line emission monitoring system for the Centralised Air Pollution Control Unit (CAPCS), Co-generation Units (CHP)s and Ammonia Stripping Plant (ASP), and the wastewater treatment plant;
· Process fine-tune, including adjustment of the ASP with new treatment media, modification of Continuous Environmental Monitoring System (CEMS) and Supervisory Control and Data Acquisition System (SCADA) rectification and improvement works following equipment failures and the alteration of different operation modes and measures to adapt to the high variation of SSOW nature and sources; and
· Visitor Centre BS works (exhibition fixture installation)
Environmental Monitoring and Audit Progress
Air Quality Monitoring
Exceedances on NOx and SO2 from CHP and NOx and SO2 from ASP were recorded on the on-line monitoring system in December 2019. Exceedances on NOx and VOCs (including methane) from CHP and Dust, NOx, VOCs (including methane) and NH3 from ASP were recorded on the on-line monitoring system in January 2020. Exceedances on NOx, SO2 and VOCs (including methane) from CHP and Carbon Monoxide, NOx, SO2, VOCs (including methane), NH3 and HF from ASP were recorded on the on-line monitoring system in February 2020. It should be noted that measurements recorded under abnormal operating conditions, e.g. start up and stopping of stacks, unstable operation, test runs and interference of sensor, are disregarded.
Exceedances in emission parameters of CHP and ASP were found to be a result of problems with the continuous fine-tuning of CHP setting, incomplete desulphurisation of biogas which fed to the CHPs, and the incomplete thermal combustion of the thermal combustion unit of the ASP.
The Contractor has implemented mitigation measures to control the exceedance (including the re-adjustment of CHP; continuous monitoring and routine maintenance of the desulphurisation column is carried out; and tuning the thermal combustion unit of the ASP to optimise combustion efficiency and overall performance).
The Contractor is recommended to closely monitor the processes of the modification of the ASP and the post-modification monitoring of emission level to avoid any exceedance.
No non-compliance to the effluent discharge limit stipulated in the discharge licence issued by the EPD under the Water Pollution Control Ordinance was recorded during this reporting period.
Waste generated from the construction of the Project includes inert construction and demolition (C&D) materials (public fill) and non-inert C&D materials (construction wastes).
Inert C&D materials (public fill) include bricks, concrete, building debris, rubble and excavated spoil. In total, 0.00 tonnes of inert C&D material were generated from the construction of the Project.
Non-inert C&D materials (construction wastes) from the construction of this Project include metals, paper/ cardboard packaging waste, plastics and other wastes such as general refuse. 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. 5.28 tonnes of general refuse was disposed of at the landfill.
0.00 L of chemical waste was collected by licenced waste collector from the construction of the Project.
Waste generated from the operation of the Project includes chemical waste, waste generated from pre-treatment process and general refuse.
5,534 L of chemical waste was collected by licenced waste collector from the operation of the Project.
1,249.3 tonnes of waste generated from pre-treatment process from the operation of the Project was disposed of at landfill. Among the recyclable waste generated from pre-treatment process from the operation of the Project, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period.
Around 8.174 tonnes of general refuse from the operation of the Project was disposed of at landfill. Among the recycled general refuse from the operation of the Project, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period.
Findings of Environmental Site Audit
A summary of the monitoring activities undertaken in this reporting period is listed below:
· Joint Environmental Site Inspections |
13 times |
· Landscape & Visual Inspections |
6 times |
Weekly joint environmental site inspections were carried out. The environmental control/ mitigation measures (related to air quality, water quality, waste (including land contamination prevention), hazard-to-life and landscape and visual) recommended in the approved EIA Report and the EM&A Manual were properly implemented by the Contractor during the reporting month.
Environmental Exceedance/Non-conformance/Compliant/Summons and Prosecution
Exceedances for the air emission limits for the CAPCS, CHP and ASP stacks were recorded during the reporting period.
An incident related to the leakage of suspension liquid from the intermediate digestate tank occurred on 28 December 2019.
No complaint/ summon/prosecution was received in this reporting period.
Future Key Issues
Activities to be undertaken in the next reporting month include:
· Operation of the Project.
· Modification of the ASP to control the air emission.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to undertake the construction Environmental Monitoring and Audit (EM&A) programme for the Contract No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I, which the project name has been updated to Organic Resources Recovery Centre (Phase I) (the Project) since November 2017. ERM was also appointed by the Contractor to undertake the operation EM&A programme starting 1 March 2019.
This is the 18th Quarterly EM&A report which summarises the monitoring results and audit findings for the EM&A programme during the reporting period from 1 December 2019 to 29 February 2020.
The structure of the report is as follows:
Section 1: Introduction
It details the scope and structure of the report.
Section 2: Project Information
It summarises the background and scope of the Project, site description, project organisation and status of the Environmental Permits (EP)/licences.
Section 3: Environmental Monitoring and Audit Requirements
It summarises the environmental monitoring requirements including monitoring parameters, programmes, methodologies, frequency, locations, Action and Limit Levels, Event/Action Plans, as well as environmental audit requirements as recommended in the EM&A Manual and approved EIA report.
Section 4: Monitoring Results
It summarises monitoring results of the reporting period.
Section 5: Site Audit
It summarises the audit findings of the environmental as well as landscape and visual site audits undertaken within the reporting period.
Section 6: Environmental Non-conformance
It summarises any exceedance of environmental performance standard, environmental complaints and summons received within the reporting period.
Section 7: Further Key Issues
It summarises the impact forecast for the next reporting month.
Section 8: Conclusions
The Organic Resources Recovery Centre (ORRC) Phase I development (hereinafter referred to as “the Project”) is to design, construct and operate a biological treatment facility with a capacity of about 200 tonnes per day and convert source-separated organic waste from commercial and industrial sectors (mostly food waste) into compost and biogas through proven biological treatment technologies. The location of the Project site is shown in Annex A.
The environmental acceptability of the construction and operation of the Project had been confirmed by findings of the associated Environmental Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection (DEP) approved this EIA Report under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on Environmental Implications and Report on Re-assessment on Hazard to Life Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010) was issued by the DEP to the EPD (Project Team), the Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre (Phase 1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint Venture (OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was issued by the DEP to the OSCAR on 16 February 2015. Variation to both EPs (Nos. EP-395/2010/B and FEP-01/395/2010/B) were made in December 2015. The latest EPs, Nos. EP-395/2010/C and FEP-01/395/2010/C, were issued by the DEP on 21 December 2015.
Under the requirements of Condition 5 of the EP (No. FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme as set out in the approved EM&A Manual (hereinafter referred to as EM&A Manual) is required to be implemented during the construction and operation of the Project. ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the Environmental Team (ET) for the construction phase EM&A programme and the Monitoring Team (MT) for the operation phase EM&A programme for the implementation of the EM&A programme in accordance with the requirements of the EP and the approved EM&A Manual.
The construction works commenced on 21 May 2015. The operation phase of the EM&A programme commenced on 1 March 2019 ([1]). The construction phase EM&A programme was completed in the end of February 2020.
The Project Site is located at Siu Ho Wan in North Lantau with an area of about 2 hectares. The layout of the Project Site is illustrated in Annex A. The facility received and treated an average of 100 tonnes of source separated organic waste per day during the reporting month.
A summary of the major activities undertaken in the reporting period is shown in Table 2.1. The site layout plan is shown in Annex B. The construction programme is shown in Annex C.
Table 2.1 Summary of Activities Undertaken in the Reporting Period
Activities Undertaken in the Reporting Period |
· Systems being operated – waste reception, pre-treatment, CAPCS extraction, the digesters, the centrifuge, , the composting tunnels the desulphurisation, the emergency flare, the CHPs, the ASP and the biological waste water treatment plant (about 100-130 t/d SSOW input); · Process fine-tune – adjustment of the ASP operational parameters with new treatment media, CEMS/SCADA modification and improvement work following equipment failures and the alteration of different operation modes and measures to adapt to the high variation of SSOW nature and sources; and · Visitor Centre BS works (exhibition fixture installation). |
The project organisation chart and contact details are shown in Annex D.
A summary of the valid permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2.
Table 2.2 Summary of Environmental Licensing, Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C
|
Throughout the Contract
|
Permit granted on 21 December 2015
|
Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00024352-2016 |
3 June 2016 – 30 June 2021 |
Approved on 3 June 2016 |
Construction Noise Permit – P1&P2 |
GW-RW0538-18 (Superseded CNP GW-RW0229-18) |
21 January 2019-20 July 2019 |
Approved on 31 December 2018 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-02 |
Throughout the implementation of the Project |
Approved on 10 November 2017 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
The air quality (including odour) monitoring to be carried out during the commissioning and operation phase of the Project are described below. No monitoring for noise, waste, land contamination, hazard-to-life and landscape and visual are required during construction and operation phases of the Project. Although water quality monitoring is not required for the construction and operation phases under the EM&A programme, there are water quality monitoring requirement under the Water Discharge Licence of the plant under the Water Pollution Control Ordinance (WPCO). As part of this EM&A programme, the monitoring results will be reviewed to check the compliance with the WPCO requirements.
According to the EM&A Manual and EP requirements, stack monitoring are required during the commissioning and operation phase of the Project.
On-line monitoring (using continuous environmental monitoring system (CEMS) shall be carried out for the centralised air pollution unit (CAPCS), cogeneration units (CHP) and the ammonia stripping plant (ASP) during the commissioning and operation phase. The calibration certificate for the on-line monitoring equipment is provided in Annex E.
The monitoring data is transmitted instantaneously to EPD (Regional Office) by telemetry system.
When the on-line monitoring for certain parameter cannot be undertaken, monitoring will be carried out using the following methodology approved by the EPD.
Table 3.1 Sampling and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be Monitored |
Gaseous and vaporous organic substances (including methane) |
USEPA Method 18 |
· CAPCS · CHP · ASP |
Particulate |
USEPA Method 5 |
· CAPCS · CHP · ASP |
Carbon monoxide (CO) |
USEPA Method 10 |
· CHP · ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
· CHP · ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
· CHP · ASP |
Hydrogen chloride (HCl) |
USEPA Method 26A |
· CHP · ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
· CHP · ASP |
Oxygen (O2); |
USEPA Method 3A |
· CAPCS · CHP · ASP |
Velocity and Volumetric Flow |
USEPA Method 2 |
· CAPCS · CHP · ASP |
Ammonia (NH3) |
USEPA CTM 027 |
· ASP |
Odour (including NH3 and H2S) |
EN 13725 |
· CAPCS |
Water vapour content (continuous measurement of the water vapour content should not be required if the sample exhaust gas is dried before the emissions are analysed) |
USEPA Method 4 |
· CAPCS · CHP · ASP |
Temperature |
USEPA Method 4 |
· CAPCS · CHP · ASP |
With reference to the EM&A Manual, the air emission of the stacks shall meet the following emission limits as presented in Tables 3.2 to 3.5.
Table 3.2 Emission Limit for CAPCS Stack
Parameter |
Emission Level (mg/Nm3) (a) |
VOCs (including methane) |
680 |
Dust (or Total Suspended Particulates (TSP)) |
6 |
Odour (including NH3 & H2S) |
220 (b) |
Notes: (a) Hourly average concentration (b) The odour unit is OU/Nm3 |
Table 3.3 Emission Limit for CHP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs (c) |
150 |
VOCs (including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) Hourly average concentration (c) NMVOCs should be monitored by gas sampling and laboratory analysis at an agreed interval. For the first 12 months (starting from August 2019), monitoring should be carried out at quarterly intervals. The monitoring frequency should then be reduced to half-yearly for next 12 months (starting from August 2020). (d) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. |
Table 3.4 Emission Limit for ASP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. |
Table 3.5 Emission Limit for Standby Flaring Gas Unit ([2])
Parameter |
Maximum Emission level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) Hourly average concentration (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. |
To determine the effectiveness of the proposed odour mitigation measures and to ensure that the operation of the ORRC1 will not cause adverse odour impacts, odour monitoring of the CAPCS stack (see Section 3.1.1) and odour patrol will be carried out.
Odour patrol shall be conducted by independent trained personnel/ competent persons in summer months (i.e. from July to September) for the first two operational years of ORRC1 at monthly intervals along an odour patrol route at the Project Site boundary as shown in Annex A.
The perceived odour intensity is divided into 5 levels. Table 3.6 describes the odour intensity for different levels.
Table 3.6 Odour Intensity Level
Level |
Odour Intensity |
0 |
Not detected. No odour perceived or an odour so weak that it cannot be easily characterised or described |
1 |
Slight identifiable odour, and slight chance to have odour nuisance |
2 |
Moderate identifiable odour, and moderate chance to have odour nuisance |
3 |
Strong identifiable, likely to have odour nuisance |
4 |
Extreme severe odour, and unacceptable odour level |
Table 3.7 shows the action level and limit level to be used for odour patrol. Should any exceedance of the action and limit levels occurs, actions in accordance with the event and action plan in Table 3.8 should be carried out.
Table 3.7 Action and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from odour patrol) |
When one documented compliant is received (a), or Odour Intensity of 2 is measured from odour patrol. |
Two or more documented complaints are received (a) within a week; or Odour intensity of 3 or above is measured from odour patrol. |
Note: (a) Once the complaint is received by the Project Proponent (EPD), the Project Proponent would investigate and verify the complaint whether it is related to the potential odour emission from the ORRC1 and its on-site wastewater treatment unit. |
Table 3.8 Event and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project Proponent (a) |
Action Level |
|
|
Exceedance of action level (Odour Patrol) |
1. Identify source/reason of exceedance; 2. Repeat odour patrol to confirm finding. |
1. Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2 weeks; 2. Rectify any unacceptable practice; 3. Implement more mitigation measures if necessary; 4. Inform Drainage Services Department (DSD) or the operator of the Siu Ho Wan Sewage Treatment Works (SHWSTW) if exceedance is considered to be caused by the operation of the SHWSTW. 5. Inform North Lantau Refuse Transfer Station (NLTS) operator if exceedance is considered to be caused by the operation of NLTS. |
Exceedance of action level (Odour Complaints) |
1. Identify source/reason of exceedance; 2. Carry out odour patrol to determinate odour intensity. |
1. Carry out investigation and verify the complaint whether it is related to potential odour emission from the nearby SHWSTW; 2. Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2 weeks; 3. Rectify any unacceptable practice; 4. Implement more mitigation measures if necessary; 5. Inform DSD or the operator of the SHWSTW if exceedance is considered to be caused by the operation of the SHWSTW. 6. Inform NLTS operator if exceedance is considered to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit level |
1. Identify source/reason of exceedance; 2. Inform EPD; 3. Repeat odour patrol to confirm findings; 4. Increase odour patrol frequency to bi-weekly; 5. Assess effectiveness of remedial action and keep EPD informed of the results; 6. If exceedance stops, cease additional odour patrol. |
1. Carry out investigation to identify the source/reason of exceedance. Investigation should be completed within 2 week; 2. Rectify any unacceptable practice; 3. Formulate remedial actions; 4. Ensure remedial actions properly implemented; 5. If exceedance continues, consider what more/enhanced mitigation measures should be implemented; 6. Inform DSD or the operator of the SHWSTW if exceedance is considered to be caused by the operation of the SHWSTW. |
Note: (a) Project Proponent shall identify an implementation agent. |
Environmental mitigation measures (related to air quality, water quality, waste, land contamination, hazard-to-life, and landscape and visual) to be implemented during the construction and operation phase of the Project are recommended in the approved EIA Report and EM&A Manual and are summarised in Annex F. Weekly site audits for construction phase and monthly site audits for operation phase will be carried out to check the implementation of these measures.
Compliance audits are to be undertaken to ensure that a valid discharge licence has been issued by EPD prior to the discharge of effluent from the operation of the Project site. The audit shall be conducted to ensure that the effluent quality is in compliance with the discharge licence requirements. The effluent quality shall meet the discharge limits as described in Table 3.9.
Table 3.9 Discharge Limits for Effluent
Parameters |
Discharge Limit (mg/L) |
Flow Rate (m3/day) |
685 |
pH (pH units) |
6-10 (a) |
Suspended Solids |
800 |
Biochemical Oxygen Demand (5 days, 20°) |
800 |
Chemical Oxygen Demand |
2,000 |
Oil & Grease |
40 |
Total Nitrogen |
200 |
Total Phosphorus |
50 |
Surfactants (total) |
25 |
Note: (a) Range. |
In accordance with EM&A Manual, the landscape and visual mitigation measures shall be implemented. Bi-weekly landscape and visual audit during the construction phase is required to ensure that the design, implementation and maintenance of landscape and visual mitigation measures recommended in the approved EIA Report are fully achieved. The implementation status of the mitigation measures for construction phase is summarised in Annex F.
For operation phase, site inspection shall be conducted once a month for the first year of operation of the Project. All measures as stated in the implementation schedule of the EM&A Manual (see Annex F), including compensatory planting, undertaken by both the Contractor and the specialist Landscape Sub-Contractor during the first year of the operation phase shall be audited by a Registered Landscape Architect (RLA) to ensure compliance with the intended aims of the measures and the effectiveness of the mitigation measures.
Monitoring results of air quality parameters from stack emissions of the centralised air pollution control system, the ammonia stripping plant and the cogeneration units will be provided once available to show compliance with the monitoring requirements stated in the EM&A Manual (Rev. F) to support the termination of the construction phase EM&A programme.
The concentrations of concerned air pollutants emitted from the stacks of the CAPCS, CHP, and ASP during the reporting period are monitored on-line by the continuous environmental monitoring system (CEMS). During the reporting period, there is no need to operate the standby flare and therefore no monitoring of the flare stack was undertaken.
With reference to the emission limits shown in Tables 3.2, 3.3 and 3.4, the hourly average concentrations and the number of exceedances of the concerned air emissions monitored for the CAPCS, CHP and ASP during this reporting period are presented in Tables 4.1 to 4.5.
It should be noted that measurements recorded under abnormal operating conditions, e.g. start up and stopping of stacks, unstable operation, test runs and interference of sensor, are disregarded.
Table 4.1 Hourly Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly Average Conc. (mg/Nm3) |
Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
VOCs (including methane) |
5 – 680 |
680 |
Nil |
Nil |
Dust (or TSP) |
0 |
6 |
Nil |
Nil |
Odour (including NH3 & H2S) (b) |
0 – 48 |
220 |
Nil |
Nil |
Notes: (a) The odour unit is OU/Nm3. |
Table 4.2 Hourly Average of Parameters Recorded for CHP 1
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 15 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 386 |
650 |
Nil |
Nil |
NOx |
0 – 299 |
300 |
Nil |
Nil |
SO2 |
0 – 154 |
50 |
Identified (d) |
Tripping of the desulphurisation system. |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs (including methane) (c) |
0 – 1,286 |
1,500 |
Nil |
Nil |
HCl |
0 – 1 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) No sampling was undertaken at CHP1 as biogas production rate could not sustain the operation of the CHP stack for the scheduled samplings. (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (d) Dates with exceedances on SO2 (number of exceedances on the day) were identified on 8 (13), 9 (23), 10 (20), 11 (3) and 20 (3) December 2019, 12 (9), 14 (1), 16 (1) and 29 (1) January 2020, 11 (1) and 12(3) February 2020. |
Table 4.3 Hourly Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) (b) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 15 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 343 |
650 |
Nil |
Nil |
NOx |
0 – 353 |
300 |
Identified (d) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
SO2 |
0 – 101 |
50 |
Identified (e) |
Tripping of the desulphurisation system. |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs (including methane) (c) |
0 – 1,378 |
1,500 |
Nil |
Nil |
HCl |
0 – 1 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) Sampling was conducted on 19 November 2019. (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (d) Dates with exceedances on NOx (number of exceedances on the day) were identified on 9 (1), 13 (1), 14 (1) and 21 (3) January 2020, 1 (2) and 3 (1) February 2020. (e) Dates with exceedances on SO2 (number of exceedances on the day) were identified on 6 (1), 8 (8), 9 (18), 10 (12) and 11 (2) December 2019, 12 (2) January 2020, 9 (2), 10 (3) and 11 (1) February 2020. |
Table 4.4 Hourly Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 11 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 285 |
650 |
Nil |
Nil |
NOx |
0 – 541 |
300 |
Identified (d) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
SO2 |
0 – 165 |
50 |
Identified (e) |
Tripping of the desulphurisation system. |
NMVOCs (b) |
3.3 |
150 |
Nil |
See Annex G for laboratory results |
VOCs (including methane) (c) |
0 – 1,973 |
1,500 |
Identified (f) |
Supplier had been arranged to check the performance of the CHP and maintenance will be arranged after detailed investigation. |
HCl |
0 – 6 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b) Sampling was conducted on 11 February 2020. (c) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (d) Dates with exceedances on NOx (number of exceedances on the day) were identified on 4 (12), 5 (19), 6 (16), 8 (11), 9 (16), 10 (13), 11 (11), 12 (19), 13 (16), 14 (15), 15 (12), 16 (5), 17 (4), 18 (16), 19 (18), 20 (7), 21 (3), 22 (11), 23 (10), 24 (7), 25 (9), 26 (11), 27 (11), 28 (9), 29 (7), 30 (6) and 31 (4) December 2019, 12 (6), 13 (11), 16 (9), 17 (3), 18 (10), 19 (24), 20 (14), 21 (13), 22 (7), 24 (9), 25 (6), 26 (1), 28 (1), 29 (4), 30 (3) and 31 (12) January 2020, 1 (15), 2 (3), 3 (8), 4 (10), 5 (20), 6 (20), 7 (22), 8 (11), 9 (12), 10 (11), 11 (5), 13 (7), 14 (23), 15 (7), 16 (14), 17 (18), 18 (14), 19 (18), 20 (15), 21 (12), 22 (13), 23 (21), 24 (22), 25 (21), 26 (21), 27 (13), 28 (11) and 29 (20) February 2020. (e) Dates with exceedances on SO2 (number of exceedances on the day) were identified on 4 (1), 5 (15), 6 (24), 7 (10), 8 (15), 9 (22), 10 (22), 11(3) and 20 (2) December 2019, 11 (3), 12 (6), 16 (1), 17 (2), 18 (1), 19 (9), 25 (5), 26 (5), 27 (4), 28 (9), 29 (16), 30 (12) and 31 (2) January 2020, 1 (6), 2 (17), 3 (4), 4 (2), 7 (10), 8 (23), 9 (18), 10 (17), 11 (16), 12 (4), 16 (1) and 21 (2) February 2020. (f) Dates with exceedances on VOCs (including methane) (number of exceedances on the day) were identified on 20 (2), 21 (2) and 22 (3) January 2020, 1 (1), 3 (1), 4 (2), 5 (1), 6 (2), 14 (1), 17 (2), 19 (6), 20 (3) and 28 (1) February 2020. |
Table 4.5 Hourly Average of Parameters Recorded for ASP
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 8.0 |
5 |
Identified (c) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
Carbon Monoxide |
0 – 158 |
100 |
Identified (d) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
NOx |
0 – 918 |
200 |
Identified (e) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
SO2 |
0 – 104 |
50 |
Identified (f) |
Modification of the desulphurisation unit is being arranged. |
VOCs (including methane) (b) |
0 – 999 |
20 |
Identified (g) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
NH3 |
0 – 207 |
35 |
Identified (h) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
HCl |
0 – 3 |
10 |
Nil |
Nil |
HF |
0 – 2.5 |
1 |
Identified (i) |
Modification of the ASP is being arranged with the supplier. The supplier will be on-site to complete the modification and review the ASP operation. |
Notes: (a) All values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) The VOCs emission limit include methane as biogas is adopted as fuel in the combustion process. (c) Dates with exceedances on Dust (or TSP) (number of exceedances on the day) were identified on 7 (1), 25 (1) and 26 (1) January 2020. (d) Dates with exceedances on Carbon Monoxide (number of exceedances on the day) were identified on 4 (1) and 5 (1) February 2020. (e) Dates with exceedances on NOx (number of exceedances on the day) were identified 11 (3), 13 (2), 14 (3), 15 (5), 16 (4), 19 (3), 20 (5), 25 (6), 26 (5), 27 (3), 28 (5), 29 (3), 30 (4) and 31 (3) December 2019, 1 (10), 2 (8), 3 (4), 5 (9), 6 (3), 7 (6), 8 (6), 10 (3), 13 (2), 14 (1), 15 (12), 16 (5), 17 (4), 19 (6), 22 (12), 23 (8), 25 (4), 26 (6), 27 (5) and 30 (1) January 2020, 3 (1), 6 (1), 9 (1), 10 (1), 11 (1), 12 (2), 14 (1), 15 (1), 17 (3), 18 (3), 21 (2), 23 (2), 24 (3) and 26 (6) February 2020. (f) Dates with exceedances on SO2 (number of exceedances on the day) were identified on 10 (2) December 2019, 7 (9), 8 (18) and 9 (6) February 2020. (g) Dates with exceedances on VOCs (including methane) (number of exceedances on the day) were identified on 21 (2) January 2020, 4 (6), 5 (3), 6 (1), 7 (1), 9 (1) and 10 (1) February 2020. (h) Dates with exceedances on NH3 (number of exceedances on the day) were identified on 20 (1), 21 (3), 27 (1), 28 (3), 30 (3) and 31 (7) January 2020, 1 (12), 2 (13), 3 (9), 4 (19), 5 (14), 6 (7), 7 (21), 8 (5), 10 (7), 11 (12), 12 (3), 15 (8), 16 (9), 19 (1), 20 (6), 21 (16), 22 (3), 23 (3), 28 (1) and 29 (24) February 2020. (i) 1 exceedance was identified on HF on 6 February 2020. |
No odour patrol was required to be conducted for this reporting period.
No odour patrol was required to be conducted for this reporting period.
No effluent was discharged from the construction activity in the reporting month, hence it was not necessary to carry out effluent discharge sampling for this reporting period.
Effluent discharge was sampled monthly from the Effluent Storage Tank as stipulated in the operation phase discharge licence. The results of the discharge sample is recorded in Table 4.6 to 4.8.
Table 4.6 Results of the Discharge Sample Collected on 9 December 2019
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
pH (pH units) |
7.87 – 9.55 |
6-10 (a) |
Yes |
Suspended Solids |
107 |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) |
29 |
800 |
Yes |
Chemical Oxygen Demand |
477 |
2,000 |
Yes |
Oil & Grease |
<5 |
40 |
Yes |
Total Nitrogen |
65.1 |
200 |
Yes |
Total Phosphorus |
32.0 |
50 |
Yes |
Surfactants (total) |
<1.0 |
25 |
Yes |
Notes: (a) Daily Average. |
Table 4.7 Results of the Discharge Sample Collected on 9 January 2020
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
pH (pH units) |
7.7 – 8.72 |
6-10 (a) |
Yes |
Suspended Solids |
58 |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) |
16 |
800 |
Yes |
Chemical Oxygen Demand |
408 |
2,000 |
Yes |
Oil & Grease |
<5 |
40 |
Yes |
Total Nitrogen |
87.6 |
200 |
Yes |
Total Phosphorus |
30.3 |
50 |
Yes |
Surfactants (total) |
<1.0 |
25 |
Yes |
Notes: (a) Daily Average. |
Table 4.8 Results of the Discharge Sample on 5 February 2020
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
pH (pH units) |
7.30 – 8.77 |
6-10 (a) |
Yes |
Suspended Solids |
56 |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) |
15 |
800 |
Yes |
Chemical Oxygen Demand |
488 |
2,000 |
Yes |
Oil & Grease |
<5 |
40 |
Yes |
Total Nitrogen |
73.2 |
200 |
Yes |
Total Phosphorus |
27.9 |
50 |
Yes |
Surfactants (total) |
<1.0 |
25 |
Yes |
Notes: (a) Daily Average. |
No exceedance of discharge limit was recorded during the reporting period.
Wastes generated from this Project include inert construction and demolition (C&D) materials (public fill) and non-inert C&D materials (construction waste). Construction waste comprises general refuse, metals and paper/cardboard packaging materials. Metals generated from the construction of the Project are also grouped into construction waste as the materials were not disposed of with others at public fill. Reference has been made to the Monthly Summary Waste Flow Table prepared by the Contractor (see Annex H). With reference to the relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 4.9.
Table 4.9 Quantities of Waste Generated from the Construction of the Project
Month / Year |
Quantity |
|||
|
Total Inert C&D Materials Generated (a) |
Non-inert C&D Materials (b) |
||
C&D Materials Recycled (c) |
C&D Waste Disposed of at Landfill (d) |
Chemical Waste |
||
December 2019 |
0.00 tonnes |
0.00 kg |
2.83 tonnes |
0.00 L |
January 2020 |
0.00 tonnes |
0.00 kg |
0.00 tonnes |
0.00 L |
February 2020 |
0.00 tonnes |
0.00 kg |
2.45 tonnes |
0.00 L |
Notes: (a) Inert C&D materials (public fill) include bricks, concrete, building debris, rubble and excavated spoil. In total, 5.28 tonnes of inert C&D material were generated from the Project. The detailed waste flow is presented in Annex H. (b) Non-inert C&D materials (construction wastes) include metals, paper / cardboard packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were grouped into construction wastes as the materials were not disposed of with others at the public fill. (c) 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. (d) Construction wastes other than metals, paper/cardboard packaging, plastics and chemicals were disposed of at NENT Landfill by subcontractors. |
Wastes generated from the operation of the Project include chemical waste, wastes generated from pre-treatment process and general refuse ([3]). Reference has been made to the Monthly Summary Waste Flow Table prepared by the Contractor (see Annex H). With reference to the relevant handling records and trip tickets of this Project, the quantities of different types of waste generated from the operation of the Project in the reporting month are summarised in Table 4.10.
Table 4.10 Quantities of Waste Generated from the Operation of the Project
Month / Year |
Chemical Waste |
Waste Generated from |
General Refuse |
||
|
Disposal of at CWTC |
Disposed of at Landfill (a) |
Recycled (b) |
Disposed of at Landfill (a) (d) |
Recycled (c) |
December 2019 |
1,009 L |
488.13 tonnes |
0.00 tonnes |
2.76 tonnes (d) |
0 kg |
January 2020 |
0 L |
388.20 tonnes |
0.00 tonnes |
2.65 tonnes (d) |
0 kg |
February 2020 |
4525 L |
372.97 tonnes |
0.00 tonnes |
2.76 tonnes (d) |
0 kg |
Notes: (a) Waste generated from pre-treatment process and general refuse other than chemical waste and recyclables were disposed of at NENT landfill by sub-contractors. (b) Among waste generated from pre-treatment process, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. (c) Among general refuse, 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0 kg of plastics were sent to recyclers for recycling during the reporting period. (d) It was assumed that four 240-litre bins filled with 80% of general refuse were collected at each collection. The general refuse density was assumed to be around 0.15 kg/L. |
Ten construction phase site inspections were conducted during the reporting period. The inspections checked the implementation of the recommended mitigation measures for air quality, landscape and visual, water quality, waste (land contamination) and hazard-to-life stated in the Implementation Schedule (see Annex F).
Follow-up actions resulting from site inspections were generally taken as reported by the Contractor. The Contractor has implemented environmental mitigation measures recommended in the approved EIA Report and EM&A Manual.
December 2019
Joint site inspections were conducted by representatives of the Contractor and the ET on 6, 11, 17 and 27 December 2019 as required for the construction of the Project. The IEC and ER were present at the joint inspection on 6 December 2019.
January 2020
Joint site inspections were conducted by representatives of the Contractor and the ET on 3, 9, 17, 22 and 31 January 2020 as required for the construction of the Project. The IEC and ER were present at the joint inspection on 17 January 2020.
February 2020
Joint site inspections were conducted by representatives of the Contractor and the ET on 7, 13, 21 and 28 February2020 as required for the construction of the Project. The IEC and ER were present at the joint inspection on 21 February 2020.
The monthly inspections of the landscape and visual mitigation measures for the operation phase of the Project covered the operation phase environmental site inspections. The inspections checked the implementation of the recommended mitigation measures for air quality, landscape and visual, water quality, waste (land contamination) and hazard-to-life stated in the Implementation Schedule (see Annex F).
Follow-up actions resulting from the site inspections were generally taken as reported by the Contractor. The Contractor has implemented environmental mitigation measures recommended in the approved EIA Report and EM&A Manual.
December 2019
The monthly inspection of the landscape and visual mitigation measures for the operation phase of the Project on 6 December 2019 covered the operation phase environmental site audit. Joint site inspections was conducted by representatives of the Contractor, ER, IEC and the MT on 6 December 2019 as required for the operation of the Project.
January 2020
The monthly inspection of the landscape and visual mitigation measures for the operation phase of the Project on 17 January 2020 covered the operation phase environmental site audit. Joint site inspections was conducted by representatives of the Contractor, ER, IEC and the MT on 17 January 2020 as required for the operation of the Project.
February 2020
The monthly inspection of the landscape and visual mitigation measures for the operation phase of the Project on 21 February 2020 covered the operation phase environmental site audit. Joint site inspections was conducted by representatives of the Contractor, ER, IEC and the MT on 21 February 2020 as required for the operation of the Project.
It was confirmed that the necessary landscape and visual mitigation measures during the construction and operation phase as summarised in Annex F were generally implemented by the Contractor. No non-compliance in relation to the landscape and visual mitigation measures was identified during the site audits in this reporting period and therefore no further actions are required. The ET/MT will keep track of the EM&A programme to check compliance with environmental requirements and the proper implementation of all necessary mitigation measures.
December 2019
Inspection of the landscape and visual mitigation measures for the construction phase of the Project was performed on 6 and 16 December 2019. Inspection of the landscape and visual mitigation measures for the operation phase of the Project was performed on 6 December 2019.
January 2020
Inspection of the landscape and visual mitigation measures for the construction phase of the Project was performed on 17 and 31 January 2020. Inspection of the landscape and visual mitigation measures for the operation phase of the Project was performed on 17 January 2020.
February 2020
Inspection of the landscape and visual mitigation measures for the construction phase of the Project was performed on 7 and 21 February 2020. Inspection of the landscape and visual mitigation measures for the operation phase of the Project was performed on 21 February 2020.
December 2019
Non-compliance of emission limits for CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the organic waste treatment processes (i.e. waste reception, waste pre-treatment, anaerobic digesters, and composting processes) and found that they were operated normally during the reporting period. The Contractor has investigated air pollution control systems combustion system for the CHP and the ASP and identified several potential causes for the exceedance. Remedial and follow-up actions had been completed by the Contractor. The Investigation Report is show in Annex J.
Suspension liquid overflow from the intermediate digestate tank (IDT) to the surface channel inside AD tanks farm was observed on 28 December 2019. The investigation report and the extract of the incident report provided by the Contractor are presented in Annex J.
January 2020
Non-compliance of emission limits for CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the organic waste treatment processes (i.e. waste reception, waste pre-treatment, anaerobic digesters, and composting processes) and found that they were operated normally during the reporting period. The Contractor has investigated air pollution control systems combustion system for the CHP and the ASP and identified several potential causes for the exceedance. Remedial and follow-up actions had been completed by the Contractor. The Investigation Report is show in Annex J.
February 2020
Non-compliance of emission limits for CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the organic waste treatment processes (i.e. waste reception, waste pre-treatment, anaerobic digesters, and composting processes) and found that they were operated normally during the reporting period. The Contractor has investigated air pollution control systems combustion system for the CHP and the ASP and identified several potential causes for the exceedance. Remedial and follow-up actions had been completed by the Contractor. The Investigation Report is show in Annex J.
Activities to be undertaken for the coming reporting period are:
· Operation of the Project.
· Modification of the ASP to control the air emission.
This EM&A Report presents the EM&A programme undertaken during the reporting period from 1 December 2019 to 29 February 2020 in accordance with EM&A Manual (Version F) and requirements of EP (FEP-01/395/2010/C).
No air quality, noise and water quality monitoring is required under the construction and commissioning EM&A requirements.
For the operation phase, exceedances of the emission limits for stack monitoring (including CAPCS, CHP and ASP stacks) were recorded under normal operating conditions during the reporting period (see Table 8.1).
Table 8.1 Exceedances for Stack Emissions
Stack |
Exceedances During the Reporting Period |
Cogeneration Unit (CHP) |
· Exceeded emission limit of NOx on 4, 5, 6, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30 and 31 December 2019, 9, 12, 13, 14, 16, 17, 18, 19, 20, 21, 22, 24, 25, 26, 28, 29, 30 and 31 January 2020, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28 and 29 February 2020 · Exceeded emission limit of SO2 on 4, 5, 6, 7, 8, 9, 10, 11 and 20 December 2019, 11, 12, 14, 16, 17, 18, 19, 25, 26, 27, 28, 29, 30 and 31 January 2020, 1, 2, 3, 4, 7, 8, 9, 10, 11, 12, 16 and 21 February 2020 · Exceeded emission limit of VOCs (including methane) on 20, 21 and 22 January 2020, 1, 3, 4, 5, 6 ,14, 17, 19, 20 and 28 February 2020 |
Ammonia Stripping Plant (ASP) |
· Exceeded emission limit on Dust (or TSP) on 7, 25 and 26 January 2020 · Exceeded emission limit on Carbon Monoxide on 4 and 5 February 2020 · Exceeded emission limit of NOx on 11, 13, 14, 15, 16, 19, 20, 25, 26, 27, 28, 29, 30 and 31 December 2019, 1, 2, 3, 5, 6, 7, 8, 10, 13, 14, 15, 16, 17, 19, 22, 23, 25, 26, 27 and 30 January 2020, 3, 6, 9, 10, 11, 12, 14, 15, 17, 18, 21, 23, 24 and 26 February 2020 · Exceeded emission limit of SO2 on 10 December 2019, 7, 8 and 9 February 2020 · Exceeded emission limit of VOCs (including methane) on 21 January 2020, 4, 5, 6, 7, 9 and 10 February 2020 · Exceeded emission limit of NH3 on 20, 21, 27, 28, 30 and 31 January 2020, 1, 2, 3, 4, 5, 6, 7, 8, 10, 11, 12, 15, 16, 19, 20, 21, 22, 23, 28 and 29 February 2020 · Exceeded emission limit on HF on 6 February 2020 |
Exceedances in emission parameters of CHP and ASP were found to be a result of the continuous fine-tuning of CHP and ASP setting.
The Contractor has implemented mitigation measures to control the exceedance, which is the modification of the CHP and ASP to optimise overall performance.
No non-compliance to the effluent discharge limit was recorded during this reporting period.
The environmental control /mitigation measures related to air quality, water quality, waste (including land contamination prevention), hazard-to-life and landscape and visual recommended in the approved EIA Report and the EM&A Manual were properly implemented by the Contractor during the reporting period.
Bi-weekly landscape and visual monitoring were conducted in the reporting period. The necessary landscape and visual mitigation measures recommended in the approved EIA Report were generally implemented by the Contractor.
No
complaint/summon/prosecution was received.
([1]) As some of the minor items are yet to be closed out in March 2019, the construction phase EM&A programme and Operation Phase EM&A programme were undertaking in parallel in March 2019.